πŸ‡ΊπŸ‡Έ U.S. EIA data (>10MW)

Latest U.S. EIA report from 2024-07
operation πŸ—οΈ πŸ’»
Projects count 200 128 159
Total πŸ”‹ battery power in GW 16.1 14.5 22.5
πŸ—οΈ = construction; πŸ’» = planning

Monthly big battery changes from U.S. EIA reports


2024-07

New projects (32):
400 MW - construction - california - Kola Energy Center - 67680
304 MW - construction - texas - SMT Ironman Battery Storage Plant - 67737
206 MW - construction - texas - Citadel Battery Storage Plant - 67738
200 MW - planning - nevada - Silver State South Storage - 67734
200 MW - construction - oregon - Seaside BESS - 67711
200 MW - planning - texas - Destiny Storage - 67654
200 MW - planning - texas - Wallie Storage - 67668
200 MW - planning - texas - Fort Watt Storage - 67656
200 MW - planning - texas - Jerboa Storage - 67658
200 MW - planning - texas - Bhalu - 67652
200 MW - planning - texas - Malala - 67660
160 MW - construction - texas - Lumina Solar Project - 65645
160 MW - construction - texas - Lumina II Solar Project - 65644
160 MW - construction - texas - IP Radian, LLC - 64859
150 MW - planning - utah - Gale 1 Solar - 61170
120 MW - construction - texas - Wigeon Whistle Battery Storage Plant - 67739
100 MW - construction - texas - Al Pastor Battery Storage Plant - 67721
100 MW - planning - wisconsin - Paris Solar - 65967
100 MW - planning - texas - Berkman Storage - 67651
100 MW - planning - texas - Third Coast BESS, LLC - 67667
100 MW - planning - california - Aramis I Solar Project - 66678
75 MW - construction - oregon - Constable BESS - 67712
75 MW - planning - california - Zeta Solar & Storage - 67676
180 MW - construction - nevada - Silver Peak - 67736
180 MW - construction - nevada - Silver Peak - 67736
180 MW - construction - nevada - Silver Peak - 67736
50 MW - operation - mississippi - OE_MS6 - 65291
50 MW - planning - texas - Lupinus Storage 3 - 67674
30 MW - construction - california - Holtville - 67695
25 MW - planning - washington - Arlington Battery Energy Storage System - 67669
20 MW - planning - pennsylvania - Northumberland Solar I - 67675
17 MW - construction - oregon - Coffee Creek BESS - 67698

Disappeared projects (1):
20 MW - cancelled - florida - South Tampa Energy Storage - 66869

Updated projects (60):

300 MW - construction - arizona - Papago Energy Storage - 66779
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
250 MW - operation - arizona - Sierra Estrella Energy Storage - 66334
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
  date: 2024-06 -> 2024-05 accelerated by 1 month
200 MW - operation - california - Condor Energy Storage LLC - 66285
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
150 MW - operation - california - Vikings Energy Farm - 65711
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
150 MW - construction - california - Scarlet II Hybrid - 66951
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
100 MW - operation - nevada - Dry Lake Solar Energy Center - 63933
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
80 MW - operation - california - Raceway Solar & Storage - 66773
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
60 MW - operation - hawaii - AES Maui Kuihelani Solar Hybrid - 64256
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
85 MW - operation - nevada - Yellow Pine II - 67091
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
50 MW - construction - tennessee - Ridgely Energy Farm - 65445
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
45 MW - operation - indiana - Cavalry Solar Hybrid - 67489
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
85 MW - operation - nevada - Yellow Pine II - 67091
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
11 MW - operation - colorado - Keenesburg Battery Storage - 67306
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
11 MW - operation - colorado - Rattlesnake Ridge Battery Storage - 67300
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation

350 MW - planning - texas - Rowdy Creek Solar and BESS - 65854
  date: 2025-05 -> 2027-05 delayed by 24 months
306 MW - planning - texas - Ash Creek BESS - 66391
  date: 2025-05 -> 2028-03 delayed by 34 months
259 MW - construction - texas - Five Wells Solar Center - Hybrid - 66420
  date: 2024-05 -> 2024-07 delayed by 2 months
180 MW - planning - texas - Indigo Solar & Storage - 66891
  date: 2025-05 -> 2026-05 delayed by 12 months
  mw: 50 -> 180
150 MW - construction - arizona - McFarland B Solar and Storage - 66637
  date: 2024-08 -> 2024-09 delayed by 1 month
130 MW - planning - new mexico - Carne Energy Storage, LLC - 67230
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction
  date: 2025-05 -> 2025-08 delayed by 3 months
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2024-06 -> 2024-08 delayed by 2 months
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2024-07 -> 2024-10 delayed by 3 months
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2024-07 -> 2024-10 delayed by 3 months
100 MW - construction - california - Cald BESS - 66617
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2024-05 -> 2024-06 delayed by 1 month
100 MW - construction - texas - Callisto I Energy Center - 66338
  date: 2024-06 -> 2024-07 delayed by 1 month
100 MW - construction - texas - Copperhead Solar, LLC - 67019
  date: 2024-05 -> 2024-07 delayed by 2 months
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2024-07 -> 2024-08 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2024-07 -> 2024-08 delayed by 1 month
100 MW - planning - texas - Holly Branch Solar, LLC - 66692
  date: 2026-10 -> 2027-08 delayed by 10 months
100 MW - planning - texas - Alamo 3 BESS 2 - 66293
  date: 2024-12 -> 2027-10 delayed by 34 months
116 MW - construction - idaho - Hemmingway BESS - 66325
  date: 2024-06 -> 2024-07 delayed by 1 month
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  date: 2024-05 -> 2024-07 delayed by 2 months
75 MW - construction - california - Hummingbird Energy Storage LLC - 65395
  date: 2024-06 -> 2024-11 delayed by 5 months
70 MW - planning - texas - Briggs Solar, LLC - 66691
  date: 2025-12 -> 2027-12 delayed by 24 months
65 MW - construction - georgia - Mossy Branch Battery Facility - 65018
  date: 2024-05 -> 2024-07 delayed by 2 months
65 MW - construction - california - San Jacinto Grid, LLC - 65657
  date: 2024-06 -> 2025-02 delayed by 8 months
58 MW - planning - utah - Parowan Solar - 65823
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (P) Planned for installation, but regulatory approvals not initiated
  date: 2025-11 -> 2027-01 delayed by 14 months
45 MW - construction - california - Lockhart ESS, LLC - 66946
  date: 2024-05 -> 2024-07 delayed by 2 months
40 MW - construction - california - Sagebrush Solar 2 ESS 40 - 66949
  date: 2024-09 -> 2024-10 delayed by 1 month
40 MW - planning - indiana - Vermillion Rise Solar - 65935
  date: 2025-03 -> 2027-12 delayed by 33 months
30 MW - construction - california - Santa Paula Energy Storage LLC - 65397
  date: 2024-05 -> 2024-06 delayed by 1 month
30 MW - construction - hawaii - AES Waiawa Phase 2 Solar - 66066
  date: 2025-01 -> 2025-02 delayed by 1 month
25 MW - construction - california - West Ford Flat - 66669
  date: 2024-05 -> 2024-06 delayed by 1 month
25 MW - construction - california - Baldy Mesa 2_Silver Peak Hybrid - 66885
  date: 2024-06 -> 2024-07 delayed by 1 month
20 MW - construction - california - Ortega Grid, LLC - 65656
  date: 2024-05 -> 2025-03 delayed by 10 months
20 MW - construction - connecticut - Pure Hedge LLC - 50736
  date: 2024-12 -> 2025-10 delayed by 10 months
15 MW - construction - california - Paulsell - 67092
  date: 2024-05 -> 2024-06 delayed by 1 month
15 MW - construction - north carolina - McLauchin - 67041
  date: 2024-05 -> 2024-08 delayed by 3 months
13 MW - construction - california - Bear Canyon - 66650
  date: 2024-05 -> 2024-06 delayed by 1 month
10 MW - construction - north carolina - Butler - 67042
  date: 2024-06 -> 2024-08 delayed by 2 months
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2024-09 -> 2024-10 delayed by 1 month
10 MW - construction - california - Hecate Energy Desert Storage 1 LLC - 65635
  date: 2024-05 -> 2025-01 delayed by 8 months
10 MW - construction - california - Carris Storage I - 65733
  date: 2024-05 -> 2025-01 delayed by 8 months

150 MW - construction - texas - Borden County BESS - 66804
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
675 MW - construction - california - Menifee Power Bank - 66494
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
80 MW - construction - california - Placerita ESS - 66462
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
125 MW - construction - california - Tumbleweed Energy Storage - 66666
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
66 MW - construction - south carolina - Lone Star Solar - 62235
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
30 MW - construction - montana - Beaver Creek Wind Facility - 65019
  plant name: Beaver Creek I -> Beaver Creek Wind Facility
20 MW - planning - indiana - Honey Creek Solar - 65821
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (P) Planned for installation, but regulatory approvals not initiated

2024-06

New projects (16):
300 MW - construction - arizona - Papago Energy Storage - 66779
200 MW - planning - texas - Blackcat BESS - 67558
185 MW - planning - texas - Wetzel BESS - 67555
185 MW - planning - texas - Serrano BESS - 67556
150 MW - construction - texas - Desert Willow Energy Storage - 67598
150 MW - planning - idaho - Kuna BESS - 67549
100 MW - planning - texas - Jim Wells BESS - 67553
82 MW - construction - california - AES ES Alamitos 2 LLC - 67579
82 MW - planning - idaho - Happy Valley Battery Storage - 67573
77 MW - planning - texas - Cairos Solar and Storage - 67581
60 MW - planning - california - Azalea (CA) - 66890
50 MW - planning - texas - Elm Flats Solar - 67552
50 MW - planning - new mexico - Wildcat Solar Power Plant LLC - 64849
45 MW - operation - indiana - Cavalry Solar Hybrid - 67489
10 MW - construction - arizona - Apache Solar 1 - 60964
10 MW - planning - texas - Cedar Hill ESS - 67570

Updated projects (54):

230 MW - operation - california - Sunlight Storage II - 66575
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
162 MW - operation - california - Proxima - 66270
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
  date: 2024-05 -> 2024-04 accelerated by 1 month
73 MW - operation - texas - Ranchland Wind Storage - 64545
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
  date: 2024-05 -> 2024-04 accelerated by 1 month
50 MW - operation - new mexico - Sky Ranch Solar - 66814
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
40 MW - operation - texas - Zier Solar - 66137
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation

259 MW - construction - texas - Five Wells Solar Center - Hybrid - 66420
  date: 2024-04 -> 2024-05 delayed by 1 month
675 MW - construction - california - Menifee Power Bank - 66494
  date: 2024-06 -> 2024-07 delayed by 1 month
200 MW - operation - california - Condor Energy Storage LLC - 66285
  date: 2024-04 -> 2024-05 delayed by 1 month
200 MW - construction - texas - Dickens - 65489
  date: 2024-04 -> 2024-06 delayed by 2 months
200 MW - construction - texas - Hydra - 65490
  date: 2024-04 -> 2024-06 delayed by 2 months
200 MW - construction - texas - Paleo - 65491
  date: 2024-04 -> 2024-06 delayed by 2 months
200 MW - planning - california - Peregrine Energy Storage LLC - 66286
  date: 2024-10 -> 2025-01 delayed by 3 months
175 MW - construction - texas - Pavo - 65492
  date: 2024-04 -> 2024-06 delayed by 2 months
150 MW - operation - california - Vikings Energy Farm - 65711
  date: 2024-04 -> 2024-05 delayed by 1 month
150 MW - construction - texas - Danish Fields Storage - 66916
  date: 2024-05 -> 2024-07 delayed by 2 months
150 MW - construction - texas - Myrtle Storage - 66913
  date: 2024-05 -> 2024-07 delayed by 2 months
150 MW - construction - arizona - McFarland B Solar and Storage - 66637
  date: 2024-07 -> 2024-08 delayed by 1 month
150 MW - planning - texas - Alamo 7 BESS 1 - 66297
  date: 2024-12 -> 2025-12 delayed by 12 months
150 MW - planning - texas - Alamo 7 BESS 2 - 66298
  date: 2024-12 -> 2025-12 delayed by 12 months
150 MW - planning - texas - Upton BESS 2 - 66303
  date: 2024-12 -> 2026-12 delayed by 24 months
150 MW - planning - texas - Crane 2 BESS 2 - 66300
  date: 2024-12 -> 2027-12 delayed by 36 months
150 MW - planning - texas - Uvalde 2 BESS 2 - 66305
  date: 2024-12 -> 2027-12 delayed by 36 months
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2024-05 -> 2024-06 delayed by 1 month
100 MW - construction - texas - Copperhead Solar, LLC - 67019
  date: 2024-04 -> 2024-05 delayed by 1 month
100 MW - operation - nevada - Dry Lake Solar Energy Center - 63933
  date: 2024-04 -> 2024-05 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2024-06 -> 2024-07 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2024-06 -> 2024-07 delayed by 1 month
100 MW - construction - texas - TX10 Hummingbird Storage - 65693
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2024-07 -> 2024-08 delayed by 1 month
100 MW - construction - california - Beaumont BESS - 66461
  date: 2024-06 -> 2024-08 delayed by 2 months
100 MW - construction - california - Pome BESS - 67299
  date: 2024-11 -> 2024-09 accelerated by 2 months
92 MW - construction - california - Northern Orchard Solar PV, LLC - 67039
  date: 2024-12 -> 2025-02 delayed by 2 months
116 MW - construction - idaho - Hemmingway BESS - 66325
  date: 2024-05 -> 2024-06 delayed by 1 month
75 MW - planning - texas - Uvalde 2 BESS 1 - 66304
  date: 2024-12 -> 2027-12 delayed by 36 months
67 MW - planning - arizona - Yuma Solar + Storage - 67321
  date: 2024-05 -> 2024-12 delayed by 7 months
50 MW - construction - texas - Tortolas - 65493
  date: 2024-04 -> 2024-06 delayed by 2 months
125 MW - construction - california - Tumbleweed Energy Storage - 66666
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2024-07 -> 2024-06 accelerated by 1 month
40 MW - construction - idaho - Black Mesa BESS - 66326
  date: 2024-05 -> 2024-06 delayed by 1 month
88 MW - construction - california - Chaparral Springs - 64864
  date: 2024-04 -> 2024-06 delayed by 2 months
116 MW - construction - idaho - Hemmingway BESS - 66325
  date: 2024-07 -> 2024-08 delayed by 1 month
30 MW - construction - california - Santa Paula Energy Storage LLC - 65397
  date: 2024-04 -> 2024-05 delayed by 1 month
30 MW - construction - hawaii - AES Waiawa Phase 2 Solar - 66066
  date: 2024-11 -> 2025-01 delayed by 2 months
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  date: 2024-04 -> 2024-06 delayed by 2 months
20 MW - construction - tennessee - Vonore Battery Energy Storage System - 64255
  date: 2024-07 -> 2024-12 delayed by 5 months
15 MW - construction - north carolina - McLauchin - 67041
  date: 2024-08 -> 2024-05 accelerated by 3 months
10 MW - construction - california - Sierra Energy Storage, LLC - 61803
  date: 2024-04 -> 2024-06 delayed by 2 months
10 MW - construction - north carolina - Butler - 67042
  date: 2024-08 -> 2024-06 accelerated by 2 months
10 MW - construction - colorado - High Mesa CO - 67323
  date: 2024-04 -> 2024-07 delayed by 3 months
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2024-07 -> 2024-09 delayed by 2 months

300 MW - construction - arizona - Eleven Mile Solar Center - 66263
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
100 MW - construction - texas - Brazos Bend BESS, LLC - 66690
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
100 MW - construction - texas - TX15 Limousin Oak Storage - 65698
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
100 MW - planning - texas - Bexar ESS - 66400
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (T) Regulatory approvals received. Not under construction
15 MW - construction - florida - Dover Energy Storage - 67120
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2024-05

New projects (10):
400 MW - planning - utah - Green River Energy Center - Hybrid - 67501
213 MW - construction - arizona - Serrano - 67503
200 MW - planning - texas - Bell Creek BESS LLC - 67535
185 MW - construction - arizona - McFarland C - 67498
170 MW - planning - arizona - Scatter Wash 1 - 67454
150 MW - construction - arizona - Harquahala 2 - 67474
85 MW - planning - arizona - Scatter Wash 2 - 67455
75 MW - planning - new mexico - Milagro Solar I - 67528
50 MW - planning - utah - Hornshadow Solar II, LLC - 67511
25 MW - planning - utah - Hornshadow Solar, LLC - 67497

Disappeared projects (4):
443 MW - cancelled - texas - Dogwood Creek Solar and BESS - 65843
75 MW - cancelled - utah - Hornshadow Solar II - 67191
75 MW - cancelled - utah - Hornshadow Solar - 67189
75 MW - cancelled - texas - Trinity River Solar 1 - 66132

Updated projects (66):

380 MW - operation - nevada - Gemini Solar - 63352
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
200 MW - construction - indiana - Pike County Energy Storage - 66881
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
147 MW - operation - california - Golden Field Solar III, LLC - 63859
  status: planning -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (T) Regulatory approvals received. Not under construction -> operation
  date: 2024-04 -> 2024-03 accelerated by 1 month
136 MW - operation - california - Arica Solar - 65744
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
100 MW - operation - texas - St. Gall Energy Storage I - 66336
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
  date: 2024-04 -> 2024-03 accelerated by 1 month
70 MW - operation - texas - Ganado Solar - 67284
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
50 MW - operation - california - Victory Pass - 65743
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
40 MW - construction - florida - Wimauma Storage - 66640
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
16 MW - operation - texas - Cameron Wind 1 LLC - 59118
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
12 MW - operation - hawaii - AES West Oahu Solar Hybrid - 64656
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
10 MW - operation - california - Boulevard Energy Storage - 66279
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - california - Clairemont Energy Storage - 66266
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - california - Elliott Energy Storage - 66278
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
20 MW - operation - california - Melrose BESS - 66281
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
20 MW - operation - california - Melrose BESS - 66281
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - california - Pala Gomez Creek BESS - 66280
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - california - Paradise Energy Storage - 66265
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation

300 MW - construction - texas - GulfStar Power, LLC - 66871
  date: 2024-06 -> 2024-10 delayed by 4 months
259 MW - construction - texas - Five Wells Solar Center - Hybrid - 66420
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2024-03 -> 2024-04 delayed by 1 month
200 MW - construction - texas - Dickens - 65489
  date: 2024-03 -> 2024-04 delayed by 1 month
200 MW - construction - texas - Hydra - 65490
  date: 2024-03 -> 2024-04 delayed by 1 month
200 MW - construction - texas - Paleo - 65491
  date: 2024-03 -> 2024-04 delayed by 1 month
200 MW - planning - california - Aratina Solar Center 2 - 64215
  date: 2025-03 -> 2025-01 accelerated by 2 months
200 MW - planning - texas - Tidwell Prairie Storage 1 - 66337
  date: 2024-12 -> 2025-03 delayed by 3 months
180 MW - planning - texas - Starr Solar Ranch - 65975
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (L) Regulatory approvals pending. Not under construction
  date: 2025-03 -> 2026-09 delayed by 18 months
175 MW - construction - texas - Pavo - 65492
  date: 2024-03 -> 2024-04 delayed by 1 month
126 MW - construction - california - AVEP BESS - 65591
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2024-06 -> 2024-09 delayed by 3 months
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2024-03 -> 2024-05 delayed by 2 months
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2024-06 -> 2024-07 delayed by 1 month
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2024-06 -> 2024-07 delayed by 1 month
100 MW - construction - texas - Copperhead Solar, LLC - 67019
  date: 2024-03 -> 2024-04 delayed by 1 month
100 MW - operation - nevada - Dry Lake Solar Energy Center - 63933
  date: 2024-03 -> 2024-04 delayed by 1 month
100 MW - construction - new mexico - San Juan Solar I - 66574
  date: 2024-05 -> 2024-06 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2024-05 -> 2024-06 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2024-05 -> 2024-06 delayed by 1 month
100 MW - construction - texas - Estonian Solar Project, LLC - 66872
  date: 2024-03 -> 2024-08 delayed by 5 months
100 MW - planning - california - Sacramento Valley Energy Center, LLC - 65808
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (L) Regulatory approvals pending. Not under construction
  date: 2024-12 -> 2026-12 delayed by 24 months
92 MW - construction - california - Northern Orchard Solar PV, LLC - 67039
  date: 2024-03 -> 2024-12 delayed by 9 months
116 MW - construction - idaho - Hemmingway BESS - 66325
  date: 2024-04 -> 2024-05 delayed by 1 month
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  date: 2024-04 -> 2024-05 delayed by 1 month
73 MW - operation - texas - Ranchland Wind Storage - 64545
  date: 2024-03 -> 2024-05 delayed by 2 months
72 MW - construction - texas - Fence Post Solar Hybrid Project, LLC - 66801
  date: 2024-04 -> 2024-06 delayed by 2 months
88 MW - construction - california - Chaparral Springs - 64864
  date: 2024-04 -> 2024-06 delayed by 2 months
50 MW - operation - new mexico - Sky Ranch Solar - 66814
  plant name: Sky Ranch Solar and Storage -> Sky Ranch Solar
  date: 2024-03 -> 2024-04 delayed by 1 month
50 MW - construction - tennessee - Ridgely Energy Farm - 65445
  date: 2024-12 -> 2025-03 delayed by 3 months
45 MW - construction - california - Lockhart ESS, LLC - 66946
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2024-06 -> 2024-05 accelerated by 1 month
40 MW - construction - idaho - Black Mesa BESS - 66326
  date: 2024-04 -> 2024-05 delayed by 1 month
40 MW - planning - california - EDPR CA Solar Park VI LLC (CA) Hybrid - 62892
  date: 2024-12 -> 2026-10 delayed by 22 months
30 MW - construction - california - Santa Paula Energy Storage LLC - 65397
  date: 2024-03 -> 2024-04 delayed by 1 month
30 MW - planning - texas - Second Division Solar - 65981
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (L) Regulatory approvals pending. Not under construction
  date: 2025-03 -> 2026-09 delayed by 18 months
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  date: 2024-03 -> 2024-04 delayed by 1 month
25 MW - construction - california - West Ford Flat - 66669
  date: 2024-03 -> 2024-05 delayed by 2 months
20 MW - construction - tennessee - Vonore Battery Energy Storage System - 64255
  date: 2024-03 -> 2024-07 delayed by 4 months
13 MW - construction - california - Bear Canyon - 66650
  date: 2024-03 -> 2024-05 delayed by 2 months
11 MW - construction - colorado - Bromley Battery Storage - 67305
  date: 2024-05 -> 2024-06 delayed by 1 month
11 MW - construction - colorado - Davis Battery Storage - 67304
  date: 2024-05 -> 2024-07 delayed by 2 months
10 MW - construction - california - Sierra Energy Storage, LLC - 61803
  date: 2024-03 -> 2024-04 delayed by 1 month
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2024-06 -> 2024-07 delayed by 1 month

252 MW - planning - oklahoma - Skeleton Creek Energy Center Hybrid - 62494
  mw: 200 -> 252
103 MW - construction - texas - Bright Arrow Solar, LLC - 66688
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
100 MW - construction - texas - Brazos Bend BESS, LLC - 66690
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
100 MW - construction - idaho - Franklin Solar Hybrid - 67190
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
100 MW - construction - texas - Ables Springs Solar & Storage - 66905
  status_verbose: (V) Under construction, more than 50 percent complete -> (U) Under construction, less than or equal to 50 percent complete
70 MW - planning - california - JVR Energy Park LLC - 64428
  status_verbose: (T) Regulatory approvals received. Not under construction -> (P) Planned for installation, but regulatory approvals not initiated
675 MW - construction - california - Menifee Power Bank - 66494
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
15 MW - construction - california - Paulsell - 67092
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation

2024-04

New projects (16):
300 MW - construction - arizona - Sun Streams 4 - 67291
215 MW - construction - arizona - Sun Streams 3 - 67285
102 MW - planning - texas - SGT Hoskins Solar Project Hybrid - 67341
100 MW - construction - california - Pome BESS - 67299
75 MW - planning - arizona - Pluto Energy Storage - 67328
74 MW - planning - south carolina - Big Fork Solar - 62184
74 MW - planning - south carolina - Colleton Solar - 62188
67 MW - planning - arizona - Yuma Solar + Storage - 67321
50 MW - planning - south carolina - Crossroads Solar - 62190
50 MW - planning - south carolina - Quest Solar - 62299
11 MW - construction - colorado - Bromley Battery Storage - 67305
11 MW - construction - colorado - Davis Battery Storage - 67304
11 MW - operation - colorado - Keenesburg Battery Storage - 67306
11 MW - operation - colorado - Rattlesnake Ridge Battery Storage - 67300
10 MW - construction - colorado - High Mesa CO - 67323
10 MW - construction - colorado - Mamm Creek - 67322

Disappeared projects (2):
100 MW - cancelled - texas - Forest Grove - Dodd - 64131
61 MW - cancelled - texas - Talitha Energy Project, LLC - 65891

Updated projects (47):

175 MW - construction - maine - Cross Town Energy Storage - 66606
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
  date: 2025-03 -> 2025-08 delayed by 5 months
150 MW - construction - massachusetts - Cranberry Point Energy Storage - 62844
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
100 MW - construction - texas - Callisto I Energy Center - 66338
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
90 MW - construction - arizona - Superstition Energy Storage - 66333
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
20 MW - operation - new jersey - Justin Court Energy Storage - 66758
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation

380 MW - operation - nevada - Gemini Solar - 63352
  date: 2024-02 -> 2024-03 delayed by 1 month
300 MW - planning - california - Nighthawk Energy Storage, LLC - 65889
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (L) Regulatory approvals pending. Not under construction
  date: 2025-02 -> 2025-04 delayed by 2 months
259 MW - construction - texas - Five Wells Solar Center - Hybrid - 66420
  date: 2024-02 -> 2024-03 delayed by 1 month
200 MW - construction - texas - Hydra - 65490
  date: 2024-02 -> 2024-03 delayed by 1 month
200 MW - construction - texas - Anemoi Energy Storage - 67236
  date: 2024-05 -> 2024-06 delayed by 1 month
200 MW - planning - california - Peregrine Energy Storage LLC - 66286
  date: 2024-09 -> 2024-10 delayed by 1 month
175 MW - construction - texas - Pavo - 65492
  date: 2024-02 -> 2024-03 delayed by 1 month
162 MW - operation - california - Proxima - 66270
  date: 2024-02 -> 2024-04 delayed by 2 months
150 MW - operation - california - Vikings Energy Farm - 65711
  date: 2024-03 -> 2024-04 delayed by 1 month
150 MW - construction - texas - Danish Fields Storage - 66916
  date: 2024-03 -> 2024-05 delayed by 2 months
150 MW - construction - texas - Myrtle Storage - 66913
  date: 2024-03 -> 2024-05 delayed by 2 months
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2024-02 -> 2024-03 delayed by 1 month
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2024-04 -> 2024-05 delayed by 1 month
103 MW - construction - texas - Bright Arrow Solar, LLC - 66688
  date: 2024-05 -> 2024-10 delayed by 5 months
100 MW - operation - texas - St. Gall Energy Storage I - 66336
  date: 2024-03 -> 2024-04 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2024-04 -> 2024-05 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2024-04 -> 2024-05 delayed by 1 month
100 MW - construction - texas - TX10 Hummingbird Storage - 65693
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2024-08 -> 2024-07 accelerated by 1 month
100 MW - planning - california - Sacramento Valley Energy Center, LLC - 65808
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (P) Planned for installation, but regulatory approvals not initiated
  date: 2026-12 -> 2024-12 accelerated by 24 months
116 MW - construction - idaho - Hemmingway BESS - 66325
  date: 2024-03 -> 2024-04 delayed by 1 month
75 MW - planning - ohio - Springwater Solar, LLC - 65900
  date: 2026-02 -> 2026-12 delayed by 10 months
74 MW - planning - california - Kingsley Solar Farm - 64634
  date: 2025-06 -> 2027-12 delayed by 30 months
  mw: 360 -> 74
61 MW - planning - texas - Oriana Solar LLC - 65849
  date: 2024-12 -> 2025-05 delayed by 5 months
50 MW - planning - texas - TREX US Red Holly - 63202
  date: 2024-07 -> 2025-07 delayed by 12 months
50 MW - planning - texas - Peeler Solar, LLC - 65932
  date: 2025-10 -> 2026-12 delayed by 14 months
  mw: 100 -> 50
40 MW - operation - texas - Zier Solar - 66137
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2024-02 -> 2024-04 delayed by 2 months
40 MW - construction - florida - Lake Mabel Storage - 66641
  date: 2024-12 -> 2025-01 delayed by 1 month
40 MW - planning - illinois - Mulligan Solar, LLC - 65349
  date: 2025-06 -> 2025-07 delayed by 1 month
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  date: 2024-02 -> 2024-03 delayed by 1 month
16 MW - operation - texas - Cameron Wind 1 LLC - 59118
  date: 2024-02 -> 2024-03 delayed by 1 month
  mw: 24 -> 16
15 MW - construction - california - Paulsell - 67092
  date: 2024-02 -> 2024-05 delayed by 3 months
12 MW - operation - hawaii - AES West Oahu Solar Hybrid - 64656
  date: 2024-02 -> 2024-03 delayed by 1 month
20 MW - operation - california - Melrose BESS - 66281
  date: 2024-02 -> 2024-03 delayed by 1 month
20 MW - operation - california - Melrose BESS - 66281
  date: 2024-02 -> 2024-03 delayed by 1 month
10 MW - operation - california - Pala Gomez Creek BESS - 66280
  date: 2024-02 -> 2024-03 delayed by 1 month
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2024-05 -> 2024-06 delayed by 1 month

100 MW - construction - california - Beaumont BESS - 66461
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
100 MW - construction - texas - TX15 Limousin Oak Storage - 65698
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
100 MW - planning - texas - Bexar ESS - 66400
  entity id: 58489 -> 66064
  entity name: OCI Solar Power -> Bexar ESS, LLC
125 MW - construction - california - Tumbleweed Energy Storage - 66666
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
50 MW - construction - tennessee - Ridgely Energy Farm - 65445
  status_verbose: (T) Regulatory approvals received. Not under construction -> (L) Regulatory approvals pending. Not under construction
20 MW - planning - hawaii - Kahana Solar, LLC - 64095
  entity id: 63703 -> 64904
  entity name: Kahana Solar, LLC -> AES Clean Energy

2024-03

New projects (10):
300 MW - construction - arizona - Eleven Mile Solar Center - 66263
200 MW - construction - texas - Anemoi Energy Storage - 67236
200 MW - construction - texas - Ebony Energy Storage - 67237
200 MW - planning - texas - Alina Energy LLC - 67250
200 MW - planning - texas - Rock Rose Energy Storage LLC - 67249
150 MW - construction - california - Trestles Grid LLC - 67229
130 MW - planning - new mexico - Carne Energy Storage, LLC - 67230
100 MW - planning - new mexico - Quail Ranch Solar and BESS - 67204
70 MW - operation - texas - Ganado Solar - 67284
85 MW - operation - nevada - Yellow Pine II - 67091

Disappeared projects (2):
300 MW - cancelled - texas - Rodeo Ranch Energy Storage - 67175
100 MW - planning - wisconsin - Paris Solar - 65967

Updated projects (72):

300 MW - construction - texas - GulfStar Power, LLC - 66871
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
250 MW - construction - texas - Zeya - 65880
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
200 MW - construction - texas - Cachi - 65861
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
200 MW - construction - texas - Castor - 65870
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
200 MW - construction - texas - Desna - 65876
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
160 MW - construction - texas - Avila - 65860
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
150 MW - construction - texas - Carina - 65589
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
125 MW - construction - texas - Octans - 65590
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
100 MW - construction - texas - Ables Springs Solar & Storage - 66905
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
99 MW - construction - california - Noosa Energy Storage LLC - 64531
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
70 MW - construction - texas - Antlia - 65588
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
63 MW - operation - texas - House Mountain - 66006
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
60 MW - operation - california - Goleta Energy Storage, LLC - 66394
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
40 MW - construction - florida - Lake Mabel Storage - 66641
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
10 MW - operation - arizona - Mesquite Solar 4, LLC - 65962
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
  date: 2024-02 -> 2024-01 accelerated by 1 month

300 MW - planning - texas - Elio Energy LLC - 65850
  date: 2025-06 -> 2026-12 delayed by 18 months
259 MW - construction - texas - Five Wells Solar Center - Hybrid - 66420
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2024-01 -> 2024-02 delayed by 1 month
200 MW - planning - texas - Eldora Energy LLC - 65847
  date: 2025-06 -> 2026-06 delayed by 12 months
162 MW - operation - california - Proxima - 66270
  date: 2024-01 -> 2024-02 delayed by 1 month
150 MW - construction - texas - Myrtle Storage - 66913
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2024-02 -> 2024-03 delayed by 1 month
150 MW - construction - arizona - McFarland B Solar and Storage - 66637
  date: 2024-05 -> 2024-07 delayed by 2 months
150 MW - construction - california - Eland Solar & Storage Center, Phase 1 Hybrid - 61168
  date: 2024-11 -> 2024-09 accelerated by 2 months
150 MW - planning - georgia - Aragon Energy Storage - 66431
  date: 2026-10 -> 2027-04 delayed by 6 months
125 MW - planning - california - Aratina Solar Center 1 Hybrid - 61167
  date: 2025-06 -> 2025-11 delayed by 5 months
  mw: 50 -> 125
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2024-01 -> 2024-02 delayed by 1 month
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2024-02 -> 2024-04 delayed by 2 months
100 MW - operation - texas - St. Gall Energy Storage I - 66336
  date: 2024-02 -> 2024-03 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2024-03 -> 2024-04 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2024-03 -> 2024-04 delayed by 1 month
100 MW - construction - texas - TX10 Hummingbird Storage - 65693
  date: 2024-07 -> 2024-08 delayed by 1 month
100 MW - construction - texas - TX15 Limousin Oak Storage - 65698
  date: 2024-06 -> 2024-08 delayed by 2 months
116 MW - construction - idaho - Hemmingway BESS - 66325
  date: 2024-01 -> 2024-03 delayed by 2 months
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  date: 2024-01 -> 2024-04 delayed by 3 months
80 MW - operation - california - Raceway Solar & Storage - 66773
  date: 2024-02 -> 2024-05 delayed by 3 months
80 MW - construction - california - Bottleneck Energy Storage - 66757
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2024-04 -> 2024-07 delayed by 3 months
75 MW - construction - california - Hummingbird Energy Storage LLC - 65395
  date: 2024-12 -> 2024-06 accelerated by 6 months
73 MW - operation - texas - Ranchland Wind Storage - 64545
  date: 2024-01 -> 2024-03 delayed by 2 months
70 MW - planning - california - Inland Empire Energy Storage - 66726
  date: 2024-06 -> 2024-12 delayed by 6 months
65 MW - construction - california - San Jacinto Grid, LLC - 65657
  date: 2024-03 -> 2024-06 delayed by 3 months
88 MW - construction - california - Chaparral Springs - 64864
  date: 2024-02 -> 2024-04 delayed by 2 months
125 MW - construction - california - Tumbleweed Energy Storage - 66666
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2024-06 -> 2024-07 delayed by 1 month
40 MW - construction - idaho - Black Mesa BESS - 66326
  date: 2024-02 -> 2024-04 delayed by 2 months
40 MW - construction - california - Scarlet Solar (CA) - 64908
  date: 2024-06 -> 2024-12 delayed by 6 months
88 MW - construction - california - Chaparral Springs - 64864
  date: 2024-02 -> 2024-04 delayed by 2 months
30 MW - construction - california - Santa Paula Energy Storage LLC - 65397
  date: 2024-02 -> 2024-03 delayed by 1 month
30 MW - planning - virginia - Deer Wood Storage, LLC - 65145
  date: 2025-04 -> 2026-11 delayed by 19 months
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
  date: 2024-01 -> 2024-02 delayed by 1 month
16 MW - operation - texas - Cameron Wind 1 LLC - 59118
  date: 2024-01 -> 2024-02 delayed by 1 month
20 MW - construction - california - Ortega Grid, LLC - 65656
  date: 2024-04 -> 2024-05 delayed by 1 month
20 MW - planning - hawaii - Kahana Solar, LLC - 64095
  date: 2024-12 -> 2027-11 delayed by 35 months
20 MW - planning - new york - South Ripley Solar - 64911
  date: 2026-12 -> 2027-12 delayed by 12 months
17 MW - planning - virginia - Powells Creek Solar - Hybrid - 65305
  date: 2024-06 -> 2024-12 delayed by 6 months
12 MW - operation - hawaii - AES West Oahu Solar Hybrid - 64656
  date: 2024-01 -> 2024-02 delayed by 1 month
12 MW - planning - delaware - ENGIE Solidago Solar Project - Hybrid - 65304
  date: 2024-06 -> 2024-12 delayed by 6 months
12 MW - planning - ohio - Salt City Solar Project - Hybrid - 65302
  date: 2024-06 -> 2024-12 delayed by 6 months
12 MW - planning - virginia - Sunnybrook Solar Project - Hybrid - 65307
  date: 2024-06 -> 2024-12 delayed by 6 months
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2024-04 -> 2024-05 delayed by 1 month

240 MW - construction - california - Rexford Solar Farm - 64633
  entity id: 64247 -> 64904
  entity name: 20SD 8me LLC -> AES Clean Energy
  mw: 300 -> 240
675 MW - construction - california - Menifee Power Bank - 66494
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
200 MW - construction - texas - Hydra - 65490
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
200 MW - construction - texas - Dickens - 65489
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
200 MW - construction - texas - Paleo - 65491
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
200 MW - construction - indiana - Pike County Energy Storage - 66881
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction
180 MW - planning - texas - Starr Solar Ranch - 65975
  mw: 30 -> 180
175 MW - construction - texas - Pavo - 65492
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
150 MW - construction - texas - Danish Fields Storage - 66916
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
100 MW - construction - new mexico - San Juan Solar I - 66574
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
75 MW - cancelled - utah - Hornshadow Solar - 67189
  status_verbose: (T) Regulatory approvals received. Not under construction -> (P) Planned for installation, but regulatory approvals not initiated
50 MW - construction - texas - Tortolas - 65493
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America
50 MW - construction - tennessee - Ridgely Energy Farm - 65445
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction
20 MW - cancelled - florida - South Tampa Energy Storage - 66869
  plant name: MacDill Storage -> South Tampa Energy Storage
10 MW - construction - california - Sierra Energy Storage, LLC - 61803
  entity id: 63883 -> 56201
  entity name: Broad Reach Power -> Engie North America

2024-02

New projects (15):
300 MW - cancelled - texas - Rodeo Ranch Energy Storage - 67175
250 MW - planning - arizona - Beehive Energy Storage - 67184
100 MW - construction - idaho - Franklin Solar Hybrid - 67190
100 MW - planning - wisconsin - Paris Solar - 65967
75 MW - cancelled - utah - Hornshadow Solar II - 67191
75 MW - cancelled - utah - Hornshadow Solar - 67189
60 MW - construction - idaho - Franklin Battery Storage - 67183
116 MW - construction - idaho - Hemmingway BESS - 66325
20 MW - planning - oregon - Powell Solar - 67157
15 MW - operation - arizona - Mohave Energy - Hybrid - 67178
15 MW - construction - california - Paulsell - 67092
15 MW - construction - florida - Dover Energy Storage - 67120
12 MW - planning - hawaii - KRS I Anahola Solar Hybrid - 58639
12 MW - planning - hawaii - KRS II Koloa Solar - 58640
10 MW - construction - california - Santee BESS - 67118

Disappeared projects (6):
180 MW - cancelled - nevada - Chuckwalla Solar, LLC - 64558
140 MW - cancelled - texas - Coati Solar, LLC - 66693
75 MW - cancelled - wisconsin - Darien Solar - 64534
50 MW - cancelled - mississippi - OE_MS5 - 64529
50 MW - operation - mississippi - OE_MS6 - 65291
15 MW - cancelled - florida - Dover Solar - 66129

Updated projects (79):

225 MW - operation - california - Solar Blue - 63848
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
220 MW - operation - nevada - Reid Gardner - 2324
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
185 MW - operation - hawaii - Kapolei Energy Storage - 66067
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
150 MW - operation - texas - Revolution - 66170
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
135 MW - operation - california - Chestnut - 63849
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
131 MW - operation - california - Daggett 2 - 64851
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
100 MW - operation - arizona - McFarland A Solar and Storage - 66636
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
100 MW - construction - texas - Estonian Solar Project, LLC - 66872
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (TS) Construction complete, but not yet in commercial operation
  date: 2024-10 -> 2024-03 accelerated by 7 months
99 MW - construction - california - Lead BESS 1 - 66660
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
99 MW - construction - california - Electrolyte BESS - 66661
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
97 MW - construction - california - Acid BESS - 66659
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
75 MW - operation - nevada - Arrow Canyon Solar Hybrid - 62248
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
32 MW - construction - california - Lead BESS 2 - 66662
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
28 MW - operation - california - Estrella Solar & Storage - 66772
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
20 MW - operation - arizona - SR McNeal - 66925
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - texas - SMT Alamo LLC - 66929
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - texas - SMT Elsa LLC - 66931
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - texas - SMT Harlingen II LLC - 66933
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - texas - SMT Los Fresnos LLC - 66932
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - texas - SMT Mercedes LLC - 66926
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - texas - SMT Mission LLC - 66927
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - texas - SMT Rio Grande I LLC - 66934
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - texas - SMT Rio Grande II LLC - 66935
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - texas - SMT Santa Rosa LLC - 66928
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation

621 MW - planning - texas - Lunis Creek Solar and BESS SLF - 65852
  date: 2024-12 -> 2025-07 delayed by 7 months
370 MW - planning - nevada - Arida Solar (Hybrid) - 63841
  date: 2027-06 -> 2027-12 delayed by 6 months
300 MW - planning - nevada - Southern Bighorn Solar Hybrid - 63113
  date: 2026-05 -> 2027-05 delayed by 12 months
  mw: 135 -> 300
259 MW - construction - texas - Five Wells Solar Center - Hybrid - 66420
  date: 2023-12 -> 2024-01 delayed by 1 month
200 MW - operation - california - Condor Energy Storage LLC - 66285
  date: 2024-03 -> 2024-04 delayed by 1 month
200 MW - planning - california - Peregrine Energy Storage LLC - 66286
  date: 2024-12 -> 2024-09 accelerated by 3 months
200 MW - planning - california - Big Rock Solar Farm - 64636
  date: 2024-12 -> 2025-05 delayed by 5 months
200 MW - planning - california - Sienna Solar Farm - 64632
  date: 2024-12 -> 2028-12 delayed by 48 months
169 MW - planning - new york - NY2 Battery - 63584
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (L) Regulatory approvals pending. Not under construction
  date: 2024-12 -> 2026-12 delayed by 24 months
150 MW - construction - texas - Myrtle Storage - 66913
  date: 2024-01 -> 2024-02 delayed by 1 month
150 MW - construction - texas - Danish Fields Storage - 66916
  date: 2024-02 -> 2024-03 delayed by 1 month
150 MW - operation - california - Vikings Energy Farm - 65711
  date: 2024-02 -> 2024-03 delayed by 1 month
150 MW - planning - texas - Alamo 7 BESS 1 - 66297
  date: 2024-05 -> 2024-12 delayed by 7 months
150 MW - planning - texas - Alamo 7 BESS 2 - 66298
  date: 2024-05 -> 2024-12 delayed by 7 months
150 MW - planning - texas - Crane 2 BESS 2 - 66300
  date: 2024-05 -> 2024-12 delayed by 7 months
150 MW - planning - texas - Upton BESS 2 - 66303
  date: 2024-05 -> 2024-12 delayed by 7 months
150 MW - planning - texas - Uvalde 2 BESS 2 - 66305
  date: 2024-05 -> 2024-12 delayed by 7 months
150 MW - planning - new york - KCE NY 29, LLC - 66862
  date: 2025-12 -> 2026-03 delayed by 3 months
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2023-12 -> 2024-01 delayed by 1 month
105 MW - planning - connecticut - KCE CT 1, LLC - 66879
  date: 2027-05 -> 2028-10 delayed by 17 months
100 MW - operation - texas - St. Gall Energy Storage I - 66336
  date: 2024-01 -> 2024-02 delayed by 1 month
100 MW - operation - nevada - Dry Lake Solar Energy Center - 63933
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-12 -> 2024-03 delayed by 3 months
100 MW - planning - texas - Alamo 3 BESS 2 - 66293
  date: 2024-05 -> 2024-12 delayed by 7 months
100 MW - planning - texas - Alamo 4 BESS - 66294
  date: 2024-05 -> 2024-12 delayed by 7 months
100 MW - planning - texas - Alamo 5 BESS 1 - 66295
  date: 2024-05 -> 2024-12 delayed by 7 months
100 MW - planning - texas - Alamo 5 BESS 2 - 66296
  date: 2024-05 -> 2024-12 delayed by 7 months
100 MW - planning - texas - Seven Flags BESS LLC - 66689
  status_verbose: (T) Regulatory approvals received. Not under construction -> (P) Planned for installation, but regulatory approvals not initiated
  date: 2025-09 -> 2025-12 delayed by 3 months
100 MW - planning - texas - TX 14 Venus Mill Storage - 65788
  date: 2025-12 -> 2026-01 delayed by 1 month
100 MW - planning - california - Sacramento Valley Energy Center, LLC - 65808
  date: 2024-12 -> 2026-12 delayed by 24 months
116 MW - construction - idaho - Hemmingway BESS - 66325
  date: 2023-12 -> 2024-01 delayed by 1 month
75 MW - planning - texas - Uvalde 2 BESS 1 - 66304
  date: 2024-05 -> 2024-12 delayed by 7 months
75 MW - construction - california - Hummingbird Energy Storage LLC - 65395
  date: 2023-12 -> 2024-12 delayed by 12 months
73 MW - operation - texas - Ranchland Wind Storage - 64545
  date: 2023-12 -> 2024-01 delayed by 1 month
72 MW - construction - texas - Fence Post Solar Hybrid Project, LLC - 66801
  date: 2024-03 -> 2024-04 delayed by 1 month
66 MW - construction - south carolina - Lone Star Solar - 62235
  date: 2023-12 -> 2024-12 delayed by 12 months
61 MW - cancelled - texas - Talitha Energy Project, LLC - 65891
  date: 2025-03 -> 2025-04 delayed by 1 month
  mw: 131 -> 61
60 MW - operation - california - Goleta Energy Storage, LLC - 66394
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-12 -> 2024-01 delayed by 1 month
58 MW - planning - utah - Parowan Solar - 65823
  date: 2024-12 -> 2025-11 delayed by 11 months
50 MW - planning - virginia - Dulles Solar and Storage - 65043
  date: 2024-12 -> 2026-12 delayed by 24 months
30 MW - construction - california - Santa Paula Energy Storage LLC - 65397
  date: 2024-01 -> 2024-02 delayed by 1 month
16 MW - operation - texas - Cameron Wind 1 LLC - 59118
  date: 2023-12 -> 2024-01 delayed by 1 month
20 MW - planning - new york - KCE NY 10, LLC - 66682
  date: 2025-12 -> 2026-03 delayed by 3 months
20 MW - planning - new york - South Ripley Solar - 64911
  date: 2024-12 -> 2026-12 delayed by 24 months
20 MW - planning - indiana - Honey Creek Solar - 65821
  date: 2024-12 -> 2026-12 delayed by 24 months
17 MW - planning - virginia - Powells Creek Solar - Hybrid - 65305
  date: 2024-05 -> 2024-06 delayed by 1 month
12 MW - planning - delaware - ENGIE Solidago Solar Project - Hybrid - 65304
  date: 2024-05 -> 2024-06 delayed by 1 month
12 MW - planning - ohio - Salt City Solar Project - Hybrid - 65302
  date: 2024-05 -> 2024-06 delayed by 1 month
12 MW - planning - virginia - Sunnybrook Solar Project - Hybrid - 65307
  date: 2024-05 -> 2024-06 delayed by 1 month
10 MW - operation - arizona - Mesquite Solar 4, LLC - 65962
  date: 2023-12 -> 2024-02 delayed by 2 months

250 MW - operation - arizona - Sierra Estrella Energy Storage - 66334
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
230 MW - operation - california - Sunlight Storage II - 66575
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
147 MW - operation - california - Golden Field Solar III, LLC - 63859
  energy source code: -> MWH
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
25 MW - construction - california - West Ford Flat - 66669
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
13 MW - construction - california - Bear Canyon - 66650
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2024-01

New projects (4):
400 MW - planning - texas - Iron Belt - 67059
174 MW - construction - texas - Longbow BESS, LLC - 67083
147 MW - operation - california - Golden Field Solar III, LLC - 63859
85 MW - operation - nevada - Yellow Pine II - 67091

Disappeared projects (1):
15 MW - cancelled - hawaii - Paeahu Solar Hybrid - 62534

Updated projects (66):

150 MW - construction - texas - Borden County BESS - 66804
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
  date: 2024-05 -> 2024-06 delayed by 1 month
136 MW - operation - california - Edwards Sanborn E1B - 65674
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
100 MW - operation - california - Edwards Sanborn E4 - 65675
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
68 MW - operation - california - Stanton Battery Energy Storage - 66423
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
675 MW - construction - california - Menifee Power Bank - 66494
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
47 MW - operation - california - Sanborn BESS 4 - 65673
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
  date: 2023-12 -> 2023-11 accelerated by 1 month
47 MW - operation - california - Edwards Sanborn E5 - 65676
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
20 MW - operation - virginia - Dry Bridge Storage - 65044
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
  date: 2023-12 -> 2023-11 accelerated by 1 month
10 MW - operation - texas - SMT Bay City LLC - 66930
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation

380 MW - operation - nevada - Gemini Solar - 63352
  date: 2023-11 -> 2024-02 delayed by 3 months
240 MW - construction - california - Rexford Solar Farm - 64633
  date: 2024-04 -> 2024-12 delayed by 8 months
225 MW - operation - california - Solar Blue - 63848
  date: 2023-11 -> 2023-12 delayed by 1 month
200 MW - planning - california - Peregrine Energy Storage LLC - 66286
  date: 2024-08 -> 2024-12 delayed by 4 months
150 MW - operation - texas - Revolution - 66170
  date: 2023-11 -> 2023-12 delayed by 1 month
150 MW - construction - texas - Myrtle Storage - 66913
  date: 2023-12 -> 2024-01 delayed by 1 month
150 MW - construction - california - Scarlet II Hybrid - 66951
  date: 2024-10 -> 2024-12 delayed by 2 months
150 MW - planning - california - Eland Solar & Storage Center, Phase 2 Hybrid - 61169
  date: 2024-11 -> 2025-03 delayed by 4 months
135 MW - operation - california - Chestnut - 63849
  date: 2023-11 -> 2023-12 delayed by 1 month
61 MW - cancelled - texas - Talitha Energy Project, LLC - 65891
  date: 2024-10 -> 2025-03 delayed by 5 months
  mw: 61 -> 131
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2023-12 -> 2024-02 delayed by 2 months
100 MW - operation - arizona - McFarland A Solar and Storage - 66636
  date: 2023-11 -> 2023-12 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2024-01 -> 2024-03 delayed by 2 months
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2024-01 -> 2024-03 delayed by 2 months
100 MW - construction - new mexico - San Juan Solar I - 66574
  date: 2024-07 -> 2024-05 accelerated by 2 months
116 MW - construction - idaho - Hemmingway BESS - 66325
  date: 2023-11 -> 2023-12 delayed by 1 month
75 MW - cancelled - wisconsin - Darien Solar - 64534
  date: 2024-11 -> 2024-12 delayed by 1 month
65 MW - construction - california - San Jacinto Grid, LLC - 65657
  date: 2024-01 -> 2024-03 delayed by 2 months
63 MW - operation - texas - House Mountain - 66006
  date: 2023-12 -> 2024-01 delayed by 1 month
88 MW - construction - california - Chaparral Springs - 64864
  date: 2023-12 -> 2024-02 delayed by 2 months
50 MW - construction - texas - Tortolas - 65493
  date: 2024-03 -> 2024-04 delayed by 1 month
43 MW - planning - california - Dynegy Oakland Power Plant - 6211
  date: 2024-11 -> 2027-05 delayed by 30 months
40 MW - construction - idaho - Black Mesa BESS - 66326
  date: 2023-12 -> 2024-02 delayed by 2 months
88 MW - construction - california - Chaparral Springs - 64864
  date: 2023-12 -> 2024-02 delayed by 2 months
30 MW - construction - california - Santa Paula Energy Storage LLC - 65397
  date: 2023-11 -> 2024-01 delayed by 2 months
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  date: 2023-12 -> 2024-01 delayed by 1 month
20 MW - construction - california - Ortega Grid, LLC - 65656
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2024-01 -> 2024-04 delayed by 3 months
10 MW - operation - texas - SMT Alamo LLC - 66929
  date: 2023-11 -> 2023-12 delayed by 1 month
10 MW - operation - texas - SMT Harlingen II LLC - 66933
  date: 2023-11 -> 2023-12 delayed by 1 month
10 MW - operation - texas - SMT Mercedes LLC - 66926
  date: 2023-11 -> 2023-12 delayed by 1 month
10 MW - operation - texas - SMT Mission LLC - 66927
  date: 2023-11 -> 2023-12 delayed by 1 month
10 MW - operation - texas - SMT Santa Rosa LLC - 66928
  date: 2023-11 -> 2023-12 delayed by 1 month
20 MW - operation - california - Melrose BESS - 66281
  date: 2023-12 -> 2024-02 delayed by 2 months
20 MW - operation - california - Melrose BESS - 66281
  date: 2023-12 -> 2024-02 delayed by 2 months
10 MW - operation - california - Pala Gomez Creek BESS - 66280
  date: 2023-12 -> 2024-02 delayed by 2 months
10 MW - construction - california - Sierra Energy Storage, LLC - 61803
  date: 2023-12 -> 2024-03 delayed by 3 months
10 MW - operation - california - Boulevard Energy Storage - 66279
  date: 2023-12 -> 2024-03 delayed by 3 months
10 MW - operation - california - Clairemont Energy Storage - 66266
  date: 2023-12 -> 2024-03 delayed by 3 months
10 MW - operation - california - Elliott Energy Storage - 66278
  date: 2023-12 -> 2024-03 delayed by 3 months
10 MW - operation - california - Paradise Energy Storage - 66265
  date: 2023-12 -> 2024-03 delayed by 3 months
10 MW - construction - california - Hecate Energy Desert Storage 1 LLC - 65635
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2024-01 -> 2024-05 delayed by 4 months
10 MW - construction - california - Carris Storage I - 65733
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2024-02 -> 2024-05 delayed by 3 months
10 MW - planning - texas - Grizzly Ridge Solar - 66410
  date: 2024-04 -> 2024-08 delayed by 4 months

675 MW - construction - california - Menifee Power Bank - 66494
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
200 MW - construction - texas - Hydra - 65490
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
200 MW - construction - texas - Dickens - 65489
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
175 MW - construction - texas - Pavo - 65492
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
162 MW - operation - california - Proxima - 66270
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
150 MW - construction - texas - Danish Fields Storage - 66916
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
100 MW - construction - california - Cald BESS - 66617
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
72 MW - construction - texas - Fence Post Solar Hybrid Project, LLC - 66801
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
65 MW - construction - georgia - Mossy Branch Battery Facility - 65018
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
50 MW - cancelled - mississippi - OE_MS5 - 64529
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
50 MW - operation - mississippi - OE_MS6 - 65291
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
45 MW - construction - california - Lockhart ESS, LLC - 66946
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
20 MW - operation - arizona - SR McNeal - 66925
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
15 MW - cancelled - florida - Dover Solar - 66129
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (T) Regulatory approvals received. Not under construction

2023-12

New projects (8):
100 MW - construction - texas - Copperhead Solar, LLC - 67019
92 MW - construction - california - Northern Orchard Solar PV, LLC - 67039
675 MW - construction - california - Menifee Power Bank - 66494
30 MW - planning - texas - Second Division Solar - 65981
180 MW - planning - texas - Starr Solar Ranch - 65975
15 MW - construction - north carolina - McLauchin - 67041
10 MW - construction - north carolina - Archie Horne - 67040
10 MW - construction - north carolina - Butler - 67042

Disappeared projects (1):
660 MW - cancelled - texas - Goldenrod Creek Solar and BESS SLF - 65845

Updated projects (38):

169 MW - operation - california - Sanborn BESS 3 - 65672
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
25 MW - construction - california - West Ford Flat - 66669
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
13 MW - construction - california - Bear Canyon - 66650
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete

400 MW - planning - texas - Hollow Branch Creek 2 Solar and BESS SLF - 65851
  date: 2024-10 -> 2025-12 delayed by 14 months
370 MW - planning - nevada - Arida Solar (Hybrid) - 63841
  date: 2024-10 -> 2027-06 delayed by 32 months
  mw: 185 -> 370
302 MW - planning - texas - Middlebrook Creek Solar and BESS - 65853
  date: 2024-10 -> 2026-02 delayed by 16 months
150 MW - operation - texas - Revolution - 66170
  date: 2023-10 -> 2023-11 delayed by 1 month
150 MW - construction - california - Scarlet II Hybrid - 66951
  date: 2024-06 -> 2024-10 delayed by 4 months
136 MW - operation - california - Edwards Sanborn E1B - 65674
  date: 2023-10 -> 2023-11 delayed by 1 month
135 MW - operation - california - Chestnut - 63849
  date: 2023-10 -> 2023-11 delayed by 1 month
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2023-10 -> 2023-12 delayed by 2 months
675 MW - construction - california - Menifee Power Bank - 66494
  date: 2024-08 -> 2024-09 delayed by 1 month
100 MW - operation - california - Edwards Sanborn E4 - 65675
  date: 2023-10 -> 2023-11 delayed by 1 month
100 MW - construction - texas - TX10 Hummingbird Storage - 65693
  date: 2024-04 -> 2024-07 delayed by 3 months
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  date: 2024-02 -> 2024-01 accelerated by 1 month
80 MW - operation - california - Raceway Solar & Storage - 66773
  date: 2023-12 -> 2024-02 delayed by 2 months
75 MW - operation - nevada - Arrow Canyon Solar Hybrid - 62248
  date: 2023-11 -> 2023-12 delayed by 1 month
73 MW - operation - texas - Ranchland Wind Storage - 64545
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-10 -> 2023-12 delayed by 2 months
68 MW - operation - california - Stanton Battery Energy Storage - 66423
  date: 2023-10 -> 2023-11 delayed by 1 month
65 MW - construction - california - San Jacinto Grid, LLC - 65657
  date: 2023-12 -> 2024-01 delayed by 1 month
63 MW - operation - texas - House Mountain - 66006
  date: 2023-11 -> 2023-12 delayed by 1 month
60 MW - operation - california - Goleta Energy Storage, LLC - 66394
  date: 2023-11 -> 2023-12 delayed by 1 month
40 MW - construction - idaho - Black Mesa BESS - 66326
  date: 2023-11 -> 2023-12 delayed by 1 month
30 MW - construction - hawaii - AES Waiawa Phase 2 Solar - 66066
  date: 2024-10 -> 2024-11 delayed by 1 month
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  date: 2023-11 -> 2023-12 delayed by 1 month
16 MW - operation - texas - Cameron Wind 1 LLC - 59118
  date: 2023-11 -> 2023-12 delayed by 1 month
20 MW - operation - virginia - Dry Bridge Storage - 65044
  status_verbose: (V) Under construction, more than 50 percent complete -> (U) Under construction, less than or equal to 50 percent complete
  date: 2023-10 -> 2023-12 delayed by 2 months
20 MW - construction - california - Ortega Grid, LLC - 65656
  date: 2023-11 -> 2024-01 delayed by 2 months
20 MW - construction - tennessee - Vonore Battery Energy Storage System - 64255
  date: 2023-12 -> 2024-03 delayed by 3 months
10 MW - operation - texas - SMT Bay City LLC - 66930
  date: 2023-10 -> 2023-11 delayed by 1 month
10 MW - construction - california - Hecate Energy Desert Storage 1 LLC - 65635
  date: 2023-12 -> 2024-01 delayed by 1 month
10 MW - planning - texas - Grizzly Ridge Solar - 66410
  date: 2024-02 -> 2024-04 delayed by 2 months
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2023-12 -> 2024-04 delayed by 4 months

220 MW - operation - nevada - Reid Gardner - 2324
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
200 MW - operation - california - Condor Energy Storage LLC - 66285
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
100 MW - operation - nevada - Dry Lake Solar Energy Center - 63933
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
76 MW - planning - texas - Gaia Hybrid - 66342
  entity name: Samsung Solar Energy 2, LLC -> Samsung C&T Renewables, LLC
61 MW - planning - texas - Eagle Springs Hybrid - 66341
  entity name: Samsung Solar Energy 2, LLC -> Samsung C&T Renewables, LLC

2023-11

New projects (0):

Updated projects (67):

220 MW - operation - nevada - Reid Gardner - 2324
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
125 MW - operation - california - Oberon II Solar Project - 65735
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
125 MW - operation - california - Oberon Solar Project - 65734
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
117 MW - operation - california - Fifth Standard Solar PV, LLC (Hybrid) - 64197
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
103 MW - construction - texas - Bright Arrow Solar, LLC - 66688
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
100 MW - operation - arizona - Saint Energy Storage II LLC - 66716
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
100 MW - construction - california - Beaumont BESS - 66461
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
  date: 2024-03 -> 2024-06 delayed by 3 months
88 MW - operation - arizona - Storey Solar and Storage - 65956
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
80 MW - construction - california - Placerita ESS - 66462
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
  date: 2024-02 -> 2024-09 delayed by 7 months
125 MW - construction - california - Tumbleweed Energy Storage - 66666
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
125 MW - construction - california - Tumbleweed Energy Storage - 66666
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
20 MW - operation - arizona - SR McNeal - 66925
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
10 MW - operation - texas - SMT Bay City LLC - 66930
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (TS) Construction complete, but not yet in commercial operation
10 MW - operation - texas - SMT Alamo LLC - 66929
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (TS) Construction complete, but not yet in commercial operation
10 MW - operation - texas - SMT Harlingen II LLC - 66933
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (TS) Construction complete, but not yet in commercial operation
10 MW - operation - texas - SMT Mercedes LLC - 66926
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (TS) Construction complete, but not yet in commercial operation
10 MW - operation - texas - SMT Mission LLC - 66927
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (TS) Construction complete, but not yet in commercial operation
10 MW - operation - texas - SMT Santa Rosa LLC - 66928
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (TS) Construction complete, but not yet in commercial operation
10 MW - operation - texas - SMT Elsa LLC - 66931
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (TS) Construction complete, but not yet in commercial operation
10 MW - operation - texas - SMT Los Fresnos LLC - 66932
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (TS) Construction complete, but not yet in commercial operation
10 MW - operation - texas - SMT Rio Grande I LLC - 66934
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (TS) Construction complete, but not yet in commercial operation
10 MW - operation - texas - SMT Rio Grande II LLC - 66935
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (TS) Construction complete, but not yet in commercial operation

225 MW - operation - california - Solar Blue - 63848
  date: 2023-09 -> 2023-11 delayed by 2 months
169 MW - operation - california - Sanborn BESS 3 - 65672
  date: 2023-09 -> 2023-10 delayed by 1 month
150 MW - construction - arizona - McFarland B Solar and Storage - 66637
  date: 2023-12 -> 2024-05 delayed by 5 months
135 MW - operation - california - Chestnut - 63849
  date: 2023-09 -> 2023-10 delayed by 1 month
131 MW - operation - california - Daggett 2 - 64851
  date: 2023-11 -> 2023-12 delayed by 1 month
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2023-09 -> 2023-10 delayed by 1 month
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2023-10 -> 2023-12 delayed by 2 months
100 MW - operation - california - Edwards Sanborn E4 - 65675
  date: 2023-09 -> 2023-10 delayed by 1 month
100 MW - operation - arizona - McFarland A Solar and Storage - 66636
  date: 2023-12 -> 2023-11 accelerated by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2023-11 -> 2024-01 delayed by 2 months
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2023-11 -> 2024-01 delayed by 2 months
100 MW - construction - new mexico - San Juan Solar I - 66574
  date: 2024-08 -> 2024-07 accelerated by 1 month
100 MW - construction - texas - Estonian Solar Project, LLC - 66872
  date: 2024-04 -> 2024-10 delayed by 6 months
116 MW - construction - idaho - Hemmingway BESS - 66325
  date: 2023-10 -> 2023-11 delayed by 1 month
75 MW - operation - nevada - Arrow Canyon Solar Hybrid - 62248
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-10 -> 2023-11 delayed by 1 month
75 MW - planning - texas - Noria Hondo Solar (Hybrid) - 65344
  date: 2024-09 -> 2025-09 delayed by 12 months
75 MW - construction - california - Baldy Mesa Solar & Storage - 66598
  date: 2023-12 -> 2025-10 delayed by 22 months
73 MW - operation - texas - Ranchland Wind Storage - 64545
  date: 2023-09 -> 2023-10 delayed by 1 month
68 MW - operation - california - Stanton Battery Energy Storage - 66423
  date: 2023-09 -> 2023-10 delayed by 1 month
65 MW - construction - california - San Jacinto Grid, LLC - 65657
  date: 2023-11 -> 2023-12 delayed by 1 month
63 MW - operation - texas - House Mountain - 66006
  date: 2023-10 -> 2023-11 delayed by 1 month
675 MW - construction - california - Menifee Power Bank - 66494
  date: 2024-09 -> 2024-08 accelerated by 1 month
47 MW - operation - california - Edwards Sanborn E5 - 65676
  date: 2023-09 -> 2023-11 delayed by 2 months
40 MW - construction - idaho - Black Mesa BESS - 66326
  date: 2023-10 -> 2023-11 delayed by 1 month
30 MW - construction - california - Santa Paula Energy Storage LLC - 65397
  date: 2023-09 -> 2023-11 delayed by 2 months
30 MW - construction - hawaii - AES Waiawa Phase 2 Solar - 66066
  date: 2023-12 -> 2024-10 delayed by 10 months
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  date: 2023-09 -> 2023-11 delayed by 2 months
25 MW - construction - california - Baldy Mesa 2_Silver Peak Hybrid - 66885
  date: 2023-12 -> 2024-06 delayed by 6 months
16 MW - operation - texas - Cameron Wind 1 LLC - 59118
  date: 2023-10 -> 2023-11 delayed by 1 month
20 MW - operation - virginia - Dry Bridge Storage - 65044
  date: 2023-09 -> 2023-10 delayed by 1 month
20 MW - operation - new jersey - Justin Court Energy Storage - 66758
  date: 2023-11 -> 2024-02 delayed by 3 months
12 MW - operation - hawaii - AES West Oahu Solar Hybrid - 64656
  date: 2023-09 -> 2024-01 delayed by 4 months
10 MW - construction - california - Hecate Energy Desert Storage 1 LLC - 65635
  date: 2023-11 -> 2023-12 delayed by 1 month
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2023-11 -> 2023-12 delayed by 1 month
10 MW - operation - california - Boulevard Energy Storage - 66279
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-09 -> 2023-12 delayed by 3 months
10 MW - operation - california - Clairemont Energy Storage - 66266
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-09 -> 2023-12 delayed by 3 months
10 MW - operation - california - Elliott Energy Storage - 66278
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-09 -> 2023-12 delayed by 3 months
20 MW - operation - california - Melrose BESS - 66281
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-09 -> 2023-12 delayed by 3 months
20 MW - operation - california - Melrose BESS - 66281
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-09 -> 2023-12 delayed by 3 months
10 MW - operation - california - Pala Gomez Creek BESS - 66280
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-09 -> 2023-12 delayed by 3 months
10 MW - operation - california - Paradise Energy Storage - 66265
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-09 -> 2023-12 delayed by 3 months
10 MW - construction - california - Carris Storage I - 65733
  date: 2023-11 -> 2024-02 delayed by 3 months
10 MW - planning - maine - South Portland ESS, LLC - 64616
  date: 2024-02 -> 2024-12 delayed by 10 months

150 MW - construction - texas - Myrtle Storage - 66913
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2023-10

New projects (5):
150 MW - construction - california - Scarlet II Hybrid - 66951
675 MW - construction - california - Menifee Power Bank - 66494
59 MW - construction - california - Sagebrush Solar 2 ESS 59 - 66950
45 MW - construction - california - Lockhart ESS, LLC - 66946
40 MW - construction - california - Sagebrush Solar 2 ESS 40 - 66949

Updated projects (60):

675 MW - construction - california - Menifee Power Bank - 66494
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
675 MW - construction - california - Menifee Power Bank - 66494
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
200 MW - operation - california - Condor Energy Storage LLC - 66285
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
  date: 2024-08 -> 2024-03 accelerated by 5 months
190 MW - operation - texas - Cunningham Storage - 65410
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
150 MW - operation - california - Vikings Energy Farm - 65711
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
  date: 2024-08 -> 2024-02 accelerated by 6 months
132 MW - operation - california - North Central Valley - 66208
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
100 MW - operation - texas - St. Gall Energy Storage I - 66336
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
100 MW - construction - texas - Brazos Bend BESS, LLC - 66690
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
100 MW - construction - new mexico - San Juan Solar I - 66574
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
80 MW - operation - california - Raceway Solar & Storage - 66773
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
75 MW - operation - california - Resurgence Solar - 64489
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
40 MW - operation - california - Resurgence Solar II - 66620
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
28 MW - operation - california - Estrella Solar & Storage - 66772
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
20 MW - operation - california - VESI Pomona - 50300
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
  date: 2023-10 -> 2023-08 accelerated by 2 months
10 MW - operation - california - BCE Los Alamitos 1 - 66533
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - california - BCE Los Alamitos 2 - 66532
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation

200 MW - construction - texas - Hydra - 65490
  date: 2023-12 -> 2024-02 delayed by 2 months
200 MW - construction - texas - Dickens - 65489
  date: 2024-02 -> 2024-03 delayed by 1 month
200 MW - construction - texas - Paleo - 65491
  date: 2024-02 -> 2024-03 delayed by 1 month
185 MW - operation - hawaii - Kapolei Energy Storage - 66067
  date: 2023-08 -> 2023-12 delayed by 4 months
175 MW - construction - texas - Pavo - 65492
  date: 2023-12 -> 2024-02 delayed by 2 months
150 MW - construction - texas - Carina - 65589
  date: 2024-06 -> 2024-12 delayed by 6 months
136 MW - operation - california - Arica Solar - 65744
  date: 2023-12 -> 2024-03 delayed by 3 months
131 MW - operation - california - Daggett 2 - 64851
  date: 2023-10 -> 2023-11 delayed by 1 month
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2023-08 -> 2023-09 delayed by 1 month
117 MW - operation - california - Fifth Standard Solar PV, LLC (Hybrid) - 64197
  date: 2023-08 -> 2023-09 delayed by 1 month
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2023-09 -> 2023-10 delayed by 1 month
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2023-11 -> 2024-06 delayed by 7 months
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2023-11 -> 2024-06 delayed by 7 months
100 MW - operation - arizona - Saint Energy Storage II LLC - 66716
  date: 2023-08 -> 2023-09 delayed by 1 month
100 MW - operation - california - Edwards Sanborn E4 - 65675
  date: 2023-08 -> 2023-09 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2023-10 -> 2023-11 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2023-10 -> 2023-11 delayed by 1 month
88 MW - operation - arizona - Storey Solar and Storage - 65956
  date: 2023-08 -> 2023-09 delayed by 1 month
116 MW - construction - idaho - Hemmingway BESS - 66325
  date: 2023-08 -> 2023-10 delayed by 2 months
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  date: 2024-04 -> 2024-02 accelerated by 2 months
75 MW - operation - nevada - Arrow Canyon Solar Hybrid - 62248
  date: 2023-08 -> 2023-10 delayed by 2 months
73 MW - operation - texas - Ranchland Wind Storage - 64545
  date: 2023-08 -> 2023-09 delayed by 1 month
70 MW - construction - texas - Antlia - 65588
  date: 2024-06 -> 2024-12 delayed by 6 months
68 MW - operation - california - Stanton Battery Energy Storage - 66423
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2023-08 -> 2023-09 delayed by 1 month
60 MW - operation - hawaii - AES Maui Kuihelani Solar Hybrid - 64256
  date: 2023-12 -> 2024-05 delayed by 5 months
52 MW - construction - hawaii - Ho'Ohana Solar 1 - 63723
  date: 2023-08 -> 2024-10 delayed by 14 months
50 MW - construction - texas - Tortolas - 65493
  date: 2023-12 -> 2024-03 delayed by 3 months
50 MW - operation - california - Victory Pass - 65743
  date: 2023-12 -> 2024-03 delayed by 3 months
40 MW - construction - idaho - Black Mesa BESS - 66326
  date: 2023-09 -> 2023-10 delayed by 1 month
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  date: 2023-08 -> 2023-09 delayed by 1 month
16 MW - operation - texas - Cameron Wind 1 LLC - 59118
  date: 2023-09 -> 2023-10 delayed by 1 month
10 MW - operation - california - Boulevard Energy Storage - 66279
  date: 2023-08 -> 2023-09 delayed by 1 month
10 MW - operation - california - Clairemont Energy Storage - 66266
  date: 2023-08 -> 2023-09 delayed by 1 month
10 MW - operation - california - Elliott Energy Storage - 66278
  date: 2023-08 -> 2023-09 delayed by 1 month
20 MW - operation - california - Melrose BESS - 66281
  date: 2023-08 -> 2023-09 delayed by 1 month
20 MW - operation - california - Melrose BESS - 66281
  date: 2023-08 -> 2023-09 delayed by 1 month
10 MW - operation - california - Pala Gomez Creek BESS - 66280
  date: 2023-08 -> 2023-09 delayed by 1 month
10 MW - operation - california - Paradise Energy Storage - 66265
  date: 2023-08 -> 2023-09 delayed by 1 month
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2023-10 -> 2023-11 delayed by 1 month
10 MW - construction - california - Sierra Energy Storage, LLC - 61803
  date: 2023-09 -> 2023-12 delayed by 3 months

200 MW - planning - california - Peregrine Energy Storage LLC - 66286
  status_verbose: (T) Regulatory approvals received. Not under construction -> (L) Regulatory approvals pending. Not under construction
162 MW - operation - california - Proxima - 66270
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
125 MW - operation - california - Oberon II Solar Project - 65735
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
125 MW - operation - california - Oberon Solar Project - 65734
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation

2023-09

New projects (30):
300 MW - construction - texas - GulfStar Power, LLC - 66871
300 MW - planning - new york - Hecate Grid Intrepid - 66911
220 MW - operation - nevada - Reid Gardner - 2324
200 MW - construction - indiana - Pike County Energy Storage - 66881
195 MW - planning - nevada - Bonanza Solar and Storage Project - 66908
150 MW - construction - texas - Myrtle Storage - 66913
150 MW - construction - texas - Danish Fields Storage - 66916
150 MW - planning - new york - KCE NY 29, LLC - 66862
122 MW - planning - texas - Lupinus Solar 2, LLC - 66896
105 MW - planning - connecticut - KCE CT 1, LLC - 66879
100 MW - construction - texas - Estonian Solar Project, LLC - 66872
100 MW - construction - texas - Ables Springs Solar & Storage - 66905
83 MW - planning - texas - Lupinus Solar 1, LLC - 66895
52 MW - planning - texas - Midpoint Solar, LLC - 66897
180 MW - planning - texas - Indigo Solar & Storage - 66891
50 MW - planning - texas - Albatross Solar, LLC - 66894
300 MW - planning - new york - Hecate Grid Intrepid - 66911
25 MW - construction - california - Baldy Mesa 2_Silver Peak Hybrid - 66885
20 MW - operation - arizona - SR McNeal - 66925
20 MW - cancelled - florida - South Tampa Energy Storage - 66869
10 MW - operation - texas - SMT Bay City LLC - 66930
10 MW - operation - texas - SMT Alamo LLC - 66929
10 MW - operation - texas - SMT Harlingen II LLC - 66933
10 MW - operation - texas - SMT Mercedes LLC - 66926
10 MW - operation - texas - SMT Mission LLC - 66927
10 MW - operation - texas - SMT Santa Rosa LLC - 66928
10 MW - operation - texas - SMT Elsa LLC - 66931
10 MW - operation - texas - SMT Los Fresnos LLC - 66932
10 MW - operation - texas - SMT Rio Grande I LLC - 66934
10 MW - operation - texas - SMT Rio Grande II LLC - 66935

Updated projects (56):

325 MW - operation - california - Desert Peak Energy Storage I - 65987
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
260 MW - operation - arizona - Sonoran Solar Energy - 66627
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
250 MW - operation - arizona - Sierra Estrella Energy Storage - 66334
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
230 MW - operation - california - Sunlight Storage II - 66575
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
150 MW - operation - new mexico - Arroyo Solar Energy Storage Hybrid - 63172
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
150 MW - operation - texas - Wolf Tank Storage - 66616
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
150 MW - construction - arizona - McFarland B Solar and Storage - 66637
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
149 MW - operation - california - Daggett 3 - 64852
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
100 MW - operation - arizona - McFarland A Solar and Storage - 66636
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
100 MW - construction - texas - TX10 Hummingbird Storage - 65693
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
100 MW - construction - texas - TX15 Limousin Oak Storage - 65698
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
  date: 2024-04 -> 2024-06 delayed by 2 months
75 MW - operation - california - Desert Peak Energy Storage II - 65988
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
75 MW - construction - california - Baldy Mesa Solar & Storage - 66598
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
65 MW - construction - california - San Jacinto Grid, LLC - 65657
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
65 MW - construction - georgia - Mossy Branch Battery Facility - 65018
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
60 MW - operation - arizona - Mesquite Solar 5, LLC - 65963
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
  date: 2023-12 -> 2023-07 accelerated by 5 months
60 MW - operation - hawaii - AES Maui Kuihelani Solar Hybrid - 64256
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
59 MW - operation - texas - Roseland Solar Project, LLC - 65028
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
50 MW - operation - texas - TX19 River Valley Storage 1 - 65699
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
50 MW - operation - texas - TX21 River Valley Storage 2 - 65700
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
50 MW - operation - texas - Roadrunner, LLC Hybrid - 62561
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
48 MW - operation - nevada - Yellow Pine Solar - 66357
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
30 MW - construction - hawaii - AES Waiawa Phase 2 Solar - 66066
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
20 MW - operation - new york - Willis Battery Storage - 63238
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
  date: 2023-09 -> 2023-07 accelerated by 2 months
20 MW - operation - new mexico - Jicarilla Solar 1 LLC - 66163
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
18 MW - operation - california - Edwards Sanborn S4 - 65677
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation

675 MW - construction - california - Menifee Power Bank - 66494
  date: 2024-08 -> 2024-06 accelerated by 2 months
675 MW - construction - california - Menifee Power Bank - 66494
  date: 2024-08 -> 2024-06 accelerated by 2 months
190 MW - operation - texas - Cunningham Storage - 65410
  date: 2023-07 -> 2023-08 delayed by 1 month
169 MW - operation - california - Sanborn BESS 3 - 65672
  date: 2023-08 -> 2023-09 delayed by 1 month
150 MW - construction - california - Desert Quartzite - 59871
  date: 2023-08 -> 2024-08 delayed by 12 months
136 MW - operation - california - Arica Solar - 65744
  date: 2023-11 -> 2023-12 delayed by 1 month
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2023-08 -> 2023-09 delayed by 1 month
100 MW - operation - arizona - Saint Energy Storage II LLC - 66716
  date: 2023-07 -> 2023-08 delayed by 1 month
100 MW - operation - california - Edwards Sanborn E4 - 65675
  date: 2023-07 -> 2023-08 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2023-09 -> 2023-10 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2023-09 -> 2023-10 delayed by 1 month
100 MW - operation - texas - St. Gall Energy Storage I - 66336
  date: 2023-12 -> 2024-01 delayed by 1 month
100 MW - planning - texas - Bexar ESS - 66400
  date: 2024-08 -> 2025-03 delayed by 7 months
116 MW - construction - idaho - Hemmingway BESS - 66325
  date: 2023-07 -> 2023-08 delayed by 1 month
75 MW - operation - california - Resurgence Solar - 64489
  date: 2023-07 -> 2023-08 delayed by 1 month
60 MW - operation - california - Goleta Energy Storage, LLC - 66394
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2023-10 -> 2023-11 delayed by 1 month
58 MW - planning - nevada - Boulder Solar III LLC - 65141
  date: 2023-12 -> 2025-12 delayed by 24 months
50 MW - operation - california - Victory Pass - 65743
  date: 2023-11 -> 2023-12 delayed by 1 month
675 MW - construction - california - Menifee Power Bank - 66494
  date: 2024-08 -> 2024-09 delayed by 1 month
40 MW - operation - california - Resurgence Solar II - 66620
  date: 2023-07 -> 2023-08 delayed by 1 month
40 MW - construction - california - Scarlet Solar (CA) - 64908
  date: 2024-03 -> 2024-06 delayed by 3 months
16 MW - operation - texas - Cameron Wind 1 LLC - 59118
  date: 2023-08 -> 2023-09 delayed by 1 month
20 MW - operation - new jersey - Justin Court Energy Storage - 66758
  date: 2023-07 -> 2023-11 delayed by 4 months
15 MW - planning - south carolina - Wolf Pit Branch Solar, LLC - 65437
  date: 2023-11 -> 2026-04 delayed by 29 months
20 MW - operation - california - Melrose BESS - 66281
  date: 2023-07 -> 2023-08 delayed by 1 month
20 MW - operation - california - Melrose BESS - 66281
  date: 2023-07 -> 2023-08 delayed by 1 month
10 MW - operation - california - Pala Gomez Creek BESS - 66280
  date: 2023-07 -> 2023-08 delayed by 1 month
10 MW - planning - maine - South Portland ESS, LLC - 64616
  date: 2023-12 -> 2024-02 delayed by 2 months

150 MW - operation - texas - Revolution - 66170
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
47 MW - operation - california - Sanborn BESS 4 - 65673
  plant name: Sanborn EBESS1 -> Sanborn BESS 4

2023-08

New projects (12):
275 MW - planning - connecticut - Elevate Middletown - 66786
150 MW - construction - texas - Borden County BESS - 66804
80 MW - operation - california - Raceway Solar & Storage - 66773
80 MW - construction - california - Bottleneck Energy Storage - 66757
72 MW - construction - texas - Fence Post Solar Hybrid Project, LLC - 66801
70 MW - planning - california - Elevate Pier S - 66787
50 MW - operation - new mexico - Sky Ranch Solar - 66814
28 MW - operation - california - Estrella Solar & Storage - 66772
24 MW - operation - texas - Upton County BESS - 64811
20 MW - operation - new jersey - Justin Court Energy Storage - 66758
15 MW - cancelled - florida - Dover Solar - 66129
15 MW - planning - new york - Elevate Arthur Kill - 66785

Updated projects (50):

750 MW - operation - california - Dynegy Moss Landing Power Plant Hybrid - 260
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
131 MW - operation - california - CED West Side Canal Battery Storage - 65980
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
125 MW - operation - colorado - Neptune Energy Center Hybrid - 63731
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
100 MW - operation - colorado - Thunder Wolf Energy Center Hybrid - 63776
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
66 MW - construction - south carolina - Lone Star Solar - 62235
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
50 MW - operation - new mexico - Buena Vista Energy Center - 66408
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
  date: 2023-07 -> 2023-06 accelerated by 1 month
50 MW - operation - texas - High Lonesome Wind Power, LLC Hybrid - 62562
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
20 MW - operation - new jersey - Andover Energy Storage Project - 65952
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation

500 MW - planning - texas - Hecate Energy Ramsey Storage - 66414
  date: 2024-06 -> 2025-12 delayed by 18 months
74 MW - planning - california - Kingsley Solar Farm - 64634
  date: 2024-06 -> 2025-06 delayed by 12 months
300 MW - planning - california - Nighthawk Energy Storage, LLC - 65889
  date: 2024-06 -> 2025-02 delayed by 8 months
260 MW - operation - arizona - Sonoran Solar Energy - 66627
  date: 2023-06 -> 2023-07 delayed by 1 month
259 MW - construction - texas - Five Wells Solar Center - Hybrid - 66420
  entity id: 65507 -> 65502
  entity name: Chesapeake Solar Project, LLC -> Five Wells Solar Center, LLC
  date: 2024-03 -> 2023-12 accelerated by 3 months
255 MW - planning - texas - Hecate Grid East Valley Storage - 66411
  date: 2024-06 -> 2025-12 delayed by 18 months
200 MW - planning - california - Aratina Solar Center 2 - 64215
  date: 2024-06 -> 2025-03 delayed by 9 months
169 MW - planning - new york - NY2 Battery - 63584
  date: 2024-06 -> 2024-12 delayed by 6 months
162 MW - operation - california - Proxima - 66270
  date: 2023-10 -> 2024-01 delayed by 3 months
150 MW - operation - new mexico - Arroyo Solar Energy Storage Hybrid - 63172
  date: 2023-06 -> 2023-07 delayed by 1 month
150 MW - operation - texas - Wolf Tank Storage - 66616
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-06 -> 2023-07 delayed by 1 month
149 MW - operation - california - Daggett 3 - 64852
  date: 2023-06 -> 2023-07 delayed by 1 month
131 MW - operation - california - Daggett 2 - 64851
  date: 2023-09 -> 2023-10 delayed by 1 month
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2023-06 -> 2023-08 delayed by 2 months
88 MW - operation - arizona - Storey Solar and Storage - 65956
  date: 2023-07 -> 2023-08 delayed by 1 month
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  date: 2023-12 -> 2024-04 delayed by 4 months
73 MW - operation - texas - Ranchland Wind Storage - 64545
  date: 2023-06 -> 2023-08 delayed by 2 months
65 MW - construction - california - San Jacinto Grid, LLC - 65657
  date: 2023-09 -> 2023-11 delayed by 2 months
65 MW - construction - georgia - Mossy Branch Battery Facility - 65018
  date: 2023-10 -> 2024-05 delayed by 7 months
60 MW - operation - arizona - Mesquite Solar 5, LLC - 65963
  date: 2023-06 -> 2023-12 delayed by 6 months
59 MW - operation - texas - Roseland Solar Project, LLC - 65028
  date: 2023-06 -> 2023-07 delayed by 1 month
50 MW - operation - texas - Roadrunner, LLC Hybrid - 62561
  date: 2023-06 -> 2023-07 delayed by 1 month
47 MW - operation - california - Sanborn BESS 4 - 65673
  date: 2023-08 -> 2023-12 delayed by 4 months
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  date: 2023-07 -> 2023-08 delayed by 1 month
20 MW - operation - new mexico - Jicarilla Solar 1 LLC - 66163
  date: 2023-06 -> 2023-07 delayed by 1 month
20 MW - operation - new york - Willis Battery Storage - 63238
  date: 2023-06 -> 2023-09 delayed by 3 months
20 MW - construction - california - Ortega Grid, LLC - 65656
  date: 2023-08 -> 2023-11 delayed by 3 months
18 MW - operation - california - Edwards Sanborn S4 - 65677
  date: 2023-06 -> 2023-07 delayed by 1 month
10 MW - construction - california - Hecate Energy Desert Storage 1 LLC - 65635
  date: 2023-09 -> 2023-11 delayed by 2 months
10 MW - construction - california - Carris Storage I - 65733
  date: 2023-09 -> 2023-11 delayed by 2 months
10 MW - operation - arizona - Mesquite Solar 4, LLC - 65962
  date: 2023-06 -> 2023-12 delayed by 6 months

250 MW - operation - arizona - Sierra Estrella Energy Storage - 66334
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (T) Regulatory approvals received. Not under construction
230 MW - operation - california - Sunlight Storage II - 66575
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction
185 MW - operation - hawaii - Kapolei Energy Storage - 66067
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
99 MW - construction - california - Lead BESS 1 - 66660
  plant name: Hanford BESS -> Lead BESS 1
99 MW - construction - california - Electrolyte BESS - 66661
  plant name: Henrietta BESS -> Electrolyte BESS
97 MW - construction - california - Acid BESS - 66659
  plant name: Malaga BESS -> Acid BESS
90 MW - construction - arizona - Superstition Energy Storage - 66333
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (T) Regulatory approvals received. Not under construction
40 MW - construction - california - Scarlet Solar (CA) - 64908
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
32 MW - construction - california - Lead BESS 2 - 66662
  plant name: BIA BESS -> Lead BESS 2
15 MW - planning - south carolina - Wolf Pit Branch Solar, LLC - 65437
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (L) Regulatory approvals pending. Not under construction

2023-07

New projects (21):
140 MW - cancelled - texas - Coati Solar, LLC - 66693
103 MW - construction - texas - Bright Arrow Solar, LLC - 66688
100 MW - operation - arizona - Saint Energy Storage II LLC - 66716
100 MW - construction - texas - Brazos Bend BESS, LLC - 66690
100 MW - planning - texas - Seven Flags BESS LLC - 66689
100 MW - planning - texas - Holly Branch Solar, LLC - 66692
99 MW - construction - california - Lead BESS 1 - 66660
99 MW - construction - california - Electrolyte BESS - 66661
97 MW - construction - california - Acid BESS - 66659
88 MW - operation - arizona - Storey Solar and Storage - 65956
125 MW - construction - california - Tumbleweed Energy Storage - 66666
70 MW - planning - california - Inland Empire Energy Storage - 66726
70 MW - planning - texas - Briggs Solar, LLC - 66691
125 MW - construction - california - Tumbleweed Energy Storage - 66666
40 MW - construction - florida - Lake Mabel Storage - 66641
40 MW - construction - florida - Wimauma Storage - 66640
32 MW - construction - california - Lead BESS 2 - 66662
25 MW - construction - california - West Ford Flat - 66669
20 MW - planning - new york - KCE NY 10, LLC - 66682
20 MW - planning - new york - Alfred Oaks Solar, LLC - 66675
20 MW - planning - new york - Cold Creek Solar - 66674

Disappeared projects (4):
350 MW - cancelled - texas - Tehuacana Creek 2 Solar and BESS - 65856
100 MW - cancelled - texas - TX18 Cottage Meadow Storage - 63879
100 MW - cancelled - texas - TX17 Nickel Prairie Storage - 63880
62 MW - cancelled - indiana - Peony Solar 1 - 66131

Updated projects (42):

240 MW - construction - california - Rexford Solar Farm - 64633
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
80 MW - operation - california - Sagebrush ESS - 65933
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
60 MW - operation - california - Goleta Energy Storage, LLC - 66394
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
50 MW - operation - new mexico - Buena Vista Energy Center - 66408
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-06 -> 2023-07 delayed by 1 month
40 MW - operation - california - Resurgence Solar II - 66620
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
20 MW - operation - new york - NY6 Battery - 65692
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
  date: 2023-06 -> 2023-05 accelerated by 1 month
12 MW - operation - ohio - Bowling Green Energy Storage Project - 65951
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
  date: 2023-06 -> 2023-05 accelerated by 1 month

418 MW - planning - texas - Tehuacana Creek 1 Solar and BESS - 65855
  date: 2024-05 -> 2025-07 delayed by 14 months
  mw: 350 -> 418
350 MW - planning - texas - Rowdy Creek Solar and BESS - 65854
  date: 2024-05 -> 2025-05 delayed by 12 months
190 MW - operation - texas - Cunningham Storage - 65410
  date: 2023-06 -> 2023-07 delayed by 1 month
185 MW - operation - hawaii - Kapolei Energy Storage - 66067
  date: 2023-07 -> 2023-08 delayed by 1 month
150 MW - operation - new mexico - Arroyo Solar Energy Storage Hybrid - 63172
  date: 2023-05 -> 2023-06 delayed by 1 month
150 MW - operation - texas - Wolf Tank Storage - 66616
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2023-05 -> 2023-06 delayed by 1 month
149 MW - operation - california - Daggett 3 - 64852
  date: 2023-09 -> 2023-06 accelerated by 3 months
131 MW - operation - california - CED West Side Canal Battery Storage - 65980
  date: 2023-05 -> 2023-06 delayed by 1 month
131 MW - operation - california - Daggett 2 - 64851
  date: 2023-11 -> 2023-09 accelerated by 2 months
117 MW - operation - california - Fifth Standard Solar PV, LLC (Hybrid) - 64197
  date: 2023-10 -> 2023-08 accelerated by 2 months
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2023-06 -> 2023-08 delayed by 2 months
100 MW - operation - colorado - Thunder Wolf Energy Center Hybrid - 63776
  date: 2023-05 -> 2023-06 delayed by 1 month
100 MW - operation - california - Edwards Sanborn E4 - 65675
  date: 2023-06 -> 2023-07 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2023-07 -> 2023-09 delayed by 2 months
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2023-07 -> 2023-09 delayed by 2 months
100 MW - construction - texas - TX10 Hummingbird Storage - 65693
  date: 2024-03 -> 2024-04 delayed by 1 month
100 MW - construction - texas - TX15 Limousin Oak Storage - 65698
  date: 2024-03 -> 2024-04 delayed by 1 month
100 MW - planning - texas - TX 14 Venus Mill Storage - 65788
  plant name: KCE TX 14: Venus Mill Storage -> TX 14 Venus Mill Storage
  date: 2024-07 -> 2025-12 delayed by 17 months
99 MW - construction - california - Noosa Energy Storage LLC - 64531
  date: 2023-10 -> 2024-09 delayed by 11 months
63 MW - operation - texas - House Mountain - 66006
  date: 2023-09 -> 2023-10 delayed by 1 month
50 MW - operation - texas - TX19 River Valley Storage 1 - 65699
  date: 2023-05 -> 2023-07 delayed by 2 months
50 MW - operation - texas - TX21 River Valley Storage 2 - 65700
  date: 2023-05 -> 2023-07 delayed by 2 months
20 MW - operation - new york - Willis Battery Storage - 63238
  date: 2023-05 -> 2023-06 delayed by 1 month
20 MW - operation - new mexico - Jicarilla Solar 1 LLC - 66163
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2023-05 -> 2023-06 delayed by 1 month

169 MW - planning - new york - NY2 Battery - 63584
  mw: 200 -> 169
75 MW - operation - california - Resurgence Solar - 64489
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  mw: 115 -> 75
20 MW - operation - new jersey - Andover Energy Storage Project - 65952
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
20 MW - operation - california - VESI Pomona - 50300
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
20 MW - operation - california - Melrose BESS - 66281
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
20 MW - operation - california - Melrose BESS - 66281
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
10 MW - operation - california - Pala Gomez Creek BESS - 66280
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
10 MW - operation - california - Boulevard Energy Storage - 66279
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
10 MW - operation - california - Clairemont Energy Storage - 66266
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
10 MW - operation - california - Elliott Energy Storage - 66278
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
10 MW - operation - california - Paradise Energy Storage - 66265
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2023-06

New projects (9):
260 MW - operation - arizona - Sonoran Solar Energy - 66627
150 MW - operation - texas - Wolf Tank Storage - 66616
150 MW - construction - arizona - McFarland B Solar and Storage - 66637
100 MW - operation - arizona - McFarland A Solar and Storage - 66636
100 MW - construction - california - Cald BESS - 66617
40 MW - operation - california - Resurgence Solar II - 66620
40 MW - planning - indiana - Vermillion Rise Solar - 65935
88 MW - construction - california - Chaparral Springs - 64864
13 MW - construction - california - Bear Canyon - 66650

Disappeared projects (1):
36 MW - cancelled - california - Willow Spring Solar 3, LLC - 60325

Updated projects (48):

162 MW - operation - california - Proxima - 66270
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
68 MW - operation - california - Stanton Battery Energy Storage - 66423
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
50 MW - cancelled - mississippi - OE_MS5 - 64529
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
50 MW - operation - mississippi - OE_MS6 - 65291
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
38 MW - operation - arizona - Foothills Solar Plant Hybrid - 57997
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
36 MW - operation - arizona - Gila Bend Hybrid - 59020
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
30 MW - operation - hawaii - AES Waikoloa Solar Hybrid - 63900
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
17 MW - operation - arizona - Cotton Center Solar Hybrid - 57561
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
17 MW - operation - arizona - Paloma Solar Hybrid - 57562
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
16 MW - operation - arizona - Hyder Solar Hybrid - 57563
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
14 MW - operation - arizona - Hyder II Hybrid - 58383
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation

210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  date: 2023-04 -> 2023-06 delayed by 2 months
190 MW - operation - texas - Cunningham Storage - 65410
  date: 2023-05 -> 2023-06 delayed by 1 month
185 MW - operation - hawaii - Kapolei Energy Storage - 66067
  date: 2023-06 -> 2023-07 delayed by 1 month
300 MW - planning - nevada - Southern Bighorn Solar Hybrid - 63113
  date: 2024-04 -> 2026-05 delayed by 25 months
125 MW - operation - california - Oberon Solar Project - 65734
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2023-06 -> 2023-09 delayed by 3 months
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2023-04 -> 2023-06 delayed by 2 months
100 MW - operation - california - Edwards Sanborn E4 - 65675
  date: 2023-04 -> 2023-06 delayed by 2 months
100 MW - cancelled - texas - Forest Grove - Dodd - 64131
  date: 2024-03 -> 2025-10 delayed by 19 months
116 MW - construction - idaho - Hemmingway BESS - 66325
  date: 2023-08 -> 2023-07 accelerated by 1 month
73 MW - operation - texas - Ranchland Wind Storage - 64545
  date: 2023-05 -> 2023-06 delayed by 1 month
70 MW - planning - california - JVR Energy Park LLC - 64428
  date: 2023-09 -> 2026-08 delayed by 35 months
65 MW - construction - california - San Jacinto Grid, LLC - 65657
  date: 2023-06 -> 2023-09 delayed by 3 months
59 MW - operation - texas - Roseland Solar Project, LLC - 65028
  date: 2023-05 -> 2023-06 delayed by 1 month
50 MW - operation - texas - High Lonesome Wind Power, LLC Hybrid - 62562
  date: 2023-04 -> 2023-06 delayed by 2 months
50 MW - operation - texas - Roadrunner, LLC Hybrid - 62561
  date: 2023-05 -> 2023-06 delayed by 1 month
50 MW - planning - montana - Beartooth Energy Storage LLC - 65407
  date: 2024-04 -> 2027-12 delayed by 44 months
48 MW - operation - nevada - Yellow Pine Solar - 66357
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-06 -> 2023-07 delayed by 1 month
40 MW - construction - california - Scarlet Solar (CA) - 64908
  date: 2023-12 -> 2024-03 delayed by 3 months
20 MW - operation - new jersey - Andover Energy Storage Project - 65952
  date: 2023-04 -> 2023-06 delayed by 2 months
20 MW - construction - california - Ortega Grid, LLC - 65656
  date: 2023-06 -> 2023-08 delayed by 2 months
20 MW - operation - california - VESI Pomona - 50300
  date: 2023-06 -> 2023-10 delayed by 4 months
18 MW - operation - california - Edwards Sanborn S4 - 65677
  date: 2023-04 -> 2023-06 delayed by 2 months
12 MW - operation - ohio - Bowling Green Energy Storage Project - 65951
  date: 2023-04 -> 2023-06 delayed by 2 months
10 MW - operation - california - BCE Los Alamitos 1 - 66533
  date: 2023-07 -> 2023-08 delayed by 1 month
10 MW - operation - california - BCE Los Alamitos 2 - 66532
  date: 2023-07 -> 2023-08 delayed by 1 month
10 MW - construction - california - Sierra Energy Storage, LLC - 61803
  date: 2023-06 -> 2023-09 delayed by 3 months
10 MW - planning - texas - Grizzly Ridge Solar - 66410
  date: 2023-04 -> 2024-02 delayed by 10 months

750 MW - operation - california - Dynegy Moss Landing Power Plant Hybrid - 260
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
240 MW - construction - california - Rexford Solar Farm - 64633
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (T) Regulatory approvals received. Not under construction
259 MW - construction - texas - Five Wells Solar Center - Hybrid - 66420
  entity id: 65502 -> 65507
  entity name: Five Wells Solar Center, LLC -> Chesapeake Solar Project, LLC
150 MW - operation - texas - Revolution - 66170
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
136 MW - operation - california - Arica Solar - 65744
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
131 MW - operation - california - CED West Side Canal Battery Storage - 65980
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
125 MW - operation - california - Oberon II Solar Project - 65735
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
99 MW - construction - california - Noosa Energy Storage LLC - 64531
  entity id: 64164 -> 63883
  entity name: Noosa Energy Storage LLC -> Broad Reach Power
75 MW - operation - nevada - Arrow Canyon Solar Hybrid - 62248
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
50 MW - operation - california - Victory Pass - 65743
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2023-05

New projects (11):
230 MW - operation - california - Sunlight Storage II - 66575
175 MW - construction - maine - Cross Town Energy Storage - 66606
150 MW - planning - illinois - Grey Fox Wind - 65939
100 MW - construction - new mexico - San Juan Solar I - 66574
50 MW - planning - texas - Peeler Solar, LLC - 65932
75 MW - construction - california - Baldy Mesa Solar & Storage - 66598
75 MW - planning - ohio - Springwater Solar, LLC - 65900
50 MW - construction - tennessee - Ridgely Energy Farm - 65445
40 MW - planning - illinois - Mulligan Solar, LLC - 65349
10 MW - operation - california - BCE Los Alamitos 1 - 66533
10 MW - operation - california - BCE Los Alamitos 2 - 66532

Updated projects (60):

132 MW - operation - california - North Central Valley - 66208
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
100 MW - operation - texas - Madero Grid - 63757
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
40 MW - operation - california - Fallbrook Energy Storage - 61365
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
16 MW - operation - texas - Cameron Wind 1 LLC - 59118
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
20 MW - construction - california - Ortega Grid, LLC - 65656
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
20 MW - construction - tennessee - Vonore Battery Energy Storage System - 64255
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
  date: 2023-08 -> 2023-12 delayed by 4 months
11 MW - operation - north carolina - Camp Lejeune Solar and Energy Storage - 59966
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
  date: 2023-04 -> 2023-03 accelerated by 1 month
10 MW - construction - california - Hecate Energy Desert Storage 1 LLC - 65635
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
10 MW - construction - california - Carris Storage I - 65733
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete

621 MW - planning - texas - Lunis Creek Solar and BESS SLF - 65852
  date: 2024-03 -> 2024-12 delayed by 9 months
600 MW - planning - texas - Clear Fork Creek Solar and BESS SLF - 65842
  date: 2024-03 -> 2025-12 delayed by 21 months
325 MW - operation - california - Desert Peak Energy Storage I - 65987
  date: 2023-06 -> 2023-07 delayed by 1 month
299 MW - planning - new york - NISA Electric Generation Project - 61331
  entity name: NYC ENERGY LLC -> NYC Energy LLC
  date: 2025-07 -> 2026-03 delayed by 8 months
210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  date: 2023-03 -> 2023-04 delayed by 1 month
162 MW - operation - california - Proxima - 66270
  date: 2023-09 -> 2023-10 delayed by 1 month
150 MW - operation - new mexico - Arroyo Solar Energy Storage Hybrid - 63172
  date: 2023-04 -> 2023-05 delayed by 1 month
150 MW - construction - california - Eland Solar & Storage Center, Phase 1 Hybrid - 61168
  date: 2024-03 -> 2024-11 delayed by 8 months
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2023-03 -> 2023-04 delayed by 1 month
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2023-04 -> 2023-06 delayed by 2 months
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2023-05 -> 2023-11 delayed by 6 months
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2023-05 -> 2023-11 delayed by 6 months
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2023-06 -> 2023-07 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2023-06 -> 2023-07 delayed by 1 month
299 MW - planning - new york - NISA Electric Generation Project - 61331
  entity name: NYC ENERGY LLC -> NYC Energy LLC
  date: 2024-03 -> 2026-03 delayed by 24 months
75 MW - operation - california - Desert Peak Energy Storage II - 65988
  date: 2023-06 -> 2023-07 delayed by 1 month
63 MW - operation - texas - House Mountain - 66006
  date: 2023-07 -> 2023-09 delayed by 2 months
60 MW - operation - california - Goleta Energy Storage, LLC - 66394
  status_verbose: (T) Regulatory approvals received. Not under construction -> (L) Regulatory approvals pending. Not under construction
  date: 2023-04 -> 2023-10 delayed by 6 months
60 MW - operation - hawaii - AES Maui Kuihelani Solar Hybrid - 64256
  date: 2023-10 -> 2023-12 delayed by 2 months
59 MW - operation - texas - Roseland Solar Project, LLC - 65028
  date: 2023-03 -> 2023-05 delayed by 2 months
88 MW - construction - california - Chaparral Springs - 64864
  date: 2023-09 -> 2023-12 delayed by 3 months
50 MW - operation - texas - High Lonesome Wind Power, LLC Hybrid - 62562
  date: 2023-03 -> 2023-04 delayed by 1 month
50 MW - operation - texas - TX19 River Valley Storage 1 - 65699
  date: 2023-03 -> 2023-05 delayed by 2 months
50 MW - operation - texas - TX21 River Valley Storage 2 - 65700
  date: 2023-03 -> 2023-05 delayed by 2 months
50 MW - operation - texas - Roadrunner, LLC Hybrid - 62561
  date: 2023-03 -> 2023-05 delayed by 2 months
125 MW - planning - california - Aratina Solar Center 1 Hybrid - 61167
  date: 2023-12 -> 2025-06 delayed by 18 months
38 MW - operation - arizona - Foothills Solar Plant Hybrid - 57997
  date: 2023-03 -> 2023-04 delayed by 1 month
36 MW - operation - arizona - Gila Bend Hybrid - 59020
  date: 2023-03 -> 2023-04 delayed by 1 month
30 MW - construction - california - Santa Paula Energy Storage LLC - 65397
  date: 2023-03 -> 2023-09 delayed by 6 months
20 MW - operation - new jersey - Andover Energy Storage Project - 65952
  date: 2023-03 -> 2023-04 delayed by 1 month
20 MW - operation - new york - Willis Battery Storage - 63238
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2023-03 -> 2023-05 delayed by 2 months
20 MW - operation - new mexico - Jicarilla Solar 1 LLC - 66163
  date: 2023-03 -> 2023-05 delayed by 2 months
20 MW - operation - california - VESI Pomona - 50300
  date: 2023-05 -> 2023-06 delayed by 1 month
20 MW - operation - virginia - Dry Bridge Storage - 65044
  date: 2023-04 -> 2023-09 delayed by 5 months
17 MW - operation - arizona - Cotton Center Solar Hybrid - 57561
  date: 2023-03 -> 2023-04 delayed by 1 month
17 MW - operation - arizona - Paloma Solar Hybrid - 57562
  date: 2023-03 -> 2023-04 delayed by 1 month
16 MW - operation - arizona - Hyder Solar Hybrid - 57563
  date: 2023-03 -> 2023-04 delayed by 1 month
14 MW - operation - arizona - Hyder II Hybrid - 58383
  date: 2023-03 -> 2023-04 delayed by 1 month
12 MW - operation - ohio - Bowling Green Energy Storage Project - 65951
  date: 2023-03 -> 2023-04 delayed by 1 month
12 MW - operation - hawaii - AES West Oahu Solar Hybrid - 64656
  date: 2023-06 -> 2023-09 delayed by 3 months
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2023-08 -> 2023-10 delayed by 2 months

675 MW - construction - california - Menifee Power Bank - 66494
  entity name: Menifee Power Bank -> Nova Power, LLC
  plant name: Nova Power -> Menifee Power Bank
675 MW - construction - california - Menifee Power Bank - 66494
  entity name: Menifee Power Bank -> Nova Power, LLC
  plant name: Nova Power -> Menifee Power Bank
117 MW - operation - california - Fifth Standard Solar PV, LLC (Hybrid) - 64197
  entity name: RWE Renewables Americas LLC -> RWE Renewables Americas, LLC
100 MW - construction - california - Beaumont BESS - 66461
  entity id: 64287 -> 65552
  entity name: Terra-Gen Operating Co-BESS -> Terra-Gen Operating Co-BESS 2
80 MW - operation - california - Sagebrush ESS - 65933
  entity id: 64287 -> 65552
  entity name: Terra-Gen Operating Co-BESS -> Terra-Gen Operating Co-BESS 2
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  entity name: RWE Renewables Americas LLC -> RWE Renewables Americas, LLC
80 MW - construction - california - Placerita ESS - 66462
  entity id: 64287 -> 65552
  entity name: Terra-Gen Operating Co-BESS -> Terra-Gen Operating Co-BESS 2
675 MW - construction - california - Menifee Power Bank - 66494
  entity name: Menifee Power Bank -> Nova Power, LLC
  plant name: Nova Power -> Menifee Power Bank
48 MW - operation - nevada - Yellow Pine Solar - 66357
  mw: 26 -> 48

2023-04

New projects (18):
500 MW - planning - texas - Hecate Energy Ramsey Storage - 66414
306 MW - planning - texas - Ash Creek BESS - 66391
259 MW - construction - texas - Five Wells Solar Center - Hybrid - 66420
255 MW - planning - texas - Hecate Grid East Valley Storage - 66411
675 MW - construction - california - Menifee Power Bank - 66494
675 MW - construction - california - Menifee Power Bank - 66494
200 MW - planning - texas - OCI Hillsboro - 66401
150 MW - planning - georgia - Aragon Energy Storage - 66431
135 MW - planning - california - Hecate Grid Gwent Storage 1 - 66409
100 MW - construction - california - Beaumont BESS - 66461
100 MW - planning - texas - Bexar ESS - 66400
80 MW - construction - california - Placerita ESS - 66462
68 MW - operation - california - Stanton Battery Energy Storage - 66423
60 MW - operation - california - Goleta Energy Storage, LLC - 66394
50 MW - operation - new mexico - Buena Vista Energy Center - 66408
675 MW - construction - california - Menifee Power Bank - 66494
50 MW - planning - texas - MRG Goody Solar Project Hybrid - 66390
10 MW - planning - texas - Grizzly Ridge Solar - 66410

Disappeared projects (3):
95 MW - cancelled - california - Sandrini Solar 100 - 65664
50 MW - construction - tennessee - Ridgely Energy Farm - 65445
22 MW - cancelled - california - Camino Solar - 63508

Updated projects (59):

150 MW - construction - california - Desert Quartzite - 59871
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
50 MW - operation - arizona - El Sol BESS - 62964
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
40 MW - construction - california - Scarlet Solar (CA) - 64908
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
36 MW - cancelled - california - Willow Spring Solar 3, LLC - 60325
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
17 MW - operation - florida - Lake Placid Solar Power Plant - 62541
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
10 MW - operation - arizona - Desert Star Hybrid - 59444
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
20 MW - operation - california - Melrose BESS - 66281
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
20 MW - operation - california - Melrose BESS - 66281
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
10 MW - operation - california - Pala Gomez Creek BESS - 66280
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
10 MW - operation - california - Boulevard Energy Storage - 66279
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
10 MW - operation - california - Clairemont Energy Storage - 66266
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
10 MW - operation - california - Elliott Energy Storage - 66278
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
10 MW - operation - california - Paradise Energy Storage - 66265
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete

250 MW - construction - texas - Zeya - 65880
  date: 2024-04 -> 2024-12 delayed by 8 months
210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  date: 2023-02 -> 2023-03 delayed by 1 month
200 MW - construction - texas - Hydra - 65490
  date: 2023-11 -> 2023-12 delayed by 1 month
200 MW - construction - texas - Dickens - 65489
  date: 2023-12 -> 2024-02 delayed by 2 months
200 MW - construction - texas - Paleo - 65491
  date: 2023-12 -> 2024-02 delayed by 2 months
200 MW - construction - texas - Cachi - 65861
  date: 2024-03 -> 2024-12 delayed by 9 months
200 MW - construction - texas - Castor - 65870
  date: 2024-05 -> 2024-12 delayed by 7 months
200 MW - construction - texas - Desna - 65876
  date: 2024-06 -> 2024-12 delayed by 6 months
190 MW - operation - texas - Cunningham Storage - 65410
  entity id: 64757 -> 57416
  entity name: BT Cunningham Storage, LLC -> Acciona Energy USA Global, LLC
  date: 2023-03 -> 2023-05 delayed by 2 months
175 MW - construction - texas - Pavo - 65492
  date: 2023-11 -> 2023-12 delayed by 1 month
160 MW - construction - texas - Avila - 65860
  date: 2024-02 -> 2024-12 delayed by 10 months
150 MW - operation - new mexico - Arroyo Solar Energy Storage Hybrid - 63172
  date: 2023-02 -> 2023-04 delayed by 2 months
131 MW - operation - california - CED West Side Canal Battery Storage - 65980
  date: 2023-02 -> 2023-05 delayed by 3 months
117 MW - operation - california - Fifth Standard Solar PV, LLC (Hybrid) - 64197
  date: 2023-09 -> 2023-10 delayed by 1 month
75 MW - operation - california - Resurgence Solar - 64489
  date: 2023-05 -> 2023-07 delayed by 2 months
100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
  date: 2023-02 -> 2023-03 delayed by 1 month
100 MW - operation - texas - Madero Grid - 63757
  date: 2023-02 -> 2023-03 delayed by 1 month
100 MW - operation - california - Edwards Sanborn E4 - 65675
  date: 2023-07 -> 2023-04 accelerated by 3 months
  mw: 109 -> 100
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2023-05 -> 2023-06 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2023-05 -> 2023-06 delayed by 1 month
80 MW - operation - california - Sagebrush ESS - 65933
  entity id: 65106 -> 64287
  entity name: Sagebrush ESS, LLC -> Terra-Gen Operating Co-BESS
  date: 2023-03 -> 2023-05 delayed by 2 months
116 MW - construction - idaho - Hemmingway BESS - 66325
  date: 2023-06 -> 2023-08 delayed by 2 months
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  date: 2023-10 -> 2023-12 delayed by 2 months
75 MW - operation - nevada - Arrow Canyon Solar Hybrid - 62248
  date: 2023-06 -> 2023-08 delayed by 2 months
59 MW - operation - texas - Roseland Solar Project, LLC - 65028
  date: 2023-02 -> 2023-03 delayed by 1 month
50 MW - construction - texas - Tortolas - 65493
  date: 2023-09 -> 2023-12 delayed by 3 months
40 MW - construction - idaho - Black Mesa BESS - 66326
  date: 2023-06 -> 2023-09 delayed by 3 months
36 MW - operation - arizona - Gila Bend Hybrid - 59020
  date: 2023-02 -> 2023-03 delayed by 1 month
30 MW - operation - hawaii - AES Waikoloa Solar Hybrid - 63900
  date: 2023-02 -> 2023-04 delayed by 2 months
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  date: 2023-04 -> 2023-07 delayed by 3 months
17 MW - operation - arizona - Cotton Center Solar Hybrid - 57561
  date: 2023-02 -> 2023-03 delayed by 1 month
17 MW - operation - arizona - Paloma Solar Hybrid - 57562
  date: 2023-02 -> 2023-03 delayed by 1 month
16 MW - operation - arizona - Hyder Solar Hybrid - 57563
  date: 2023-02 -> 2023-03 delayed by 1 month
15 MW - planning - california - Black Walnut Energy Storage LLC - 65396
  date: 2023-12 -> 2025-06 delayed by 18 months
14 MW - operation - arizona - Hyder II Hybrid - 58383
  date: 2023-02 -> 2023-03 delayed by 1 month
14 MW - planning - california - Homestead Energy Storage LLC - 65398
  date: 2024-02 -> 2026-06 delayed by 28 months
12 MW - operation - ohio - Bowling Green Energy Storage Project - 65951
  date: 2023-02 -> 2023-03 delayed by 1 month
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2023-06 -> 2023-08 delayed by 2 months

750 MW - operation - california - Dynegy Moss Landing Power Plant Hybrid - 260
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
169 MW - operation - california - Sanborn BESS 3 - 65672
  mw: 175 -> 169
136 MW - operation - california - Edwards Sanborn E1B - 65674
  mw: 140 -> 136
131 MW - operation - california - Daggett 2 - 64851
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
47 MW - operation - california - Sanborn BESS 4 - 65673
  mw: 57 -> 47
47 MW - operation - california - Edwards Sanborn E5 - 65676
  mw: 75 -> 47
18 MW - operation - california - Edwards Sanborn S4 - 65677
  mw: 20 -> 18
11 MW - operation - north carolina - Camp Lejeune Solar and Energy Storage - 59966
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2023-03

New projects (40):
260 MW - planning - texas - OCI SunRoper - 65893
250 MW - operation - arizona - Sierra Estrella Energy Storage - 66334
225 MW - operation - california - Solar Blue - 63848
200 MW - operation - california - Condor Energy Storage LLC - 66285
200 MW - planning - california - Peregrine Energy Storage LLC - 66286
200 MW - planning - texas - Tidwell Prairie Storage 1 - 66337
162 MW - operation - california - Proxima - 66270
150 MW - planning - texas - Alamo 7 BESS 1 - 66297
150 MW - planning - texas - Alamo 7 BESS 2 - 66298
150 MW - planning - texas - Crane 2 BESS 2 - 66300
150 MW - planning - texas - Upton BESS 2 - 66303
150 MW - planning - texas - Uvalde 2 BESS 2 - 66305
150 MW - planning - texas - Peregrine BESS 1 - 66301
150 MW - planning - texas - Peregrine BESS 2 - 66302
135 MW - operation - california - Chestnut - 63849
100 MW - operation - texas - St. Gall Energy Storage I - 66336
100 MW - planning - texas - Alamo 3 BESS 2 - 66293
100 MW - planning - texas - Alamo 4 BESS - 66294
100 MW - planning - texas - Alamo 5 BESS 1 - 66295
100 MW - planning - texas - Alamo 5 BESS 2 - 66296
100 MW - construction - texas - Callisto I Energy Center - 66338
100 MW - cancelled - texas - TX18 Cottage Meadow Storage - 63879
100 MW - cancelled - texas - TX17 Nickel Prairie Storage - 63880
90 MW - construction - arizona - Superstition Energy Storage - 66333
116 MW - construction - idaho - Hemmingway BESS - 66325
76 MW - planning - texas - Gaia Hybrid - 66342
75 MW - planning - texas - Uvalde 2 BESS 1 - 66304
61 MW - planning - texas - Eagle Springs Hybrid - 66341
50 MW - construction - tennessee - Ridgely Energy Farm - 65445
40 MW - construction - idaho - Black Mesa BESS - 66326
48 MW - operation - nevada - Yellow Pine Solar - 66357
20 MW - operation - california - VESI Pomona - 50300
17 MW - planning - virginia - Powells Creek Solar - Hybrid - 65305
12 MW - planning - ohio - Salt City Solar Project - Hybrid - 65302
12 MW - planning - virginia - Sunnybrook Solar Project - Hybrid - 65307
20 MW - operation - california - Melrose BESS - 66281
20 MW - operation - california - Melrose BESS - 66281
10 MW - operation - california - Pala Gomez Creek BESS - 66280
10 MW - operation - california - Boulevard Energy Storage - 66279
10 MW - operation - california - Elliott Energy Storage - 66278

Disappeared projects (3):
280 MW - cancelled - nevada - Hot Pot Solar - 65419
100 MW - cancelled - montana - Haymaker Hybrid - 63878
25 MW - cancelled - colorado - Pike Solar Hybrid - 64212

Updated projects (54):

325 MW - operation - california - Desert Peak Energy Storage I - 65987
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
200 MW - construction - texas - Hydra - 65490
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
  date: 2023-06 -> 2023-11 delayed by 5 months
200 MW - construction - texas - Dickens - 65489
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
  date: 2023-06 -> 2023-12 delayed by 6 months
200 MW - construction - texas - Paleo - 65491
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
  date: 2023-06 -> 2023-12 delayed by 6 months
175 MW - construction - texas - Pavo - 65492
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
  date: 2023-06 -> 2023-11 delayed by 5 months
75 MW - operation - california - Resurgence Solar - 64489
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
75 MW - operation - california - Desert Peak Energy Storage II - 65988
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
75 MW - construction - california - Hummingbird Energy Storage LLC - 65395
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
50 MW - construction - texas - Tortolas - 65493
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
  date: 2023-06 -> 2023-09 delayed by 3 months
36 MW - operation - hawaii - Waiawa Solar Power Hybrid - 65058
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation

650 MW - planning - new york - Swiftsure - 64235
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (P) Planned for installation, but regulatory approvals not initiated
  date: 2025-12 -> 2026-06 delayed by 6 months
300 MW - planning - arizona - Atlas - 63798
  date: 2023-12 -> 2024-12 delayed by 12 months
300 MW - planning - california - Humidor Storage I - 65703
  date: 2024-01 -> 2025-06 delayed by 17 months
300 MW - planning - arizona - Red Antelope Solar & Energy Storage Farm - 64208
  date: 2024-11 -> 2027-05 delayed by 30 months
210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  date: 2023-01 -> 2023-02 delayed by 1 month
200 MW - planning - california - Big Rock Solar Farm - 64636
  date: 2023-12 -> 2024-12 delayed by 12 months
190 MW - operation - texas - Cunningham Storage - 65410
  date: 2023-02 -> 2023-03 delayed by 1 month
150 MW - construction - texas - Carina - 65589
  date: 2023-10 -> 2024-06 delayed by 8 months
150 MW - operation - california - Vikings Energy Farm - 65711
  date: 2023-12 -> 2024-08 delayed by 8 months
150 MW - construction - massachusetts - Cranberry Point Energy Storage - 62844
  date: 2024-06 -> 2025-05 delayed by 11 months
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2023-01 -> 2023-03 delayed by 2 months
100 MW - construction - texas - TX10 Hummingbird Storage - 65693
  date: 2024-01 -> 2024-03 delayed by 2 months
100 MW - construction - texas - TX15 Limousin Oak Storage - 65698
  date: 2024-01 -> 2024-03 delayed by 2 months
100 MW - planning - new york - Clermont - 64236
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (P) Planned for installation, but regulatory approvals not initiated
  date: 2024-12 -> 2026-12 delayed by 24 months
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  date: 2023-09 -> 2023-10 delayed by 1 month
80 MW - planning - california - Chiquito Grid, LLC - 65655
  date: 2024-12 -> 2025-12 delayed by 12 months
73 MW - operation - texas - Ranchland Wind Storage - 64545
  date: 2023-01 -> 2023-05 delayed by 4 months
70 MW - construction - texas - Antlia - 65588
  date: 2023-10 -> 2024-06 delayed by 8 months
63 MW - operation - texas - House Mountain - 66006
  date: 2023-05 -> 2023-07 delayed by 2 months
61 MW - cancelled - texas - Talitha Energy Project, LLC - 65891
  date: 2024-06 -> 2024-10 delayed by 4 months
61 MW - planning - texas - Oriana Solar LLC - 65849
  date: 2024-06 -> 2024-12 delayed by 6 months
59 MW - operation - texas - Roseland Solar Project, LLC - 65028
  date: 2023-01 -> 2023-02 delayed by 1 month
50 MW - operation - texas - High Lonesome Wind Power, LLC Hybrid - 62562
  date: 2023-01 -> 2023-03 delayed by 2 months
50 MW - operation - texas - Roadrunner, LLC Hybrid - 62561
  date: 2023-01 -> 2023-03 delayed by 2 months
40 MW - operation - california - Fallbrook Energy Storage - 61365
  date: 2023-01 -> 2023-03 delayed by 2 months
40 MW - construction - california - Scarlet Solar (CA) - 64908
  date: 2024-12 -> 2023-12 accelerated by 12 months
30 MW - construction - montana - Beaver Creek Wind Facility - 65019
  date: 2024-12 -> 2025-09 delayed by 9 months
30 MW - construction - montana - Beaver Creek IV - 65023
  date: 2024-12 -> 2025-09 delayed by 9 months
30 MW - planning - new mexico - Rockmont Solar and Storage Project - 64216
  date: 2024-04 -> 2026-06 delayed by 26 months
16 MW - operation - texas - Cameron Wind 1 LLC - 59118
  date: 2023-06 -> 2023-08 delayed by 2 months
20 MW - operation - new jersey - Andover Energy Storage Project - 65952
  date: 2023-02 -> 2023-03 delayed by 1 month
20 MW - operation - new york - NY6 Battery - 65692
  date: 2023-05 -> 2023-06 delayed by 1 month
20 MW - construction - montana - Beaver Creek II - 65020
  date: 2024-12 -> 2025-05 delayed by 5 months
20 MW - construction - montana - Beaver Creek III - 65021
  date: 2024-12 -> 2025-05 delayed by 5 months
17 MW - operation - florida - Lake Placid Solar Power Plant - 62541
  date: 2023-01 -> 2023-02 delayed by 1 month
12 MW - operation - ohio - Bowling Green Energy Storage Project - 65951
  date: 2023-01 -> 2023-02 delayed by 1 month
10 MW - construction - california - Sierra Energy Storage, LLC - 61803
  date: 2023-03 -> 2023-06 delayed by 3 months
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2023-04 -> 2023-06 delayed by 2 months

300 MW - planning - texas - Elio Energy LLC - 65850
  mw: 80 -> 300
125 MW - operation - colorado - Neptune Energy Center Hybrid - 63731
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
100 MW - operation - colorado - Thunder Wolf Energy Center Hybrid - 63776
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
60 MW - operation - arizona - Mesquite Solar 5, LLC - 65963
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
12 MW - operation - hawaii - AES West Oahu Solar Hybrid - 64656
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
10 MW - operation - arizona - Mesquite Solar 4, LLC - 65962
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2023-02

New projects (13):
230 MW - operation - california - Sunlight Storage - 65857
203 MW - operation - texas - Crossett Power Management LLC - 66009
150 MW - operation - texas - Revolution - 66170
132 MW - operation - california - North Central Valley - 66208
101 MW - operation - texas - Flower Valley II - 66007
101 MW - operation - texas - Swoose II - 66008
100 MW - planning - texas - Yaupon Solar Project (Hybrid) - 66216
100 MW - planning - california - Buena Vista Energy LLC - 56446
58 MW - planning - utah - Parowan Solar - 65823
20 MW - operation - new mexico - Jicarilla Solar 1 LLC - 66163
20 MW - planning - texas - Barilla Solar - 58710
10 MW - operation - california - Clairemont Energy Storage - 66266
10 MW - operation - california - Paradise Energy Storage - 66265

Disappeared projects (1):
200 MW - cancelled - nevada - Iron Point Solar (Hybrid) - 65377

Updated projects (51):

112 MW - operation - california - Blythe Mesa Solar II - 65053
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
100 MW - operation - nevada - Dry Lake Solar Energy Center - 63933
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
63 MW - operation - texas - House Mountain - 66006
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
50 MW - operation - texas - TX13 Endurance Park Storage - 65696
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
50 MW - operation - texas - TX23 Roughneck Storage - 65701
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
40 MW - operation - california - BigBeau Solar, LLC - 64993
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
15 MW - planning - south carolina - Wolf Pit Branch Solar, LLC - 65437
  status: construction -> planning
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (P) Planned for installation, but regulatory approvals not initiated

169 MW - planning - new york - NY2 Battery - 63584
  date: 2023-06 -> 2024-06 delayed by 12 months
252 MW - planning - oklahoma - Skeleton Creek Energy Center Hybrid - 62494
  date: 2023-12 -> 2025-12 delayed by 24 months
185 MW - operation - hawaii - Kapolei Energy Storage - 66067
  date: 2023-05 -> 2023-06 delayed by 1 month
180 MW - cancelled - nevada - Chuckwalla Solar, LLC - 64558
  date: 2023-12 -> 2025-12 delayed by 24 months
136 MW - operation - california - Arica Solar - 65744
  date: 2023-12 -> 2023-11 accelerated by 1 month
126 MW - construction - california - AVEP BESS - 65591
  date: 2023-05 -> 2024-06 delayed by 13 months
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2023-03 -> 2023-04 delayed by 1 month
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2023-04 -> 2023-05 delayed by 1 month
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2023-04 -> 2023-05 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2023-04 -> 2023-05 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2023-04 -> 2023-05 delayed by 1 month
80 MW - operation - california - Sagebrush ESS - 65933
  date: 2023-01 -> 2023-03 delayed by 2 months
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  date: 2023-08 -> 2023-09 delayed by 1 month
80 MW - planning - california - Chiquito Grid, LLC - 65655
  date: 2023-12 -> 2024-12 delayed by 12 months
75 MW - cancelled - wisconsin - Darien Solar - 64534
  date: 2023-12 -> 2024-11 delayed by 11 months
65 MW - construction - california - San Jacinto Grid, LLC - 65657
  date: 2023-05 -> 2023-06 delayed by 1 month
43 MW - planning - california - Dynegy Oakland Power Plant - 6211
  date: 2023-12 -> 2024-11 delayed by 11 months
40 MW - construction - california - Scarlet Solar (CA) - 64908
  date: 2023-08 -> 2024-12 delayed by 16 months
40 MW - planning - california - EDPR CA Solar Park VI LLC (CA) Hybrid - 62892
  date: 2023-12 -> 2024-12 delayed by 12 months
38 MW - operation - arizona - Foothills Solar Plant Hybrid - 57997
  date: 2022-12 -> 2023-03 delayed by 3 months
36 MW - operation - hawaii - Waiawa Solar Power Hybrid - 65058
  date: 2022-12 -> 2023-01 delayed by 1 month
36 MW - operation - arizona - Gila Bend Hybrid - 59020
  date: 2022-12 -> 2023-02 delayed by 2 months
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  date: 2023-03 -> 2023-04 delayed by 1 month
20 MW - operation - new york - Willis Battery Storage - 63238
  date: 2023-02 -> 2023-03 delayed by 1 month
20 MW - operation - virginia - Dry Bridge Storage - 65044
  entity name: Dominion Energy Inc -> Dominion Energy Inc.
  date: 2022-12 -> 2023-04 delayed by 4 months
20 MW - operation - new york - NY6 Battery - 65692
  date: 2023-02 -> 2023-05 delayed by 3 months
20 MW - construction - california - Ortega Grid, LLC - 65656
  date: 2023-03 -> 2023-06 delayed by 3 months
17 MW - operation - florida - Lake Placid Solar Power Plant - 62541
  date: 2022-12 -> 2023-01 delayed by 1 month
17 MW - operation - arizona - Cotton Center Solar Hybrid - 57561
  date: 2022-12 -> 2023-02 delayed by 2 months
17 MW - operation - arizona - Paloma Solar Hybrid - 57562
  date: 2022-12 -> 2023-02 delayed by 2 months
16 MW - operation - arizona - Hyder Solar Hybrid - 57563
  date: 2022-12 -> 2023-02 delayed by 2 months
14 MW - operation - arizona - Hyder II Hybrid - 58383
  date: 2022-12 -> 2023-02 delayed by 2 months
12 MW - operation - ohio - Bowling Green Energy Storage Project - 65951
  date: 2023-02 -> 2023-01 accelerated by 1 month
22 MW - cancelled - california - Camino Solar - 63508
  date: 2023-12 -> 2024-12 delayed by 12 months
10 MW - operation - arizona - Desert Star Hybrid - 59444
  date: 2022-12 -> 2023-02 delayed by 2 months
10 MW - construction - california - Sierra Energy Storage, LLC - 61803
  date: 2023-02 -> 2023-03 delayed by 1 month
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2023-03 -> 2023-04 delayed by 1 month
10 MW - construction - california - Hecate Energy Desert Storage 1 LLC - 65635
  date: 2023-05 -> 2023-09 delayed by 4 months
10 MW - construction - california - Carris Storage I - 65733
  date: 2023-05 -> 2023-09 delayed by 4 months

150 MW - operation - california - Vikings Energy Farm - 65711
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction
131 MW - operation - california - CED West Side Canal Battery Storage - 65980
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
75 MW - construction - california - Hummingbird Energy Storage LLC - 65395
  status_verbose: (T) Regulatory approvals received. Not under construction -> (L) Regulatory approvals pending. Not under construction
50 MW - planning - virginia - Dulles Solar and Storage - 65043
  entity name: Dominion Energy Inc -> Dominion Energy Inc.
15 MW - planning - california - Black Walnut Energy Storage LLC - 65396
  status_verbose: (T) Regulatory approvals received. Not under construction -> (L) Regulatory approvals pending. Not under construction

2023-01

New projects (4):
185 MW - operation - hawaii - Kapolei Energy Storage - 66067
75 MW - cancelled - texas - Trinity River Solar 1 - 66132
62 MW - cancelled - indiana - Peony Solar 1 - 66131
40 MW - operation - texas - Zier Solar - 66137

Updated projects (33):

131 MW - operation - california - Daggett 2 - 64851
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
50 MW - operation - texas - Byrd Ranch Storage - 65259
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
12 MW - operation - new mexico - Taos Mesa Energy Facility Hybrid - 63728
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - virginia - Danville BESS 1 - 65499
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation

500 MW - planning - california - Bellefield Solar and Energy Storage Farm - 64210
  date: 2024-11 -> 2025-12 delayed by 13 months
500 MW - planning - california - Bellefield 2 Solar & Energy Storage Farm - 64209
  date: 2024-12 -> 2026-11 delayed by 23 months
300 MW - planning - california - Humidor Storage I - 65703
  date: 2023-11 -> 2024-01 delayed by 2 months
210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  date: 2022-12 -> 2023-01 delayed by 1 month
150 MW - construction - california - Eland Solar & Storage Center, Phase 1 Hybrid - 61168
  date: 2023-11 -> 2024-03 delayed by 4 months
150 MW - planning - california - Eland Solar & Storage Center, Phase 2 Hybrid - 61169
  date: 2023-11 -> 2024-11 delayed by 12 months
136 MW - operation - california - Edwards Sanborn E1B - 65674
  date: 2023-09 -> 2023-10 delayed by 1 month
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2022-12 -> 2023-01 delayed by 1 month
112 MW - operation - california - Blythe Mesa Solar II - 65053
  date: 2022-11 -> 2022-12 delayed by 1 month
100 MW - operation - california - Edwards Sanborn E4 - 65675
  date: 2023-04 -> 2023-07 delayed by 3 months
100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
  date: 2022-12 -> 2023-02 delayed by 2 months
100 MW - operation - texas - Madero Grid - 63757
  date: 2022-12 -> 2023-02 delayed by 2 months
100 MW - construction - texas - TX10 Hummingbird Storage - 65693
  date: 2023-08 -> 2024-01 delayed by 5 months
100 MW - construction - texas - TX15 Limousin Oak Storage - 65698
  date: 2023-10 -> 2024-01 delayed by 3 months
63 MW - operation - texas - House Mountain - 66006
  date: 2023-04 -> 2023-05 delayed by 1 month
59 MW - operation - texas - Roseland Solar Project, LLC - 65028
  date: 2022-12 -> 2023-01 delayed by 1 month
47 MW - operation - california - Sanborn BESS 4 - 65673
  date: 2023-06 -> 2023-08 delayed by 2 months
50 MW - operation - texas - TX23 Roughneck Storage - 65701
  date: 2022-11 -> 2022-12 delayed by 1 month
50 MW - operation - arizona - El Sol BESS - 62964
  date: 2022-12 -> 2023-02 delayed by 2 months
40 MW - operation - california - Fallbrook Energy Storage - 61365
  date: 2022-12 -> 2023-01 delayed by 1 month
30 MW - construction - california - Santa Paula Energy Storage LLC - 65397
  date: 2022-11 -> 2023-03 delayed by 4 months
20 MW - operation - new york - Willis Battery Storage - 63238
  date: 2023-01 -> 2023-02 delayed by 1 month
20 MW - planning - new york - South Ripley Solar - 64911
  date: 2023-12 -> 2024-12 delayed by 12 months
17 MW - operation - florida - Lake Placid Solar Power Plant - 62541
  date: 2022-11 -> 2022-12 delayed by 1 month

380 MW - operation - nevada - Gemini Solar - 63352
  mw: 280 -> 380
100 MW - cancelled - texas - Forest Grove - Dodd - 64131
  entity name: Renewable Energy Ventures LLC -> Vistra Zero LLC
88 MW - construction - california - Chaparral Springs - 64864
  mw: 50 -> 52
30 MW - operation - hawaii - AES Waikoloa Solar Hybrid - 63900
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2022-12

New projects (1):
30 MW - construction - hawaii - AES Waiawa Phase 2 Solar - 66066

Updated projects (40):

350 MW - operation - california - Crimson - 65140
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
350 MW - operation - california - Crimson - 65140
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
125 MW - operation - texas - Noble Solar - 65271
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
125 MW - operation - california - Oberon II Solar Project - 65735
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
100 MW - operation - texas - TX12 Silicon Hill Storage - 65695
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
75 MW - operation - nevada - Arrow Canyon Solar Hybrid - 62248
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
50 MW - operation - texas - TX11 Republic Road Storage - 65694
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
24 MW - operation - new york - Orangeville Storage - 64686
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
20 MW - operation - california - Rabbitbrush Solar, LLC - 64630
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation

169 MW - operation - california - Sanborn BESS 3 - 65672
  date: 2023-05 -> 2023-08 delayed by 3 months
136 MW - operation - california - Edwards Sanborn E1B - 65674
  date: 2023-08 -> 2023-09 delayed by 1 month
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2022-11 -> 2022-12 delayed by 1 month
100 MW - operation - california - Edwards Sanborn E4 - 65675
  date: 2023-02 -> 2023-04 delayed by 2 months
47 MW - operation - california - Edwards Sanborn E5 - 65676
  date: 2023-06 -> 2023-09 delayed by 3 months
73 MW - operation - texas - Ranchland Wind Storage - 64545
  date: 2022-11 -> 2023-01 delayed by 2 months
59 MW - operation - texas - Roseland Solar Project, LLC - 65028
  date: 2022-11 -> 2022-12 delayed by 1 month
47 MW - operation - california - Sanborn BESS 4 - 65673
  date: 2023-01 -> 2023-06 delayed by 5 months
50 MW - operation - texas - Byrd Ranch Storage - 65259
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2022-10 -> 2022-11 delayed by 1 month
50 MW - operation - texas - High Lonesome Wind Power, LLC Hybrid - 62562
  date: 2022-11 -> 2023-01 delayed by 2 months
50 MW - operation - texas - Roadrunner, LLC Hybrid - 62561
  date: 2022-11 -> 2023-01 delayed by 2 months
50 MW - operation - texas - TX19 River Valley Storage 1 - 65699
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2023-01 -> 2023-03 delayed by 2 months
50 MW - operation - texas - TX21 River Valley Storage 2 - 65700
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2023-01 -> 2023-03 delayed by 2 months
88 MW - construction - california - Chaparral Springs - 64864
  date: 2022-12 -> 2023-09 delayed by 9 months
50 MW - cancelled - mississippi - OE_MS5 - 64529
  date: 2022-12 -> 2023-12 delayed by 12 months
50 MW - planning - virginia - Dulles Solar and Storage - 65043
  date: 2023-10 -> 2024-12 delayed by 14 months
40 MW - operation - california - Fallbrook Energy Storage - 61365
  date: 2022-10 -> 2022-12 delayed by 2 months
30 MW - construction - hawaii - Hale Kuawehi Solar Hybrid - 62529
  date: 2023-10 -> 2024-11 delayed by 13 months
20 MW - operation - virginia - Dry Bridge Storage - 65044
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2022-10 -> 2022-12 delayed by 2 months
20 MW - operation - new york - Willis Battery Storage - 63238
  date: 2022-12 -> 2023-01 delayed by 1 month
18 MW - operation - california - Edwards Sanborn S4 - 65677
  date: 2023-02 -> 2023-04 delayed by 2 months
12 MW - operation - new mexico - Taos Mesa Energy Facility Hybrid - 63728
  date: 2022-10 -> 2022-11 delayed by 1 month
11 MW - operation - north carolina - Camp Lejeune Solar and Energy Storage - 59966
  energy source code: -> MWH
  date: 2023-03 -> 2023-04 delayed by 1 month
10 MW - operation - virginia - Danville BESS 1 - 65499
  date: 2022-10 -> 2022-11 delayed by 1 month

149 MW - operation - california - Daggett 3 - 64852
  mw: 144 -> 149
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
50 MW - operation - texas - TX23 Roughneck Storage - 65701
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
50 MW - operation - texas - TX13 Endurance Park Storage - 65696
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
10 MW - construction - california - Sierra Energy Storage, LLC - 61803
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2022-11

New projects (6):
325 MW - operation - california - Desert Peak Energy Storage I - 65987
131 MW - operation - california - CED West Side Canal Battery Storage - 65980
127 MW - operation - california - Lancaster Area Battery - 66050
75 MW - operation - california - Desert Peak Energy Storage II - 65988
63 MW - operation - texas - House Mountain - 66006
11 MW - operation - north carolina - Camp Lejeune Solar and Energy Storage - 59966

Disappeared projects (1):
100 MW - cancelled - texas - TX17 Nickel Prairie Storage - 63880

Updated projects (41):

125 MW - operation - california - LeConte Energy Storage - 64701
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
117 MW - operation - california - Fifth Standard Solar PV, LLC (Hybrid) - 64197
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
80 MW - operation - california - Sagebrush ESS - 65933
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (V) Under construction, more than 50 percent complete
60 MW - operation - arizona - Mesquite Solar 5, LLC - 65963
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
10 MW - operation - arizona - Mesquite Solar 4, LLC - 65962
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete

350 MW - operation - california - Crimson - 65140
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2022-09 -> 2022-10 delayed by 1 month
190 MW - operation - texas - Cunningham Storage - 65410
  date: 2022-12 -> 2023-02 delayed by 2 months
125 MW - operation - texas - Noble Solar - 65271
  date: 2022-09 -> 2022-10 delayed by 1 month
125 MW - operation - colorado - Neptune Energy Center Hybrid - 63731
  date: 2022-12 -> 2023-06 delayed by 6 months
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2022-11 -> 2023-03 delayed by 4 months
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2022-11 -> 2023-04 delayed by 5 months
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2022-11 -> 2023-04 delayed by 5 months
100 MW - operation - texas - TX12 Silicon Hill Storage - 65695
  date: 2022-09 -> 2022-10 delayed by 1 month
100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
  date: 2022-10 -> 2022-12 delayed by 2 months
100 MW - operation - texas - Madero Grid - 63757
  date: 2022-10 -> 2022-12 delayed by 2 months
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2022-11 -> 2023-04 delayed by 5 months
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2022-11 -> 2023-04 delayed by 5 months
100 MW - operation - colorado - Thunder Wolf Energy Center Hybrid - 63776
  date: 2022-12 -> 2023-05 delayed by 5 months
65 MW - construction - california - San Jacinto Grid, LLC - 65657
  date: 2023-04 -> 2023-05 delayed by 1 month
50 MW - operation - texas - Byrd Ranch Storage - 65259
  date: 2022-09 -> 2022-10 delayed by 1 month
50 MW - operation - texas - TX11 Republic Road Storage - 65694
  date: 2022-09 -> 2022-10 delayed by 1 month
50 MW - operation - texas - TX23 Roughneck Storage - 65701
  date: 2022-09 -> 2022-11 delayed by 2 months
50 MW - operation - texas - TX13 Endurance Park Storage - 65696
  date: 2022-11 -> 2022-12 delayed by 1 month
50 MW - operation - texas - TX19 River Valley Storage 1 - 65699
  date: 2022-12 -> 2023-01 delayed by 1 month
50 MW - operation - texas - TX21 River Valley Storage 2 - 65700
  date: 2022-12 -> 2023-01 delayed by 1 month
125 MW - planning - california - Aratina Solar Center 1 Hybrid - 61167
  date: 2023-09 -> 2023-12 delayed by 3 months
43 MW - planning - california - Dynegy Oakland Power Plant - 6211
  date: 2023-07 -> 2023-12 delayed by 5 months
40 MW - operation - california - Fallbrook Energy Storage - 61365
  date: 2022-09 -> 2022-10 delayed by 1 month
20 MW - operation - new york - Willis Battery Storage - 63238
  date: 2022-11 -> 2022-12 delayed by 1 month
20 MW - operation - new york - NY6 Battery - 65692
  date: 2022-11 -> 2023-02 delayed by 3 months
20 MW - operation - new jersey - Andover Energy Storage Project - 65952
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2022-10 -> 2023-02 delayed by 4 months
17 MW - operation - florida - Lake Placid Solar Power Plant - 62541
  date: 2022-09 -> 2022-11 delayed by 2 months
15 MW - cancelled - hawaii - Paeahu Solar Hybrid - 62534
  date: 2023-09 -> 2024-10 delayed by 13 months
12 MW - operation - new mexico - Taos Mesa Energy Facility Hybrid - 63728
  date: 2022-09 -> 2022-10 delayed by 1 month
12 MW - operation - ohio - Bowling Green Energy Storage Project - 65951
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2022-10 -> 2023-02 delayed by 4 months
10 MW - operation - virginia - Danville BESS 1 - 65499
  date: 2022-09 -> 2022-10 delayed by 1 month
10 MW - construction - california - Hecate Energy Desert Storage 1 LLC - 65635
  date: 2023-04 -> 2023-05 delayed by 1 month
10 MW - construction - california - Carris Storage I - 65733
  date: 2023-04 -> 2023-05 delayed by 1 month

350 MW - operation - california - Crimson - 65140
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
149 MW - operation - california - Daggett 3 - 64852
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
10 MW - construction - california - Sierra Energy Storage, LLC - 61803
  entity id: 59380 -> 63883
  entity name: Enel Green Power NA, Inc. -> Broad Reach Power

2022-10

New projects (2):
60 MW - operation - arizona - Mesquite Solar 5, LLC - 65963
10 MW - operation - arizona - Mesquite Solar 4, LLC - 65962

Disappeared projects (4):
2250 MW - cancelled - nevada - Chill Sun Solar Project - 65895
40 MW - cancelled - california - Santa Ana Storage 3 - 65789
10 MW - cancelled - california - Sierra - 64320
10 MW - cancelled - california - Chevron - Lost Hills Hybrid - 63545

Updated projects (52):

136 MW - operation - california - Arica Solar - 65744
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
  date: 2022-12 -> 2023-12 delayed by 12 months
133 MW - operation - california - Edwards Sanborn E1A - 64878
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
132 MW - operation - california - Arlington Energy Center II - 64481
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
110 MW - operation - california - Arlington Energy Center III - 64564
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
52 MW - construction - hawaii - Ho'Ohana Solar 1 - 63723
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
50 MW - operation - arizona - El Sol BESS - 62964
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (V) Under construction, more than 50 percent complete
50 MW - operation - california - Victory Pass - 65743
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
  date: 2022-11 -> 2023-11 delayed by 12 months
38 MW - operation - arizona - Foothills Solar Plant Hybrid - 57997
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (V) Under construction, more than 50 percent complete
36 MW - operation - arizona - Gila Bend Hybrid - 59020
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (V) Under construction, more than 50 percent complete
16 MW - operation - texas - Cameron Wind 1 LLC - 59118
  status: construction -> planning
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (T) Regulatory approvals received. Not under construction
  date: 2022-10 -> 2023-06 delayed by 8 months
20 MW - operation - virginia - Dry Bridge Storage - 65044
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
17 MW - operation - arizona - Cotton Center Solar Hybrid - 57561
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (V) Under construction, more than 50 percent complete
17 MW - operation - arizona - Paloma Solar Hybrid - 57562
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (V) Under construction, more than 50 percent complete
16 MW - operation - arizona - Hyder Solar Hybrid - 57563
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (V) Under construction, more than 50 percent complete
14 MW - operation - arizona - Hyder II Hybrid - 58383
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (V) Under construction, more than 50 percent complete

210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  date: 2022-09 -> 2022-12 delayed by 3 months
350 MW - operation - california - Crimson - 65140
  date: 2022-08 -> 2022-09 delayed by 1 month
350 MW - operation - california - Crimson - 65140
  date: 2022-09 -> 2022-10 delayed by 1 month
125 MW - operation - california - LeConte Energy Storage - 64701
  date: 2022-08 -> 2022-09 delayed by 1 month
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2022-09 -> 2022-11 delayed by 2 months
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2022-09 -> 2022-11 delayed by 2 months
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2022-09 -> 2022-11 delayed by 2 months
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2022-10 -> 2022-11 delayed by 1 month
100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
  date: 2022-08 -> 2022-10 delayed by 2 months
100 MW - operation - texas - Madero Grid - 63757
  date: 2022-08 -> 2022-10 delayed by 2 months
75 MW - construction - california - Hummingbird Energy Storage LLC - 65395
  date: 2023-06 -> 2023-12 delayed by 6 months
73 MW - operation - texas - Ranchland Wind Storage - 64545
  date: 2022-09 -> 2022-11 delayed by 2 months
70 MW - planning - california - JVR Energy Park LLC - 64428
  date: 2022-12 -> 2023-09 delayed by 9 months
50 MW - operation - texas - Byrd Ranch Storage - 65259
  date: 2022-08 -> 2022-09 delayed by 1 month
50 MW - operation - texas - TX11 Republic Road Storage - 65694
  date: 2022-08 -> 2022-09 delayed by 1 month
50 MW - operation - texas - TX23 Roughneck Storage - 65701
  date: 2022-08 -> 2022-09 delayed by 1 month
50 MW - operation - texas - High Lonesome Wind Power, LLC Hybrid - 62562
  date: 2022-09 -> 2022-11 delayed by 2 months
50 MW - operation - texas - Roadrunner, LLC Hybrid - 62561
  date: 2022-09 -> 2022-11 delayed by 2 months
40 MW - operation - california - Fallbrook Energy Storage - 61365
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2022-08 -> 2022-09 delayed by 1 month
40 MW - operation - california - BigBeau Solar, LLC - 64993
  date: 2022-09 -> 2022-12 delayed by 3 months
30 MW - operation - hawaii - AES Waikoloa Solar Hybrid - 63900
  date: 2022-11 -> 2023-02 delayed by 3 months
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  date: 2022-12 -> 2023-03 delayed by 3 months
20 MW - operation - california - Rabbitbrush Solar, LLC - 64630
  date: 2022-08 -> 2022-10 delayed by 2 months
18 MW - operation - california - Edwards Sanborn S4 - 65677
  date: 2022-12 -> 2023-02 delayed by 2 months
17 MW - operation - florida - Lake Placid Solar Power Plant - 62541
  date: 2022-08 -> 2022-09 delayed by 1 month
15 MW - planning - california - Black Walnut Energy Storage LLC - 65396
  date: 2023-06 -> 2023-12 delayed by 6 months
12 MW - operation - new mexico - Taos Mesa Energy Facility Hybrid - 63728
  date: 2022-08 -> 2022-09 delayed by 1 month
12 MW - operation - hawaii - AES West Oahu Solar Hybrid - 64656
  date: 2023-01 -> 2023-06 delayed by 5 months
10 MW - construction - california - Sierra Energy Storage, LLC - 61803
  date: 2022-12 -> 2023-02 delayed by 2 months

59 MW - operation - texas - Roseland Solar Project, LLC - 65028
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
139 MW - operation - california - Slate Hybrid - 63727
  entity name: Goldman Sachs Renewable Power LLC -> MN8 Energy LLC
88 MW - construction - california - Chaparral Springs - 64864
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
139 MW - operation - california - Slate Hybrid - 63727
  entity name: Goldman Sachs Renewable Power LLC -> MN8 Energy LLC
40 MW - construction - california - Scarlet Solar (CA) - 64908
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (T) Regulatory approvals received. Not under construction
36 MW - operation - hawaii - Waiawa Solar Power Hybrid - 65058
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
139 MW - operation - california - Slate Hybrid - 63727
  entity name: Goldman Sachs Renewable Power LLC -> MN8 Energy LLC
139 MW - operation - california - Slate Hybrid - 63727
  entity name: Goldman Sachs Renewable Power LLC -> MN8 Energy LLC

2022-09

New projects (27):
2250 MW - cancelled - nevada - Chill Sun Solar Project - 65895
660 MW - cancelled - texas - Goldenrod Creek Solar and BESS SLF - 65845
621 MW - planning - texas - Lunis Creek Solar and BESS SLF - 65852
600 MW - planning - texas - Clear Fork Creek Solar and BESS SLF - 65842
443 MW - cancelled - texas - Dogwood Creek Solar and BESS - 65843
400 MW - planning - texas - Hollow Branch Creek 2 Solar and BESS SLF - 65851
350 MW - planning - texas - Rowdy Creek Solar and BESS - 65854
418 MW - planning - texas - Tehuacana Creek 1 Solar and BESS - 65855
350 MW - cancelled - texas - Tehuacana Creek 2 Solar and BESS - 65856
302 MW - planning - texas - Middlebrook Creek Solar and BESS - 65853
300 MW - planning - california - Nighthawk Energy Storage, LLC - 65889
250 MW - construction - texas - Zeya - 65880
200 MW - construction - texas - Cachi - 65861
200 MW - construction - texas - Castor - 65870
200 MW - construction - texas - Desna - 65876
200 MW - planning - texas - Eldora Energy LLC - 65847
160 MW - construction - texas - Avila - 65860
100 MW - planning - texas - TX 14 Venus Mill Storage - 65788
100 MW - planning - california - Sacramento Valley Energy Center, LLC - 65808
80 MW - operation - california - Sagebrush ESS - 65933
300 MW - planning - texas - Elio Energy LLC - 65850
61 MW - planning - texas - Oriana Solar LLC - 65849
61 MW - cancelled - texas - Talitha Energy Project, LLC - 65891
40 MW - cancelled - california - Santa Ana Storage 3 - 65789
20 MW - operation - new jersey - Andover Energy Storage Project - 65952
20 MW - planning - indiana - Honey Creek Solar - 65821
12 MW - operation - ohio - Bowling Green Energy Storage Project - 65951

Disappeared projects (1):
50 MW - construction - tennessee - Ridgely Energy Farm - 65445

Updated projects (38):

750 MW - operation - california - Dynegy Moss Landing Power Plant Hybrid - 260
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
260 MW - operation - texas - DeCordova Steam Electric Station - 8063
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
190 MW - operation - texas - Cunningham Storage - 65410
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (V) Under construction, more than 50 percent complete
125 MW - operation - california - Oberon Solar Project - 65734
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
42 MW - operation - california - Edwards Sanborn S1 - 64929
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
39 MW - operation - hawaii - Mililani South Solar Farm - 57242
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
35 MW - operation - california - Edwards Sanborn S3 - 64928
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
12 MW - operation - hawaii - AES West Oahu Solar Hybrid - 64656
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
10 MW - construction - california - Sierra Energy Storage, LLC - 61803
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete

210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  date: 2022-08 -> 2022-09 delayed by 1 month
200 MW - planning - california - Aratina Solar Center 2 - 64215
  date: 2023-06 -> 2024-06 delayed by 12 months
150 MW - operation - new mexico - Arroyo Solar Energy Storage Hybrid - 63172
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2022-12 -> 2023-02 delayed by 2 months
150 MW - construction - california - Eland Solar & Storage Center, Phase 1 Hybrid - 61168
  date: 2023-07 -> 2023-11 delayed by 4 months
125 MW - operation - california - LeConte Energy Storage - 64701
  date: 2022-07 -> 2022-08 delayed by 1 month
75 MW - operation - california - Resurgence Solar - 64489
  date: 2022-12 -> 2023-05 delayed by 5 months
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2022-09 -> 2022-10 delayed by 1 month
100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
  date: 2022-07 -> 2022-08 delayed by 1 month
100 MW - operation - texas - Madero Grid - 63757
  date: 2022-07 -> 2022-08 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2022-10 -> 2022-11 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2022-10 -> 2022-11 delayed by 1 month
73 MW - operation - texas - Ranchland Wind Storage - 64545
  date: 2022-07 -> 2022-09 delayed by 2 months
65 MW - construction - california - San Jacinto Grid, LLC - 65657
  date: 2023-03 -> 2023-04 delayed by 1 month
60 MW - operation - hawaii - AES Maui Kuihelani Solar Hybrid - 64256
  date: 2022-12 -> 2023-10 delayed by 10 months
50 MW - operation - texas - TX11 Republic Road Storage - 65694
  date: 2022-07 -> 2022-08 delayed by 1 month
50 MW - operation - texas - TX23 Roughneck Storage - 65701
  date: 2022-07 -> 2022-08 delayed by 1 month
50 MW - operation - texas - High Lonesome Wind Power, LLC Hybrid - 62562
  date: 2022-07 -> 2022-09 delayed by 2 months
50 MW - operation - texas - Roadrunner, LLC Hybrid - 62561
  date: 2022-08 -> 2022-09 delayed by 1 month
40 MW - construction - california - Scarlet Solar (CA) - 64908
  date: 2023-03 -> 2023-08 delayed by 5 months
20 MW - operation - new york - Willis Battery Storage - 63238
  date: 2022-09 -> 2022-11 delayed by 2 months
12 MW - operation - new mexico - Taos Mesa Energy Facility Hybrid - 63728
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2022-07 -> 2022-08 delayed by 1 month
10 MW - cancelled - california - Chevron - Lost Hills Hybrid - 63545
  date: 2022-08 -> 2022-09 delayed by 1 month
10 MW - construction - california - Hecate Energy Desert Storage 1 LLC - 65635
  date: 2022-12 -> 2023-04 delayed by 4 months
10 MW - construction - california - Carris Storage I - 65733
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction
  date: 2022-12 -> 2023-04 delayed by 4 months

224 MW - construction - california - Anode (Springville) BESS - 65458
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
224 MW - construction - california - Anode (Springville) BESS - 65458
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
40 MW - operation - california - Fallbrook Energy Storage - 61365
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
20 MW - operation - california - Rabbitbrush Solar, LLC - 64630
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
20 MW - construction - california - Ortega Grid, LLC - 65656
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction

2022-08

New projects (7):
136 MW - operation - california - Arica Solar - 65744
125 MW - operation - california - Oberon Solar Project - 65734
125 MW - operation - california - Oberon II Solar Project - 65735
95 MW - cancelled - california - Sandrini Solar 100 - 65664
50 MW - operation - california - Victory Pass - 65743
20 MW - operation - new york - NY6 Battery - 65692
10 MW - construction - california - Carris Storage I - 65733

Disappeared projects (1):
20 MW - cancelled - california - Renz Energy Storage - 63529

Updated projects (41):

100 MW - operation - california - Luna Storage - 63685
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
77 MW - operation - texas - Azure Sky Solar - 63905
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
59 MW - operation - texas - Roseland Solar Project, LLC - 65028
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
50 MW - operation - california - Maverick Solar 6, LLC - 64105
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
40 MW - operation - georgia - Hickory Park Solar Hybrid - 63522
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
30 MW - operation - hawaii - AES Waikoloa Solar Hybrid - 63900
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
16 MW - operation - texas - Cameron Wind 1 LLC - 59118
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
20 MW - operation - california - Santa Ana Storage 2 - 64921
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation

260 MW - operation - texas - DeCordova Steam Electric Station - 8063
  date: 2022-06 -> 2022-07 delayed by 1 month
210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  date: 2022-06 -> 2022-08 delayed by 2 months
350 MW - operation - california - Crimson - 65140
  date: 2022-06 -> 2022-08 delayed by 2 months
350 MW - operation - california - Crimson - 65140
  date: 2022-08 -> 2022-09 delayed by 1 month
131 MW - operation - california - Daggett 2 - 64851
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (T) Regulatory approvals received. Not under construction
  date: 2023-06 -> 2023-11 delayed by 5 months
125 MW - operation - california - LeConte Energy Storage - 64701
  date: 2022-06 -> 2022-07 delayed by 1 month
117 MW - operation - california - Fifth Standard Solar PV, LLC (Hybrid) - 64197
  date: 2022-12 -> 2023-09 delayed by 9 months
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2022-08 -> 2022-09 delayed by 1 month
224 MW - construction - california - Anode (Springville) BESS - 65458
  date: 2022-08 -> 2022-09 delayed by 1 month
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  date: 2022-08 -> 2022-09 delayed by 1 month
100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
  date: 2022-06 -> 2022-07 delayed by 1 month
100 MW - operation - texas - Madero Grid - 63757
  date: 2022-06 -> 2022-07 delayed by 1 month
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  date: 2022-12 -> 2023-08 delayed by 8 months
47 MW - operation - california - Edwards Sanborn E5 - 65676
  date: 2022-12 -> 2023-06 delayed by 6 months
50 MW - operation - texas - Roadrunner, LLC Hybrid - 62561
  date: 2022-06 -> 2022-08 delayed by 2 months
42 MW - operation - california - Edwards Sanborn S1 - 64929
  date: 2022-06 -> 2022-07 delayed by 1 month
35 MW - operation - california - Edwards Sanborn S3 - 64928
  date: 2022-06 -> 2022-07 delayed by 1 month
30 MW - planning - new mexico - Rockmont Solar and Storage Project - 64216
  date: 2023-06 -> 2024-04 delayed by 10 months
24 MW - operation - new york - Orangeville Storage - 64686
  date: 2022-06 -> 2022-10 delayed by 4 months
17 MW - operation - florida - Lake Placid Solar Power Plant - 62541
  date: 2022-06 -> 2022-08 delayed by 2 months
12 MW - operation - new mexico - Taos Mesa Energy Facility Hybrid - 63728
  plant producer type: IPP -> Electric Utility
  date: 2022-06 -> 2022-07 delayed by 1 month
10 MW - cancelled - california - Sierra - 64320
  date: 2022-08 -> 2022-09 delayed by 1 month
10 MW - operation - virginia - Danville BESS 1 - 65499
  date: 2022-07 -> 2022-09 delayed by 2 months
10 MW - operation - arizona - Desert Star Hybrid - 59444
  date: 2022-06 -> 2022-12 delayed by 6 months
10 MW - planning - maine - South Portland ESS, LLC - 64616
  date: 2023-06 -> 2023-12 delayed by 6 months

112 MW - operation - california - Blythe Mesa Solar II - 65053
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
139 MW - operation - california - Slate Hybrid - 63727
  entity name: Goldman Sachs Renewable Power Group -> Goldman Sachs Renewable Power LLC
139 MW - operation - california - Slate Hybrid - 63727
  entity name: Goldman Sachs Renewable Power Group -> Goldman Sachs Renewable Power LLC
139 MW - operation - california - Slate Hybrid - 63727
  entity name: Goldman Sachs Renewable Power Group -> Goldman Sachs Renewable Power LLC
139 MW - operation - california - Slate Hybrid - 63727
  entity name: Goldman Sachs Renewable Power Group -> Goldman Sachs Renewable Power LLC
10 MW - cancelled - california - Chevron - Lost Hills Hybrid - 63545
  entity name: Goldman Sachs Renewable Power Group -> Goldman Sachs Renewable Power LLC

2022-07

New projects (10):
300 MW - planning - california - Humidor Storage I - 65703
150 MW - operation - california - Vikings Energy Farm - 65711
100 MW - operation - texas - TX12 Silicon Hill Storage - 65695
100 MW - construction - texas - TX10 Hummingbird Storage - 65693
100 MW - construction - texas - TX15 Limousin Oak Storage - 65698
50 MW - operation - texas - TX11 Republic Road Storage - 65694
50 MW - operation - texas - TX23 Roughneck Storage - 65701
50 MW - operation - texas - TX13 Endurance Park Storage - 65696
50 MW - operation - texas - TX19 River Valley Storage 1 - 65699
50 MW - operation - texas - TX21 River Valley Storage 2 - 65700

Updated projects (25):

25 MW - operation - massachusetts - Outer Cape Community Battery - 62604
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
  date: 2022-06 -> 2022-05 accelerated by 1 month

240 MW - construction - california - Rexford Solar Farm - 64633
  date: 2023-04 -> 2024-04 delayed by 12 months
260 MW - operation - texas - DeCordova Steam Electric Station - 8063
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2022-05 -> 2022-06 delayed by 1 month
150 MW - operation - new mexico - Arroyo Solar Energy Storage Hybrid - 63172
  date: 2022-10 -> 2022-12 delayed by 2 months
133 MW - operation - california - Edwards Sanborn E1A - 64878
  date: 2022-07 -> 2022-08 delayed by 1 month
125 MW - operation - texas - Noble Solar - 65271
  date: 2022-06 -> 2022-09 delayed by 3 months
100 MW - operation - california - Luna Storage - 63685
  date: 2022-05 -> 2022-06 delayed by 1 month
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2022-08 -> 2022-10 delayed by 2 months
200 MW - construction - california - Cathode (Hinson) BESS - 65457
  date: 2022-08 -> 2022-10 delayed by 2 months
80 MW - planning - california - Chiquito Grid, LLC - 65655
  date: 2023-03 -> 2023-12 delayed by 9 months
75 MW - operation - nevada - Arrow Canyon Solar Hybrid - 62248
  date: 2022-12 -> 2023-06 delayed by 6 months
50 MW - operation - california - Maverick Solar 6, LLC - 64105
  date: 2022-05 -> 2022-06 delayed by 1 month
42 MW - operation - california - Edwards Sanborn S1 - 64929
  date: 2022-05 -> 2022-06 delayed by 1 month
40 MW - operation - georgia - Hickory Park Solar Hybrid - 63522
  date: 2022-05 -> 2022-06 delayed by 1 month
40 MW - operation - california - BigBeau Solar, LLC - 64993
  date: 2022-08 -> 2022-09 delayed by 1 month
40 MW - construction - california - Scarlet Solar (CA) - 64908
  date: 2022-12 -> 2023-03 delayed by 3 months
36 MW - operation - hawaii - Waiawa Solar Power Hybrid - 65058
  date: 2022-10 -> 2022-12 delayed by 2 months
35 MW - operation - california - Edwards Sanborn S3 - 64928
  date: 2022-05 -> 2022-06 delayed by 1 month
24 MW - operation - new york - Orangeville Storage - 64686
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2022-05 -> 2022-06 delayed by 1 month
20 MW - construction - connecticut - Pure Hedge LLC - 50736
  date: 2023-01 -> 2024-12 delayed by 23 months
10 MW - cancelled - california - Chevron - Lost Hills Hybrid - 63545
  date: 2022-07 -> 2022-08 delayed by 1 month
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2022-08 -> 2023-03 delayed by 7 months

120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
77 MW - operation - texas - Azure Sky Solar - 63905
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
20 MW - operation - california - Rabbitbrush Solar, LLC - 64630
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2022-06

New projects (10):
169 MW - operation - california - Sanborn BESS 3 - 65672
136 MW - operation - california - Edwards Sanborn E1B - 65674
100 MW - operation - california - Edwards Sanborn E4 - 65675
80 MW - planning - california - Chiquito Grid, LLC - 65655
47 MW - operation - california - Edwards Sanborn E5 - 65676
65 MW - construction - california - San Jacinto Grid, LLC - 65657
47 MW - operation - california - Sanborn BESS 4 - 65673
18 MW - operation - california - Edwards Sanborn S4 - 65677
20 MW - construction - california - Ortega Grid, LLC - 65656
10 MW - construction - california - Hecate Energy Desert Storage 1 LLC - 65635

Updated projects (26):

200 MW - operation - california - Diablo Energy Storage - 62175
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
182 MW - operation - california - Elkhorn Battery Energy Storage System - 62564
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
122 MW - operation - california - Edwards Sanborn E2 - 64879
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
60 MW - operation - california - Coso Battery Storage - 63943
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
139 MW - operation - california - Slate Hybrid - 63727
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - construction - california - Painter Energy Storage - 62729
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
  date: 2022-07 -> 2022-08 delayed by 1 month

150 MW - operation - new mexico - Arroyo Solar Energy Storage Hybrid - 63172
  date: 2022-08 -> 2022-10 delayed by 2 months
100 MW - cancelled - montana - Haymaker Hybrid - 63878
  date: 2024-12 -> 2025-10 delayed by 10 months
  mw: 200 -> 100
77 MW - operation - texas - Azure Sky Solar - 63905
  date: 2022-05 -> 2022-06 delayed by 1 month
73 MW - operation - texas - Ranchland Wind Storage - 64545
  date: 2022-05 -> 2022-07 delayed by 2 months
50 MW - operation - texas - Roadrunner, LLC Hybrid - 62561
  date: 2022-05 -> 2022-06 delayed by 1 month
42 MW - operation - california - Edwards Sanborn S1 - 64929
  date: 2022-04 -> 2022-05 delayed by 1 month
40 MW - operation - georgia - Hickory Park Solar Hybrid - 63522
  date: 2022-04 -> 2022-05 delayed by 1 month
40 MW - operation - california - Fallbrook Energy Storage - 61365
  date: 2022-06 -> 2022-08 delayed by 2 months
35 MW - operation - california - Edwards Sanborn S3 - 64928
  date: 2022-04 -> 2022-05 delayed by 1 month
30 MW - construction - hawaii - Hale Kuawehi Solar Hybrid - 62529
  date: 2022-12 -> 2023-10 delayed by 10 months
25 MW - operation - massachusetts - Outer Cape Community Battery - 62604
  date: 2022-04 -> 2022-06 delayed by 2 months
24 MW - operation - new york - Orangeville Storage - 64686
  date: 2022-04 -> 2022-05 delayed by 1 month
20 MW - operation - california - Santa Ana Storage 2 - 64921
  date: 2022-05 -> 2022-06 delayed by 1 month
20 MW - operation - new york - Willis Battery Storage - 63238
  date: 2022-08 -> 2022-09 delayed by 1 month
12 MW - operation - hawaii - AES West Oahu Solar Hybrid - 64656
  date: 2022-09 -> 2023-01 delayed by 4 months
10 MW - operation - virginia - Danville BESS 1 - 65499
  date: 2022-06 -> 2022-07 delayed by 1 month
10 MW - cancelled - california - Sierra - 64320
  date: 2022-05 -> 2022-08 delayed by 3 months

133 MW - operation - california - Edwards Sanborn E1A - 64878
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
125 MW - operation - california - LeConte Energy Storage - 64701
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
10 MW - cancelled - california - Chevron - Lost Hills Hybrid - 63545
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (OT) Other

2022-05

New projects (5):
150 MW - construction - california - Desert Quartzite - 59871
150 MW - construction - texas - Carina - 65589
126 MW - construction - california - AVEP BESS - 65591
125 MW - construction - texas - Octans - 65590
70 MW - construction - texas - Antlia - 65588

Updated projects (36):

224 MW - construction - california - Anode (Springville) BESS - 65458
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
224 MW - construction - california - Anode (Springville) BESS - 65458
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
50 MW - operation - nevada - Dodge Flat - 63913
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
72 MW - operation - california - RE Tranquillity - 59939
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
139 MW - operation - california - Slate Hybrid - 63727
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
30 MW - operation - oregon - Wheatridge Hybrid - 62745
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
25 MW - operation - nevada - Fish Springs - 64148
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
12 MW - operation - new mexico - Taos Mesa Energy Facility Hybrid - 63728
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (V) Under construction, more than 50 percent complete
  date: 2022-05 -> 2022-06 delayed by 1 month
139 MW - operation - california - Slate Hybrid - 63727
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation

210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  date: 2022-03 -> 2022-06 delayed by 3 months
200 MW - operation - california - Diablo Energy Storage - 62175
  date: 2022-03 -> 2022-04 delayed by 1 month
182 MW - operation - california - Elkhorn Battery Energy Storage System - 62564
  date: 2022-03 -> 2022-04 delayed by 1 month
149 MW - operation - california - Daggett 3 - 64852
  date: 2022-12 -> 2023-09 delayed by 9 months
122 MW - operation - california - Edwards Sanborn E2 - 64879
  date: 2022-03 -> 2022-04 delayed by 1 month
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  date: 2022-03 -> 2022-09 delayed by 6 months
100 MW - operation - california - Luna Storage - 63685
  date: 2022-04 -> 2022-05 delayed by 1 month
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  date: 2022-11 -> 2022-12 delayed by 1 month
73 MW - operation - texas - Ranchland Wind Storage - 64545
  date: 2022-03 -> 2022-05 delayed by 2 months
60 MW - operation - california - Coso Battery Storage - 63943
  date: 2022-03 -> 2022-04 delayed by 1 month
139 MW - operation - california - Slate Hybrid - 63727
  date: 2022-03 -> 2022-04 delayed by 1 month
42 MW - operation - california - Edwards Sanborn S1 - 64929
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2022-03 -> 2022-04 delayed by 1 month
40 MW - operation - california - BigBeau Solar, LLC - 64993
  date: 2022-07 -> 2022-08 delayed by 1 month
36 MW - operation - hawaii - Waiawa Solar Power Hybrid - 65058
  date: 2022-09 -> 2022-10 delayed by 1 month
35 MW - operation - california - Edwards Sanborn S3 - 64928
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2022-03 -> 2022-04 delayed by 1 month
24 MW - operation - new york - Orangeville Storage - 64686
  date: 2022-03 -> 2022-04 delayed by 1 month
20 MW - operation - california - Santa Ana Storage 2 - 64921
  date: 2022-04 -> 2022-05 delayed by 1 month
17 MW - operation - florida - Lake Placid Solar Power Plant - 62541
  date: 2022-04 -> 2022-06 delayed by 2 months
22 MW - cancelled - california - Camino Solar - 63508
  date: 2023-03 -> 2023-12 delayed by 9 months
10 MW - cancelled - california - Chevron - Lost Hills Hybrid - 63545
  date: 2022-06 -> 2022-07 delayed by 1 month

100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
100 MW - operation - texas - Madero Grid - 63757
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
39 MW - operation - hawaii - Mililani South Solar Farm - 57242
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
30 MW - construction - california - Santa Paula Energy Storage LLC - 65397
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
10 MW - cancelled - california - Sierra - 64320
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2022-04

New projects (15):
750 MW - operation - california - Dynegy Moss Landing Power Plant Hybrid - 260
200 MW - construction - texas - Dickens - 65489
200 MW - construction - texas - Hydra - 65490
200 MW - construction - texas - Paleo - 65491
175 MW - construction - texas - Pavo - 65492
224 MW - construction - california - Anode (Springville) BESS - 65458
224 MW - construction - california - Anode (Springville) BESS - 65458
112 MW - construction - california - Separator (Etiwanda) BESS - 65456
200 MW - construction - california - Cathode (Hinson) BESS - 65457
200 MW - construction - california - Cathode (Hinson) BESS - 65457
50 MW - construction - tennessee - Ridgely Energy Farm - 65445
66 MW - construction - south carolina - Lone Star Solar - 62235
50 MW - construction - texas - Tortolas - 65493
50 MW - planning - montana - Beartooth Energy Storage LLC - 65407
10 MW - operation - virginia - Danville BESS 1 - 65499

Updated projects (27):

139 MW - operation - california - Slate Hybrid - 63727
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - california - Kearny North Energy Storage - 64612
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - california - Kearny South Energy Storage - 64614
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation

210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  date: 2022-02 -> 2022-03 delayed by 1 month
200 MW - operation - california - Diablo Energy Storage - 62175
  date: 2022-02 -> 2022-03 delayed by 1 month
350 MW - operation - california - Crimson - 65140
  date: 2022-08 -> 2022-06 accelerated by 2 months
350 MW - operation - california - Crimson - 65140
  date: 2022-10 -> 2022-08 accelerated by 2 months
125 MW - operation - california - LeConte Energy Storage - 64701
  date: 2022-04 -> 2022-06 delayed by 2 months
100 MW - operation - texas - Madero Grid - 63757
  date: 2022-05 -> 2022-06 delayed by 1 month
77 MW - operation - texas - Azure Sky Solar - 63905
  date: 2022-02 -> 2022-05 delayed by 3 months
60 MW - operation - california - Coso Battery Storage - 63943
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2022-02 -> 2022-03 delayed by 1 month
40 MW - operation - georgia - Hickory Park Solar Hybrid - 63522
  date: 2022-03 -> 2022-04 delayed by 1 month
40 MW - operation - california - BigBeau Solar, LLC - 64993
  date: 2022-06 -> 2022-07 delayed by 1 month
40 MW - planning - california - EDPR CA Solar Park VI LLC (CA) Hybrid - 62892
  date: 2022-12 -> 2023-12 delayed by 12 months
39 MW - operation - hawaii - Mililani South Solar Farm - 57242
  date: 2022-09 -> 2022-07 accelerated by 2 months
72 MW - operation - california - RE Tranquillity - 59939
  date: 2022-02 -> 2022-03 delayed by 1 month
139 MW - operation - california - Slate Hybrid - 63727
  date: 2022-02 -> 2022-03 delayed by 1 month
20 MW - construction - tennessee - Vonore Battery Energy Storage System - 64255
  date: 2022-07 -> 2023-08 delayed by 13 months
12 MW - operation - new mexico - Taos Mesa Energy Facility Hybrid - 63728
  date: 2023-03 -> 2022-05 accelerated by 10 months
139 MW - operation - california - Slate Hybrid - 63727
  date: 2022-02 -> 2022-03 delayed by 1 month
10 MW - cancelled - california - Sierra - 64320
  date: 2022-03 -> 2022-05 delayed by 2 months
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2022-09 -> 2022-07 accelerated by 2 months
  mw: 40 -> 10

125 MW - operation - texas - Noble Solar - 65271
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
100 MW - operation - california - Luna Storage - 63685
  entity id: 63403 -> 61012
  entity name: Luna Storage, LLC -> AES Distributed Energy
139 MW - operation - california - Slate Hybrid - 63727
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
50 MW - operation - texas - Roadrunner, LLC Hybrid - 62561
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
50 MW - operation - texas - High Lonesome Wind Power, LLC Hybrid - 62562
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2022-03

New projects (11):
280 MW - cancelled - nevada - Hot Pot Solar - 65419
299 MW - planning - new york - NISA Electric Generation Project - 61331
200 MW - cancelled - nevada - Iron Point Solar (Hybrid) - 65377
190 MW - operation - texas - Cunningham Storage - 65410
75 MW - construction - california - Hummingbird Energy Storage LLC - 65395
75 MW - planning - texas - Noria Hondo Solar (Hybrid) - 65344
59 MW - operation - texas - Roseland Solar Project, LLC - 65028
30 MW - construction - california - Santa Paula Energy Storage LLC - 65397
15 MW - planning - california - Black Walnut Energy Storage LLC - 65396
15 MW - planning - south carolina - Wolf Pit Branch Solar, LLC - 65437
14 MW - planning - california - Homestead Energy Storage LLC - 65398

Disappeared projects (4):
316 MW - cancelled - new york - Ravenswood - 2500
316 MW - cancelled - new york - Ravenswood - 2500
316 MW - cancelled - new york - Ravenswood - 2500
60 MW - cancelled - hawaii - Kupehau - 63799

Updated projects (40):

50 MW - operation - texas - Byrd Ranch Storage - 65259
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
46 MW - operation - alaska - Soldotna - 57206
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
10 MW - operation - arkansas - Searcy Solar Hybrid - 62617
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
10 MW - operation - arizona - Desert Star Hybrid - 59444
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (V) Under construction, more than 50 percent complete

650 MW - planning - new york - Swiftsure - 64235
  date: 2023-12 -> 2025-12 delayed by 24 months
300 MW - planning - arizona - Atlas - 63798
  date: 2022-12 -> 2023-12 delayed by 12 months
200 MW - planning - california - Big Rock Solar Farm - 64636
  date: 2022-12 -> 2023-12 delayed by 12 months
182 MW - operation - california - Elkhorn Battery Energy Storage System - 62564
  date: 2022-01 -> 2022-03 delayed by 2 months
133 MW - operation - california - Edwards Sanborn E1A - 64878
  date: 2022-05 -> 2022-07 delayed by 2 months
122 MW - operation - california - Edwards Sanborn E2 - 64879
  date: 2022-02 -> 2022-03 delayed by 1 month
110 MW - operation - california - Arlington Energy Center III - 64564
  date: 2022-12 -> 2022-08 accelerated by 4 months
  mw: 47 -> 110
100 MW - planning - new york - Clermont - 64236
  date: 2023-12 -> 2024-12 delayed by 12 months
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  date: 2022-04 -> 2022-11 delayed by 7 months
299 MW - planning - new york - NISA Electric Generation Project - 61331
  date: 2023-11 -> 2024-03 delayed by 4 months
  mw: 300 -> 79
60 MW - operation - california - Coso Battery Storage - 63943
  date: 2022-01 -> 2022-02 delayed by 1 month
50 MW - operation - nevada - Dodge Flat - 63913
  date: 2022-02 -> 2022-03 delayed by 1 month
50 MW - planning - texas - TREX US Red Holly - 63202
  date: 2022-05 -> 2024-07 delayed by 26 months
139 MW - operation - california - Slate Hybrid - 63727
  date: 2022-01 -> 2022-02 delayed by 1 month
43 MW - planning - california - Dynegy Oakland Power Plant - 6211
  date: 2022-12 -> 2023-07 delayed by 7 months
  mw: 36 -> 43
40 MW - operation - georgia - Hickory Park Solar Hybrid - 63522
  date: 2022-02 -> 2022-03 delayed by 1 month
40 MW - operation - california - BigBeau Solar, LLC - 64993
  date: 2022-04 -> 2022-06 delayed by 2 months
39 MW - operation - hawaii - Mililani South Solar Farm - 57242
  date: 2022-07 -> 2022-09 delayed by 2 months
139 MW - operation - california - Slate Hybrid - 63727
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2022-01 -> 2022-02 delayed by 1 month
30 MW - construction - montana - Beaver Creek Wind Facility - 65019
  date: 2023-06 -> 2024-12 delayed by 18 months
30 MW - construction - montana - Beaver Creek IV - 65023
  date: 2023-06 -> 2024-12 delayed by 18 months
25 MW - operation - nevada - Fish Springs - 64148
  date: 2022-02 -> 2022-03 delayed by 1 month
24 MW - operation - new york - Orangeville Storage - 64686
  date: 2022-01 -> 2022-03 delayed by 2 months
20 MW - operation - new york - Willis Battery Storage - 63238
  date: 2022-06 -> 2022-08 delayed by 2 months
20 MW - construction - montana - Beaver Creek II - 65020
  date: 2023-06 -> 2024-12 delayed by 18 months
20 MW - construction - montana - Beaver Creek III - 65021
  date: 2023-06 -> 2024-12 delayed by 18 months
20 MW - planning - hawaii - Kahana Solar, LLC - 64095
  date: 2023-12 -> 2024-12 delayed by 12 months
15 MW - cancelled - hawaii - Paeahu Solar Hybrid - 62534
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (L) Regulatory approvals pending. Not under construction
  date: 2023-04 -> 2023-09 delayed by 5 months
15 MW - planning - hawaii - Barbers Point Solar, LLC - 64094
  date: 2023-12 -> 2024-12 delayed by 12 months
10 MW - operation - california - Kearny North Energy Storage - 64612
  date: 2022-01 -> 2022-02 delayed by 1 month
10 MW - operation - california - Kearny South Energy Storage - 64614
  date: 2022-01 -> 2022-02 delayed by 1 month
10 MW - cancelled - california - Chevron - Lost Hills Hybrid - 63545
  date: 2022-05 -> 2022-06 delayed by 1 month
10 MW - planning - maine - South Portland ESS, LLC - 64616
  date: 2023-01 -> 2023-06 delayed by 5 months

120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
75 MW - operation - california - Resurgence Solar - 64489
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction
139 MW - operation - california - Slate Hybrid - 63727
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation

2022-02

New projects (8):
125 MW - operation - texas - Noble Solar - 65271
50 MW - operation - texas - Byrd Ranch Storage - 65259
50 MW - operation - mississippi - OE_MS6 - 65291
88 MW - operation - california - RE Garland - 60233
39 MW - operation - hawaii - Mililani South Solar Farm - 57242
36 MW - cancelled - california - Willow Spring Solar 3, LLC - 60325
35 MW - operation - california - Edwards Sanborn S3 - 64928
12 MW - planning - delaware - ENGIE Solidago Solar Project - Hybrid - 65304

Updated projects (37):

149 MW - operation - california - Daggett 3 - 64852
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
125 MW - operation - colorado - Neptune Energy Center Hybrid - 63731
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
100 MW - operation - colorado - Thunder Wolf Energy Center Hybrid - 63776
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
90 MW - operation - nevada - Townsite Solar Project Hybrid - 60654
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
50 MW - operation - california - Hudson - High Desert Hybrid - 64624
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
88 MW - construction - california - Chaparral Springs - 64864
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
40 MW - operation - georgia - Cool Springs Solar (Hybrid) - 63721
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
30 MW - construction - hawaii - Hale Kuawehi Solar Hybrid - 62529
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
13 MW - operation - california - Edwards Sanborn E3 - 64877
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
  mw: 14 -> 13
11 MW - operation - florida - Trenton - 63995
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
  date: 2022-01 -> 2021-12 accelerated by 1 month

500 MW - planning - california - Bellefield Solar and Energy Storage Farm - 64210
  date: 2023-06 -> 2024-11 delayed by 17 months
500 MW - planning - california - Bellefield 2 Solar & Energy Storage Farm - 64209
  date: 2023-06 -> 2024-12 delayed by 18 months
300 MW - planning - arizona - Red Antelope Solar & Energy Storage Farm - 64208
  date: 2023-06 -> 2024-11 delayed by 17 months
  mw: 500 -> 300
210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  date: 2021-12 -> 2022-02 delayed by 2 months
200 MW - operation - california - Diablo Energy Storage - 62175
  date: 2022-01 -> 2022-02 delayed by 1 month
169 MW - planning - new york - NY2 Battery - 63584
  date: 2022-11 -> 2023-06 delayed by 7 months
100 MW - cancelled - montana - Haymaker Hybrid - 63878
  date: 2022-12 -> 2024-12 delayed by 24 months
182 MW - operation - california - Elkhorn Battery Energy Storage System - 62564
  date: 2021-12 -> 2022-01 delayed by 1 month
122 MW - operation - california - Edwards Sanborn E2 - 64879
  date: 2021-12 -> 2022-02 delayed by 2 months
100 MW - operation - texas - Madero Grid - 63757
  date: 2022-06 -> 2022-05 accelerated by 1 month
100 MW - cancelled - texas - TX17 Nickel Prairie Storage - 63880
  date: 2022-12 -> 2023-09 delayed by 9 months
77 MW - operation - texas - Azure Sky Solar - 63905
  date: 2021-12 -> 2022-02 delayed by 2 months
60 MW - operation - california - Coso Battery Storage - 63943
  date: 2021-12 -> 2022-01 delayed by 1 month
50 MW - operation - nevada - Dodge Flat - 63913
  date: 2021-12 -> 2022-02 delayed by 2 months
46 MW - operation - alaska - Soldotna - 57206
  date: 2021-12 -> 2022-01 delayed by 1 month
25 MW - operation - nevada - Fish Springs - 64148
  date: 2021-12 -> 2022-02 delayed by 2 months
24 MW - operation - new york - Orangeville Storage - 64686
  date: 2021-12 -> 2022-01 delayed by 1 month
20 MW - operation - new york - Willis Battery Storage - 63238
  date: 2022-03 -> 2022-06 delayed by 3 months
20 MW - operation - virginia - Dry Bridge Storage - 65044
  date: 2022-12 -> 2022-10 accelerated by 2 months
17 MW - operation - florida - Lake Placid Solar Power Plant - 62541
  date: 2021-12 -> 2022-04 delayed by 4 months
10 MW - operation - california - Kearny North Energy Storage - 64612
  date: 2021-12 -> 2022-01 delayed by 1 month
10 MW - operation - california - Kearny South Energy Storage - 64614
  date: 2021-12 -> 2022-01 delayed by 1 month
10 MW - operation - arkansas - Searcy Solar Hybrid - 62617
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2021-12 -> 2022-01 delayed by 1 month

133 MW - operation - california - Edwards Sanborn E1A - 64878
  mw: 72 -> 133
139 MW - operation - california - Slate Hybrid - 63727
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
42 MW - operation - california - Edwards Sanborn S1 - 64929
  mw: 11 -> 42
36 MW - operation - hawaii - Waiawa Solar Power Hybrid - 65058
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2022-01

New projects (1):
370 MW - planning - nevada - Arida Solar (Hybrid) - 63841

Disappeared projects (1):
88 MW - operation - california - RE Garland - 60233

Updated projects (42):

409 MW - operation - florida - Manatee Solar Energy Center - 60014
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
150 MW - construction - california - Eland Solar & Storage Center, Phase 1 Hybrid - 61168
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
  date: 2022-11 -> 2023-07 delayed by 8 months
125 MW - operation - california - LeConte Energy Storage - 64701
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
112 MW - operation - california - Blythe Mesa Solar II - 65053
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
100 MW - operation - california - Sanborn BESS 2 - 64713
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
60 MW - operation - california - Cal Flats BESS - 63930
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
50 MW - operation - texas - Roadrunner, LLC Hybrid - 62561
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
50 MW - operation - texas - High Lonesome Wind Power, LLC Hybrid - 62562
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
72 MW - operation - california - RE Tranquillity - 59939
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
  mw: 72 -> 37
36 MW - operation - hawaii - Waiawa Solar Power Hybrid - 65058
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
10 MW - operation - california - Henrietta D Energy Storage LLC - 60641
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation

200 MW - operation - california - Diablo Energy Storage - 62175
  date: 2021-11 -> 2022-01 delayed by 2 months
150 MW - operation - new mexico - Arroyo Solar Energy Storage Hybrid - 63172
  date: 2022-06 -> 2022-08 delayed by 2 months
150 MW - planning - california - Eland Solar & Storage Center, Phase 2 Hybrid - 61169
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (T) Regulatory approvals received. Not under construction
  date: 2023-07 -> 2023-11 delayed by 4 months
300 MW - planning - nevada - Southern Bighorn Solar Hybrid - 63113
  date: 2023-09 -> 2024-04 delayed by 7 months
100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
  date: 2022-05 -> 2022-06 delayed by 1 month
100 MW - operation - texas - Madero Grid - 63757
  date: 2022-04 -> 2022-06 delayed by 2 months
90 MW - operation - nevada - Townsite Solar Project Hybrid - 60654
  date: 2021-11 -> 2021-12 delayed by 1 month
77 MW - operation - texas - Azure Sky Solar - 63905
  date: 2021-11 -> 2021-12 delayed by 1 month
50 MW - operation - california - Hudson - High Desert Hybrid - 64624
  date: 2021-11 -> 2021-12 delayed by 1 month
50 MW - operation - california - Maverick Solar 6, LLC - 64105
  date: 2021-12 -> 2022-05 delayed by 5 months
46 MW - operation - alaska - Soldotna - 57206
  date: 2021-11 -> 2021-12 delayed by 1 month
139 MW - operation - california - Slate Hybrid - 63727
  entity id: 62780 -> 61944
  entity name: RE Slate 1 LLC -> Goldman Sachs Renewable Power Group
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2021-11 -> 2022-01 delayed by 2 months
40 MW - operation - georgia - Cool Springs Solar (Hybrid) - 63721
  date: 2021-11 -> 2021-12 delayed by 1 month
40 MW - operation - georgia - Hickory Park Solar Hybrid - 63522
  date: 2021-12 -> 2022-02 delayed by 2 months
139 MW - operation - california - Slate Hybrid - 63727
  entity id: 62780 -> 61944
  entity name: RE Slate 1 LLC -> Goldman Sachs Renewable Power Group
  date: 2021-12 -> 2022-01 delayed by 1 month
30 MW - operation - oregon - Wheatridge Hybrid - 62745
  date: 2021-12 -> 2022-03 delayed by 3 months
30 MW - planning - new mexico - Rockmont Solar and Storage Project - 64216
  date: 2022-06 -> 2023-06 delayed by 12 months
25 MW - operation - massachusetts - Outer Cape Community Battery - 62604
  date: 2021-12 -> 2022-04 delayed by 4 months
24 MW - operation - new york - Orangeville Storage - 64686
  date: 2021-11 -> 2021-12 delayed by 1 month
20 MW - construction - connecticut - Pure Hedge LLC - 50736
  date: 2022-01 -> 2023-01 delayed by 12 months
20 MW - cancelled - california - Renz Energy Storage - 63529
  date: 2022-05 -> 2023-05 delayed by 12 months
11 MW - operation - florida - Trenton - 63995
  date: 2021-11 -> 2022-01 delayed by 2 months
139 MW - operation - california - Slate Hybrid - 63727
  entity id: 62780 -> 61944
  entity name: RE Slate 1 LLC -> Goldman Sachs Renewable Power Group
  date: 2022-01 -> 2022-02 delayed by 1 month

260 MW - operation - texas - DeCordova Steam Electric Station - 8063
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
122 MW - operation - california - Edwards Sanborn E2 - 64879
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  mw: 66 -> 122
139 MW - operation - california - Slate Hybrid - 63727
  entity id: 62780 -> 61944
  entity name: RE Slate 1 LLC -> Goldman Sachs Renewable Power Group
10 MW - construction - california - Painter Energy Storage - 62729
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction
17 MW - operation - florida - Lake Placid Solar Power Plant - 62541
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
13 MW - operation - california - Edwards Sanborn E3 - 64877
  plant name: Edwards Sanborn E3 -> Edwards Sanborn E3
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  mw: 12 -> 14
10 MW - operation - california - Kearny North Energy Storage - 64612
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
10 MW - operation - california - Kearny South Energy Storage - 64614
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation

2021-12

New projects (5):
350 MW - operation - california - Crimson - 65140
350 MW - operation - california - Crimson - 65140
58 MW - planning - nevada - Boulder Solar III LLC - 65141
72 MW - operation - california - RE Tranquillity - 59939
30 MW - planning - virginia - Deer Wood Storage, LLC - 65145

Updated projects (34):

260 MW - operation - texas - DeCordova Steam Electric Station - 8063
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
100 MW - operation - texas - Bat Cave - 64312
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
100 MW - operation - texas - North Fork TX - 64317
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
100 MW - operation - texas - Chisholm Grid Energy Storage System - 63737
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
75 MW - operation - california - RE Mustang LLC - 59150
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
73 MW - operation - texas - Ranchland Wind Storage - 64545
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
40 MW - operation - texas - 2W Permian Solar Project Hybrid - 63255
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
30 MW - operation - oregon - Wheatridge Hybrid - 62745
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (V) Under construction, more than 50 percent complete
25 MW - operation - arizona - Agua Fria - 141
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
  date: 2021-10 -> 2021-09 accelerated by 1 month
20 MW - operation - california - Hecate Energy Johanna Facility - 62889
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
20 MW - operation - california - Hecate Energy Johanna Facility - 62889
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation

200 MW - operation - california - Diablo Energy Storage - 62175
  date: 2021-10 -> 2021-11 delayed by 1 month
182 MW - operation - california - Elkhorn Battery Energy Storage System - 62564
  date: 2021-11 -> 2021-12 delayed by 1 month
100 MW - operation - california - Sanborn BESS 2 - 64713
  date: 2021-10 -> 2021-11 delayed by 1 month
100 MW - operation - california - Luna Storage - 63685
  date: 2021-10 -> 2022-04 delayed by 6 months
77 MW - operation - texas - Azure Sky Solar - 63905
  date: 2021-10 -> 2021-11 delayed by 1 month
72 MW - operation - california - RE Tranquillity - 59939
  date: 2021-10 -> 2021-11 delayed by 1 month
60 MW - operation - california - Coso Battery Storage - 63943
  date: 2021-11 -> 2021-12 delayed by 1 month
50 MW - operation - california - Hudson - High Desert Hybrid - 64624
  date: 2021-10 -> 2021-11 delayed by 1 month
46 MW - operation - alaska - Soldotna - 57206
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2021-10 -> 2021-11 delayed by 1 month
40 MW - operation - georgia - Hickory Park Solar Hybrid - 63522
  date: 2021-11 -> 2021-12 delayed by 1 month
25 MW - operation - massachusetts - Outer Cape Community Battery - 62604
  date: 2021-11 -> 2021-12 delayed by 1 month
11 MW - operation - florida - Trenton - 63995
  date: 2021-10 -> 2021-11 delayed by 1 month
10 MW - operation - california - Henrietta D Energy Storage LLC - 60641
  date: 2021-10 -> 2021-11 delayed by 1 month
10 MW - operation - california - Kearny North Energy Storage - 64612
  date: 2021-11 -> 2021-12 delayed by 1 month
10 MW - operation - california - Kearny South Energy Storage - 64614
  date: 2021-11 -> 2021-12 delayed by 1 month
10 MW - cancelled - california - Sierra - 64320
  date: 2021-12 -> 2022-03 delayed by 3 months

210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
122 MW - operation - california - Edwards Sanborn E2 - 64879
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
139 MW - operation - california - Slate Hybrid - 63727
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
24 MW - operation - new york - Orangeville Storage - 64686
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
17 MW - operation - florida - Lake Placid Solar Power Plant - 62541
  status_verbose: (V) Under construction, more than 50 percent complete -> (U) Under construction, less than or equal to 50 percent complete
13 MW - operation - california - Edwards Sanborn E3 - 64877
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
139 MW - operation - california - Slate Hybrid - 63727
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2021-11

New projects (20):
112 MW - operation - california - Blythe Mesa Solar II - 65053
750 MW - operation - california - Dynegy Moss Landing Power Plant Hybrid - 260
65 MW - construction - georgia - Mossy Branch Battery Facility - 65018
88 MW - construction - california - Chaparral Springs - 64864
50 MW - planning - virginia - Dulles Solar and Storage - 65043
88 MW - operation - california - RE Garland - 60233
40 MW - operation - california - BigBeau Solar, LLC - 64993
40 MW - construction - california - Scarlet Solar (CA) - 64908
36 MW - operation - hawaii - Waiawa Solar Power Hybrid - 65058
30 MW - construction - montana - Beaver Creek Wind Facility - 65019
30 MW - construction - montana - Beaver Creek IV - 65023
16 MW - operation - texas - Cameron Wind 1 LLC - 59118
20 MW - operation - california - Santa Ana Storage 2 - 64921
20 MW - operation - california - Rabbitbrush Solar, LLC - 64630
20 MW - operation - virginia - Dry Bridge Storage - 65044
20 MW - construction - montana - Beaver Creek II - 65020
20 MW - construction - montana - Beaver Creek III - 65021
20 MW - planning - new york - South Ripley Solar - 64911
17 MW - operation - florida - Lake Placid Solar Power Plant - 62541
42 MW - operation - california - Edwards Sanborn S1 - 64929

Disappeared projects (1):
10 MW - cancelled - california - Goleta Grid Resiliency - 63736

Updated projects (28):

100 MW - operation - california - Sanborn BESS 1 - 64712
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
50 MW - operation - texas - Lily Solar Hybrid - 63892
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation

200 MW - operation - california - Diablo Energy Storage - 62175
  date: 2021-09 -> 2021-10 delayed by 1 month
182 MW - operation - california - Elkhorn Battery Energy Storage System - 62564
  date: 2021-10 -> 2021-11 delayed by 1 month
117 MW - operation - california - Fifth Standard Solar PV, LLC (Hybrid) - 64197
  date: 2022-09 -> 2022-12 delayed by 3 months
100 MW - operation - texas - Bat Cave - 64312
  date: 2021-09 -> 2021-10 delayed by 1 month
100 MW - operation - texas - North Fork TX - 64317
  date: 2021-09 -> 2021-10 delayed by 1 month
100 MW - operation - texas - Chisholm Grid Energy Storage System - 63737
  date: 2021-09 -> 2021-10 delayed by 1 month
77 MW - operation - texas - Azure Sky Solar - 63905
  date: 2021-09 -> 2021-10 delayed by 1 month
60 MW - operation - california - Cal Flats BESS - 63930
  date: 2021-10 -> 2021-11 delayed by 1 month
52 MW - construction - hawaii - Ho'Ohana Solar 1 - 63723
  date: 2022-09 -> 2023-08 delayed by 11 months
50 MW - operation - california - Hudson - High Desert Hybrid - 64624
  date: 2021-09 -> 2021-10 delayed by 1 month
40 MW - operation - california - Fallbrook Energy Storage - 61365
  date: 2021-12 -> 2022-06 delayed by 6 months
25 MW - operation - arizona - Agua Fria - 141
  date: 2021-09 -> 2021-10 delayed by 1 month
25 MW - operation - massachusetts - Outer Cape Community Battery - 62604
  date: 2021-09 -> 2021-11 delayed by 2 months
24 MW - operation - new york - Orangeville Storage - 64686
  date: 2021-10 -> 2021-11 delayed by 1 month
  mw: 20 -> 24
12 MW - operation - new mexico - Taos Mesa Energy Facility Hybrid - 63728
  date: 2021-09 -> 2023-03 delayed by 18 months
11 MW - operation - florida - Trenton - 63995
  date: 2021-09 -> 2021-10 delayed by 1 month
10 MW - operation - california - Henrietta D Energy Storage LLC - 60641
  date: 2021-09 -> 2021-10 delayed by 1 month
20 MW - operation - california - Hecate Energy Johanna Facility - 62889
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2021-09 -> 2021-10 delayed by 1 month
20 MW - operation - california - Hecate Energy Johanna Facility - 62889
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2021-09 -> 2021-10 delayed by 1 month
10 MW - operation - california - Kearny North Energy Storage - 64612
  date: 2021-10 -> 2021-11 delayed by 1 month
10 MW - operation - california - Kearny South Energy Storage - 64614
  date: 2021-10 -> 2021-11 delayed by 1 month
10 MW - cancelled - california - Sierra - 64320
  date: 2021-10 -> 2021-12 delayed by 2 months
10 MW - cancelled - california - Chevron - Lost Hills Hybrid - 63545
  date: 2022-02 -> 2022-05 delayed by 3 months

75 MW - operation - california - RE Mustang LLC - 59150
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
133 MW - operation - california - Edwards Sanborn E1A - 64878
  mw: 36 -> 72
122 MW - operation - california - Edwards Sanborn E2 - 64879
  mw: 33 -> 66

2021-10

New projects (1):
25 MW - operation - arizona - Agua Fria - 141

Updated projects (25):

150 MW - operation - new mexico - Arroyo Solar Energy Storage Hybrid - 63172
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
88 MW - operation - california - RE Garland - 60233
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
  mw: 88 -> 45

182 MW - operation - california - Elkhorn Battery Energy Storage System - 62564
  date: 2021-08 -> 2021-10 delayed by 2 months
100 MW - operation - texas - Bat Cave - 64312
  date: 2021-08 -> 2021-09 delayed by 1 month
100 MW - operation - texas - North Fork TX - 64317
  date: 2021-08 -> 2021-09 delayed by 1 month
100 MW - operation - california - Sanborn BESS 2 - 64713
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2021-09 -> 2021-10 delayed by 1 month
100 MW - operation - texas - Madero Grid - 63757
  date: 2022-01 -> 2022-04 delayed by 3 months
100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
  date: 2022-03 -> 2022-05 delayed by 2 months
77 MW - operation - texas - Azure Sky Solar - 63905
  date: 2021-08 -> 2021-09 delayed by 1 month
60 MW - operation - california - Cal Flats BESS - 63930
  date: 2021-09 -> 2021-10 delayed by 1 month
60 MW - operation - california - Coso Battery Storage - 63943
  date: 2021-10 -> 2021-11 delayed by 1 month
50 MW - operation - texas - Lily Solar Hybrid - 63892
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2021-08 -> 2021-09 delayed by 1 month
125 MW - planning - california - Aratina Solar Center 1 Hybrid - 61167
  date: 2022-08 -> 2023-09 delayed by 13 months
40 MW - operation - texas - 2W Permian Solar Project Hybrid - 63255
  date: 2021-08 -> 2021-10 delayed by 2 months
24 MW - operation - new york - Orangeville Storage - 64686
  date: 2021-09 -> 2021-10 delayed by 1 month
11 MW - operation - florida - Trenton - 63995
  date: 2021-08 -> 2021-09 delayed by 1 month
10 MW - operation - california - Kearny North Energy Storage - 64612
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2021-09 -> 2021-10 delayed by 1 month
10 MW - operation - california - Kearny South Energy Storage - 64614
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2021-09 -> 2021-10 delayed by 1 month
10 MW - cancelled - california - Chevron - Lost Hills Hybrid - 63545
  date: 2021-11 -> 2022-02 delayed by 3 months

100 MW - operation - california - Sanborn BESS 1 - 64712
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
75 MW - operation - california - RE Mustang LLC - 59150
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
50 MW - operation - california - Hudson - High Desert Hybrid - 64624
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
139 MW - operation - california - Slate Hybrid - 63727
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
40 MW - operation - georgia - Cool Springs Solar (Hybrid) - 63721
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
12 MW - operation - new mexico - Taos Mesa Energy Facility Hybrid - 63728
  status_verbose: (T) Regulatory approvals received. Not under construction -> (L) Regulatory approvals pending. Not under construction

2021-09

New projects (6):
149 MW - operation - california - Daggett 3 - 64852
131 MW - operation - california - Daggett 2 - 64851
133 MW - operation - california - Edwards Sanborn E1A - 64878
122 MW - operation - california - Edwards Sanborn E2 - 64879
25 MW - operation - nevada - Battle Mountain Solar Project - 61098
13 MW - operation - california - Edwards Sanborn E3 - 64877

Updated projects (20):

230 MW - operation - california - McCoy Solar Energy Project Hybrid - 58462
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
75 MW - operation - california - RE Mustang LLC - 59150
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete

200 MW - operation - california - Diablo Energy Storage - 62175
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2021-08 -> 2021-09 delayed by 1 month
182 MW - operation - california - Elkhorn Battery Energy Storage System - 62564
  date: 2021-07 -> 2021-08 delayed by 1 month
100 MW - operation - texas - Bat Cave - 64312
  date: 2021-07 -> 2021-08 delayed by 1 month
100 MW - operation - texas - North Fork TX - 64317
  date: 2021-07 -> 2021-08 delayed by 1 month
100 MW - operation - texas - Chisholm Grid Energy Storage System - 63737
  date: 2021-07 -> 2021-09 delayed by 2 months
100 MW - operation - california - Sanborn BESS 1 - 64712
  date: 2021-08 -> 2021-09 delayed by 1 month
100 MW - operation - california - Sanborn BESS 2 - 64713
  date: 2021-08 -> 2021-09 delayed by 1 month
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  date: 2022-05 -> 2022-04 accelerated by 1 month
60 MW - operation - california - Cal Flats BESS - 63930
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2021-08 -> 2021-09 delayed by 1 month
50 MW - operation - texas - Lily Solar Hybrid - 63892
  date: 2021-07 -> 2021-08 delayed by 1 month
46 MW - operation - alaska - Soldotna - 57206
  date: 2021-09 -> 2021-10 delayed by 1 month
24 MW - operation - new york - Orangeville Storage - 64686
  date: 2021-08 -> 2021-09 delayed by 1 month
10 MW - cancelled - california - Chevron - Lost Hills Hybrid - 63545
  date: 2021-10 -> 2021-11 delayed by 1 month

50 MW - operation - california - Hudson - High Desert Hybrid - 64624
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
50 MW - operation - california - Maverick Solar 6, LLC - 64105
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
25 MW - operation - massachusetts - Outer Cape Community Battery - 62604
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
20 MW - operation - california - Johanna Energy Center, LLC - 63843
  entity name: Santa Ana Storage 1 -> Johanna Energy Center, LLC
20 MW - operation - california - Hecate Energy Johanna Facility - 62889
  mw: 20 -> 10

2021-08

New projects (0):

Updated projects (30):

100 MW - operation - texas - Gambit Energy Storage - Angleton Storage - 64528
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
90 MW - operation - nevada - Townsite Solar Project Hybrid - 60654
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
63 MW - operation - california - Blythe Solar 110, LLC - 60093
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
50 MW - operation - california - Hudson - High Desert Hybrid - 64624
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
50 MW - operation - nevada - Dodge Flat - 63913
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (V) Under construction, more than 50 percent complete
40 MW - operation - georgia - Hickory Park Solar Hybrid - 63522
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (V) Under construction, more than 50 percent complete
30 MW - operation - california - Top Gun Energy Storage - 61366
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
  date: 2021-07 -> 2021-06 accelerated by 1 month
25 MW - operation - arizona - Agua Fria - 141
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
20 MW - operation - california - Johanna Energy Center, LLC - 63843
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
  date: 2021-08 -> 2021-06 accelerated by 2 months
10 MW - cancelled - california - Sierra - 64320
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete

100 MW - operation - texas - Bat Cave - 64312
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2021-06 -> 2021-07 delayed by 1 month
100 MW - operation - texas - North Fork TX - 64317
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2021-06 -> 2021-07 delayed by 1 month
60 MW - operation - california - Coso Battery Storage - 63943
  date: 2021-08 -> 2021-10 delayed by 2 months
50 MW - operation - texas - Lily Solar Hybrid - 63892
  date: 2021-06 -> 2021-07 delayed by 1 month
40 MW - operation - texas - 2W Permian Solar Project Hybrid - 63255
  date: 2021-07 -> 2021-08 delayed by 1 month
10 MW - construction - california - Painter Energy Storage - 62729
  date: 2021-12 -> 2022-09 delayed by 9 months
20 MW - operation - california - Hecate Energy Johanna Facility - 62889
  date: 2021-06 -> 2021-09 delayed by 3 months
11 MW - operation - florida - Trenton - 63995
  date: 2021-07 -> 2021-08 delayed by 1 month
20 MW - operation - california - Hecate Energy Johanna Facility - 62889
  date: 2021-06 -> 2021-09 delayed by 3 months
10 MW - operation - california - Kearny North Energy Storage - 64612
  date: 2021-06 -> 2021-09 delayed by 3 months
10 MW - operation - california - Kearny South Energy Storage - 64614
  date: 2021-06 -> 2021-09 delayed by 3 months

409 MW - operation - florida - Manatee Solar Energy Center - 60014
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  mw: 50 -> 210
125 MW - operation - california - LeConte Energy Storage - 64701
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (L) Regulatory approvals pending. Not under construction
100 MW - operation - texas - Chisholm Grid Energy Storage System - 63737
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
77 MW - operation - texas - Azure Sky Solar - 63905
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
72 MW - operation - california - RE Tranquillity - 59939
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
30 MW - planning - new mexico - Rockmont Solar and Storage Project - 64216
  mw: 200 -> 30
25 MW - operation - nevada - Fish Springs - 64148
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
10 MW - operation - arkansas - Searcy Solar Hybrid - 62617
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2021-07

New projects (6):
125 MW - operation - california - LeConte Energy Storage - 64701
100 MW - operation - california - Sanborn BESS 1 - 64712
100 MW - operation - california - Sanborn BESS 2 - 64713
75 MW - operation - california - RE Mustang LLC - 59150
25 MW - operation - arizona - Agua Fria - 141
24 MW - operation - new york - Orangeville Storage - 64686

Disappeared projects (1):
100 MW - cancelled - texas - TX18 Cottage Meadow Storage - 63879

Updated projects (18):

750 MW - operation - california - Dynegy Moss Landing Power Plant Hybrid - 260
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
  date: 2021-06 -> 2021-05 accelerated by 1 month
115 MW - operation - california - Blythe Solar III, LLC Hybrid - 60094
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
10 MW - operation - north carolina - Grissom Solar, LLC - 64450
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
10 MW - operation - california - Kearny North Energy Storage - 64612
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
10 MW - operation - california - Kearny South Energy Storage - 64614
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete

100 MW - operation - california - Luna Storage - 63685
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2021-07 -> 2021-10 delayed by 3 months
50 MW - operation - texas - High Lonesome Wind Power, LLC Hybrid - 62562
  date: 2022-05 -> 2022-07 delayed by 2 months
40 MW - operation - texas - 2W Permian Solar Project Hybrid - 63255
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2021-05 -> 2021-07 delayed by 2 months
30 MW - operation - california - Top Gun Energy Storage - 61366
  date: 2021-05 -> 2021-07 delayed by 2 months
20 MW - operation - california - Johanna Energy Center, LLC - 63843
  date: 2021-05 -> 2021-08 delayed by 3 months
20 MW - operation - new york - Willis Battery Storage - 63238
  date: 2021-09 -> 2022-03 delayed by 6 months
11 MW - operation - florida - Trenton - 63995
  date: 2021-06 -> 2021-07 delayed by 1 month
22 MW - cancelled - california - Camino Solar - 63508
  date: 2022-05 -> 2023-03 delayed by 10 months
10 MW - operation - california - Henrietta D Energy Storage LLC - 60641
  date: 2021-06 -> 2021-09 delayed by 3 months
10 MW - cancelled - california - Chevron - Lost Hills Hybrid - 63545
  date: 2021-09 -> 2021-10 delayed by 1 month

88 MW - operation - california - RE Garland - 60233
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
  mw: 210 -> 50
12 MW - operation - new mexico - Taos Mesa Energy Facility Hybrid - 63728
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction

2021-06

New projects (13):
74 MW - planning - california - Kingsley Solar Farm - 64634
240 MW - construction - california - Rexford Solar Farm - 64633
210 MW - operation - texas - Blue Jay Solar I, LLC - 64672
200 MW - planning - california - Big Rock Solar Farm - 64636
200 MW - planning - california - Sienna Solar Farm - 64632
50 MW - operation - california - Hudson - High Desert Hybrid - 64624
50 MW - operation - nevada - Dodge Flat - 63913
50 MW - operation - texas - High Lonesome Wind Power, LLC Hybrid - 62562
50 MW - operation - texas - Roadrunner, LLC Hybrid - 62561
12 MW - operation - hawaii - AES West Oahu Solar Hybrid - 64656
10 MW - operation - california - Kearny North Energy Storage - 64612
10 MW - operation - california - Kearny South Energy Storage - 64614
10 MW - planning - maine - South Portland ESS, LLC - 64616

Updated projects (14):

100 MW - operation - california - Saticoy - 63891
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
  date: 2021-05 -> 2021-04 accelerated by 1 month
100 MW - operation - texas - Gambit Energy Storage - Angleton Storage - 64528
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
  date: 2022-04 -> 2022-05 delayed by 1 month
30 MW - operation - arizona - Wilmot Energy Center LLC - 64426
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
  date: 2021-05 -> 2021-04 accelerated by 1 month
20 MW - operation - new york - Willis Battery Storage - 63238
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
14 MW - operation - hawaii - AES Kekaha Solar, LLC Hybrid - 63280
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
11 MW - operation - california - Silverstrand Grid Energy Storage System - 63735
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
10 MW - operation - north carolina - Grissom Solar, LLC - 64450
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete

60 MW - operation - california - Cal Flats BESS - 63930
  date: 2021-07 -> 2021-08 delayed by 1 month
10 MW - operation - arizona - Desert Star Hybrid - 59444
  date: 2021-12 -> 2022-06 delayed by 6 months

750 MW - operation - california - Dynegy Moss Landing Power Plant Hybrid - 260
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
100 MW - operation - texas - Chisholm Grid Energy Storage System - 63737
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
10 MW - cancelled - california - Chevron - Lost Hills Hybrid - 63545
  entity name: GSRP -> Goldman Sachs Renewable Power Group

2021-05

New projects (4):
180 MW - cancelled - nevada - Chuckwalla Solar, LLC - 64558
73 MW - operation - texas - Ranchland Wind Storage - 64545
50 MW - cancelled - mississippi - OE_MS5 - 64529
110 MW - operation - california - Arlington Energy Center III - 64564

Updated projects (15):

200 MW - operation - california - Diablo Energy Storage - 62175
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
115 MW - operation - california - Blythe Solar II, LLC - 60092
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
100 MW - operation - texas - Madero Grid - 63757
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
88 MW - operation - california - RE Garland - 60233
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
72 MW - operation - california - RE Tranquillity - 59939
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
60 MW - operation - california - Coso Battery Storage - 63943
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete

750 MW - operation - california - Dynegy Moss Landing Power Plant Hybrid - 260
  date: 2021-03 -> 2021-06 delayed by 3 months
260 MW - operation - texas - DeCordova Steam Electric Station - 8063
  date: 2022-02 -> 2022-05 delayed by 3 months
50 MW - planning - texas - TREX US Red Holly - 63202
  date: 2021-08 -> 2022-05 delayed by 9 months
25 MW - operation - massachusetts - Outer Cape Community Battery - 62604
  date: 2021-03 -> 2021-09 delayed by 6 months
20 MW - construction - connecticut - Pure Hedge LLC - 50736
  date: 2021-09 -> 2022-01 delayed by 4 months
10 MW - cancelled - california - Goleta Grid Resiliency - 63736
  date: 2022-12 -> 2022-09 accelerated by 3 months

100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction
63 MW - operation - california - Blythe Solar 110, LLC - 60093
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
40 MW - operation - georgia - Cool Springs Solar (Hybrid) - 63721
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2021-04

New projects (9):
132 MW - operation - california - Arlington Energy Center II - 64481
75 MW - operation - california - Resurgence Solar - 64489
100 MW - operation - texas - Gambit Energy Storage - Angleton Storage - 64528
99 MW - construction - california - Noosa Energy Storage LLC - 64531
75 MW - cancelled - wisconsin - Darien Solar - 64534
30 MW - operation - arizona - Wilmot Energy Center LLC - 64426
25 MW - operation - nevada - Fish Springs - 64148
10 MW - operation - north carolina - Grissom Solar, LLC - 64450
10 MW - operation - arizona - Desert Star Hybrid - 59444

Disappeared projects (1):
10 MW - cancelled - arizona - Desert Star Hybrid - 62965

Updated projects (15):

230 MW - operation - california - McCoy Solar Energy Project Hybrid - 58462
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
100 MW - operation - california - Luna Storage - 63685
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
60 MW - operation - california - Cal Flats BESS - 63930
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
10 MW - operation - california - Vallecito - 62801
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
  date: 2021-03 -> 2021-02 accelerated by 1 month

169 MW - planning - new york - NY2 Battery - 63584
  date: 2021-11 -> 2022-11 delayed by 12 months
115 MW - operation - california - Blythe Solar II, LLC - 60092
  date: 2021-02 -> 2021-03 delayed by 1 month
100 MW - operation - california - Saticoy - 63891
  date: 2021-04 -> 2021-05 delayed by 1 month
139 MW - operation - california - Slate Hybrid - 63727
  date: 2021-10 -> 2022-03 delayed by 5 months
  mw: 300 -> 50
20 MW - operation - california - Hecate Energy Johanna Facility - 62889
  date: 2021-04 -> 2021-06 delayed by 2 months
20 MW - cancelled - california - Renz Energy Storage - 63529
  date: 2021-12 -> 2022-05 delayed by 5 months
11 MW - operation - california - Silverstrand Grid Energy Storage System - 63735
  date: 2021-03 -> 2021-04 delayed by 1 month
20 MW - operation - california - Hecate Energy Johanna Facility - 62889
  date: 2021-04 -> 2021-06 delayed by 2 months

60 MW - operation - california - Coso Battery Storage - 63943
  entity id: 63611 -> 64172
  entity name: Coso Battery Storage LLC -> Arevon Asset Management
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
  entity id: 59380 -> 63883
  entity name: Enel Green Power NA, Inc. -> Broad Reach Power
11 MW - operation - florida - Trenton - 63995
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2021-03

New projects (9):
299 MW - planning - new york - NISA Electric Generation Project - 61331
88 MW - operation - california - RE Garland - 60233
72 MW - operation - california - RE Tranquillity - 59939
70 MW - planning - california - JVR Energy Park LLC - 64428
139 MW - operation - california - Slate Hybrid - 63727
10 MW - construction - california - Painter Energy Storage - 62729
139 MW - operation - california - Slate Hybrid - 63727
20 MW - construction - connecticut - Pure Hedge LLC - 50736
139 MW - operation - california - Slate Hybrid - 63727

Updated projects (22):

139 MW - operation - california - Slate Hybrid - 63727
  entity name: RE Slate LLC -> RE Slate 1 LLC
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
100 MW - operation - california - AES ES ALAMITOS, LLC - 61204
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (V) Under construction, more than 50 percent complete -> operation
35 MW - operation - california - Desert Harvest II LLC - 64103
  status: construction -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
  date: 2021-02 -> 2021-01 accelerated by 1 month

150 MW - construction - massachusetts - Cranberry Point Energy Storage - 62844
  date: 2023-05 -> 2024-06 delayed by 13 months
117 MW - operation - california - Fifth Standard Solar PV, LLC (Hybrid) - 64197
  date: 2022-12 -> 2022-09 accelerated by 3 months
100 MW - operation - texas - Madero Grid - 63757
  date: 2021-12 -> 2022-01 delayed by 1 month
100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
  date: 2022-01 -> 2022-03 delayed by 2 months
60 MW - operation - california - Cal Flats BESS - 63930
  entity id: 63600 -> 61230
  entity name: Cal Flats BESS, LLC -> CD Arevon USA, Inc.
  date: 2021-06 -> 2021-07 delayed by 1 month
60 MW - operation - california - Coso Battery Storage - 63943
  date: 2021-06 -> 2021-08 delayed by 2 months
50 MW - operation - arizona - El Sol BESS - 62964
  date: 2021-12 -> 2022-12 delayed by 12 months
40 MW - operation - california - Fallbrook Energy Storage - 61365
  date: 2021-05 -> 2021-12 delayed by 7 months
38 MW - operation - arizona - Foothills Solar Plant Hybrid - 57997
  date: 2021-12 -> 2022-12 delayed by 12 months
36 MW - operation - arizona - Gila Bend Hybrid - 59020
  date: 2021-12 -> 2022-12 delayed by 12 months
30 MW - operation - california - Top Gun Energy Storage - 61366
  date: 2021-04 -> 2021-05 delayed by 1 month
17 MW - operation - arizona - Cotton Center Solar Hybrid - 57561
  date: 2021-12 -> 2022-12 delayed by 12 months
17 MW - operation - arizona - Paloma Solar Hybrid - 57562
  date: 2021-12 -> 2022-12 delayed by 12 months
16 MW - operation - arizona - Hyder Solar Hybrid - 57563
  date: 2021-12 -> 2022-12 delayed by 12 months
15 MW - cancelled - hawaii - Paeahu Solar Hybrid - 62534
  date: 2022-12 -> 2023-04 delayed by 4 months
14 MW - operation - arizona - Hyder II Hybrid - 58383
  date: 2021-12 -> 2022-12 delayed by 12 months
10 MW - cancelled - arizona - Desert Star Hybrid - 62965
  date: 2021-12 -> 2022-12 delayed by 12 months

115 MW - operation - california - Blythe Solar III, LLC Hybrid - 60094
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
20 MW - cancelled - california - Renz Energy Storage - 63529
  plant name: Llagas Energy Storage -> Renz Energy Storage

2021-02

New projects (5):
100 MW - operation - texas - Bat Cave - 64312
100 MW - operation - texas - North Fork TX - 64317
63 MW - operation - california - Blythe Solar 110, LLC - 60093
22 MW - cancelled - california - Camino Solar - 63508
10 MW - cancelled - california - Sierra - 64320

Disappeared projects (1):
22 MW - cancelled - california - Camino Solar - 63508

Updated projects (20):

50 MW - operation - california - Maverick Solar 6, LLC - 64105
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
40 MW - operation - california - Fallbrook Energy Storage - 61365
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
20 MW - operation - california - Hecate Energy Johanna Facility - 62889
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
  date: 2021-01 -> 2021-04 delayed by 3 months
10 MW - operation - arkansas - Searcy Solar Hybrid - 62617
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete

750 MW - operation - california - Dynegy Moss Landing Power Plant Hybrid - 260
  date: 2020-12 -> 2021-03 delayed by 3 months
260 MW - operation - texas - DeCordova Steam Electric Station - 8063
  date: 2021-07 -> 2022-02 delayed by 7 months
100 MW - cancelled - montana - Haymaker Hybrid - 63878
  date: 2021-12 -> 2022-12 delayed by 12 months
100 MW - cancelled - texas - TX17 Nickel Prairie Storage - 63880
  date: 2021-12 -> 2022-12 delayed by 12 months
35 MW - operation - california - Desert Harvest II LLC - 64103
  status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
  date: 2020-12 -> 2021-02 delayed by 2 months
30 MW - operation - california - Top Gun Energy Storage - 61366
  date: 2021-03 -> 2021-04 delayed by 1 month
20 MW - operation - california - Hecate Energy Johanna Facility - 62889
  date: 2021-01 -> 2021-04 delayed by 3 months
20 MW - operation - california - Johanna Energy Center, LLC - 63843
  date: 2021-01 -> 2021-05 delayed by 4 months
10 MW - operation - california - Vallecito - 62801
  date: 2020-12 -> 2021-03 delayed by 3 months
10 MW - operation - california - Henrietta D Energy Storage LLC - 60641
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2021-04 -> 2021-06 delayed by 2 months

150 MW - operation - new mexico - Arroyo Solar Energy Storage Hybrid - 63172
  mw: 40 -> 150
117 MW - operation - california - Fifth Standard Solar PV, LLC (Hybrid) - 64197
  plant name: Fifth Standard Solar PV, LLC -> Fifth Standard Solar PV, LLC (Hybrid)
100 MW - operation - texas - Chisholm Grid Energy Storage System - 63737
  entity name: Astral Electricity, LLC -> Chisholm Grid, LLC
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
  plant name: Big Star Solar, LLC -> Big Star Solar, LLC (Hybrid)
11 MW - operation - california - Silverstrand Grid Energy Storage System - 63735
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
10 MW - cancelled - california - Goleta Grid Resiliency - 63736
  entity id: 62742 -> 61198
  entity name: ENEL BELLA ENERGY STORAGE, LLC -> esVolta LP

2021-01

New projects (13):
650 MW - planning - new york - Swiftsure - 64235
500 MW - planning - california - Bellefield 2 Solar & Energy Storage Farm - 64209
300 MW - planning - arizona - Red Antelope Solar & Energy Storage Farm - 64208
500 MW - planning - california - Bellefield Solar and Energy Storage Farm - 64210
30 MW - planning - new mexico - Rockmont Solar and Storage Project - 64216
200 MW - planning - california - Aratina Solar Center 2 - 64215
117 MW - operation - california - Fifth Standard Solar PV, LLC (Hybrid) - 64197
100 MW - planning - new york - Clermont - 64236
80 MW - construction - texas - Big Star Solar, LLC (Hybrid) - 64202
60 MW - operation - hawaii - AES Maui Kuihelani Solar Hybrid - 64256
25 MW - cancelled - colorado - Pike Solar Hybrid - 64212
20 MW - construction - tennessee - Vonore Battery Energy Storage System - 64255
20 MW - operation - california - Hecate Energy Johanna Facility - 62889

Updated projects (14):

409 MW - operation - florida - Manatee Solar Energy Center - 60014
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
40 MW - operation - georgia - Cool Springs Solar (Hybrid) - 63721
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
35 MW - operation - california - Desert Harvest II LLC - 64103
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
11 MW - operation - california - Silverstrand Grid Energy Storage System - 63735
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete

100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
  date: 2021-06 -> 2022-01 delayed by 7 months
20 MW - operation - new york - Willis Battery Storage - 63238
  date: 2021-06 -> 2021-09 delayed by 3 months
10 MW - operation - california - Henrietta D Energy Storage LLC - 60641
  date: 2021-03 -> 2021-04 delayed by 1 month
10 MW - cancelled - california - Goleta Grid Resiliency - 63736
  date: 2021-06 -> 2022-12 delayed by 18 months

200 MW - operation - california - Diablo Energy Storage - 62175
  mw: 250 -> 200
115 MW - operation - california - Blythe Solar II, LLC - 60092
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
100 MW - cancelled - texas - TX17 Nickel Prairie Storage - 63880
  entity id: 63552 -> 63289
100 MW - operation - texas - Madero Grid - 63757
  mw: 200 -> 100
100 MW - cancelled - texas - TX18 Cottage Meadow Storage - 63879
  entity id: 63552 -> 63289
30 MW - operation - oregon - Wheatridge Hybrid - 62745
  entity name: Wheatridge Wind Energy, LLC -> Wheatridge Wind Holdings, LLC

2020-12

New projects (4):
120 MW - operation - texas - Azure Sky Wind Project, LLC Hybrid - 64164
100 MW - cancelled - texas - Forest Grove - Dodd - 64131
50 MW - operation - california - Maverick Solar 6, LLC - 64105
35 MW - operation - california - Desert Harvest II LLC - 64103

Updated projects (6):

182 MW - operation - california - Elkhorn Battery Energy Storage System - 62564
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
  date: 2021-03 -> 2021-07 delayed by 4 months
25 MW - operation - massachusetts - Outer Cape Community Battery - 62604
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
10 MW - operation - california - Henrietta D Energy Storage LLC - 60641
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete

20 MW - operation - california - Johanna Energy Center, LLC - 63843
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
  date: 2020-10 -> 2021-01 delayed by 3 months
10 MW - cancelled - california - Goleta Grid Resiliency - 63736
  date: 2021-03 -> 2021-06 delayed by 3 months

100 MW - operation - nevada - Dry Lake Solar Energy Center - 63933
  entity id: 63603 -> 13407
  entity name: Nevada Power Company DBA NV Energy -> Nevada Power Co

2020-11

New projects (4):
260 MW - operation - texas - DeCordova Steam Electric Station - 8063
100 MW - operation - texas - Ignacio Grid Energy Storage System - 64089
20 MW - planning - hawaii - Kahana Solar, LLC - 64095
15 MW - planning - hawaii - Barbers Point Solar, LLC - 64094

Disappeared projects (1):
10 MW - construction - california - Painter Energy Storage - 62729

Updated projects (8):

115 MW - operation - california - Blythe Solar II, LLC - 60092
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
115 MW - operation - california - Blythe Solar III, LLC Hybrid - 60094
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
100 MW - operation - california - Saticoy - 63891
  status: planning -> construction πŸ—οΈ
  status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
46 MW - operation - alaska - Soldotna - 57206
  status: planning -> construction πŸ—οΈ
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete

100 MW - operation - texas - Madero Grid - 63757
  date: 2021-09 -> 2021-12 delayed by 3 months
14 MW - operation - hawaii - AES Kekaha Solar, LLC Hybrid - 63280
  date: 2020-09 -> 2021-04 delayed by 7 months
10 MW - cancelled - california - Chevron - Lost Hills Hybrid - 63545
  date: 2021-08 -> 2021-09 delayed by 1 month

100 MW - operation - california - Luna Storage - 63685
  status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (L) Regulatory approvals pending. Not under construction

2020-10

New projects (2):
60 MW - operation - california - Coso Battery Storage - 63943
11 MW - operation - florida - Trenton - 63995

Updated projects (9):

100 MW - operation - texas - Chisholm Grid Energy Storage System - 63737
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
20 MW - operation - california - Hecate Energy Johanna Facility - 62889
  status: planning -> construction πŸ—οΈ
  status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
20 MW - operation - california - Stanton Energy Reliability Center Hybrid - 60698
  status: planning -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (OT) Other -> operation
  date: 2020-09 -> 2020-08 accelerated by 1 month
20 MW - operation - california - Stanton Energy Reliability Center Hybrid - 60698
  status: planning -> operation 🍾 πŸŽ‰ 🍸
  status_verbose: (OT) Other -> operation
  date: 2020-09 -> 2020-08 accelerated by 1 month

139 MW - operation - california - Slate Hybrid - 63727
  date: 2020-12 -> 2021-10 delayed by 10 months
100 MW - operation - texas - Madero Grid - 63757
  date: 2021-07 -> 2021-09 delayed by 2 months
30 MW - operation - california - Top Gun Energy Storage - 61366
  date: 2021-01 -> 2021-03 delayed by 2 months
10 MW - operation - california - Henrietta D Energy Storage LLC - 60641
  date: 2021-01 -> 2021-03 delayed by 2 months

750 MW - operation - california - Dynegy Moss Landing Power Plant Hybrid - 260
  status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete

2020-09

New projects (81):
409 MW - operation - florida - Manatee Solar Energy Center - 60014
750 MW - operation - california - Dynegy Moss Landing Power Plant Hybrid - 260
139 MW - operation - california - Slate Hybrid - 63727
300 MW - planning - arizona - Atlas - 63798
380 MW - operation - nevada - Gemini Solar - 63352
250 MW - operation - california - Gateway Energy Storage System - 63834
200 MW - operation - california - Diablo Energy Storage - 62175
230 MW - operation - california - McCoy Solar Energy Project Hybrid - 58462
100 MW - operation - texas - Madero Grid - 63757
169 MW - planning - new york - NY2 Battery - 63584
100 MW - cancelled - montana - Haymaker Hybrid - 63878
252 MW - planning - oklahoma - Skeleton Creek Energy Center Hybrid - 62494
182 MW - operation - california - Elkhorn Battery Energy Storage System - 62564
150 MW - construction - california - Eland Solar & Storage Center, Phase 1 Hybrid - 61168
150 MW - construction - massachusetts - Cranberry Point Energy Storage - 62844
150 MW - planning - california - Eland Solar & Storage Center, Phase 2 Hybrid - 61169
300 MW - planning - nevada - Southern Bighorn Solar Hybrid - 63113
316 MW - cancelled - new york - Ravenswood - 2500
125 MW - operation - colorado - Neptune Energy Center Hybrid - 63731
115 MW - operation - california - Blythe Solar II, LLC - 60092
115 MW - operation - california - Blythe Solar III, LLC Hybrid - 60094
100 MW - operation - california - AES ES ALAMITOS, LLC - 61204
100 MW - operation - california - Saticoy - 63891
100 MW - operation - texas - Chisholm Grid Energy Storage System - 63737
100 MW - operation - california - Luna Storage - 63685
100 MW - cancelled - texas - TX17 Nickel Prairie Storage - 63880
100 MW - cancelled - texas - TX18 Cottage Meadow Storage - 63879
100 MW - operation - colorado - Thunder Wolf Energy Center Hybrid - 63776
100 MW - operation - nevada - Dry Lake Solar Energy Center - 63933
316 MW - cancelled - new york - Ravenswood - 2500
90 MW - operation - nevada - Townsite Solar Project Hybrid - 60654
316 MW - cancelled - new york - Ravenswood - 2500
77 MW - operation - texas - Azure Sky Solar - 63905
75 MW - operation - nevada - Arrow Canyon Solar Hybrid - 62248
60 MW - operation - california - Cal Flats BESS - 63930
60 MW - cancelled - hawaii - Kupehau - 63799
52 MW - construction - hawaii - Ho'Ohana Solar 1 - 63723
50 MW - operation - texas - Lily Solar Hybrid - 63892
50 MW - planning - texas - TREX US Red Holly - 63202
50 MW - operation - arizona - El Sol BESS - 62964
125 MW - planning - california - Aratina Solar Center 1 Hybrid - 61167
46 MW - operation - alaska - Soldotna - 57206
40 MW - operation - texas - 2W Permian Solar Project Hybrid - 63255
40 MW - operation - california - Fallbrook Energy Storage - 61365
40 MW - operation - georgia - Cool Springs Solar (Hybrid) - 63721
40 MW - operation - georgia - Hickory Park Solar Hybrid - 63522
150 MW - operation - new mexico - Arroyo Solar Energy Storage Hybrid - 63172
40 MW - planning - california - EDPR CA Solar Park VI LLC (CA) Hybrid - 62892
38 MW - operation - arizona - Foothills Solar Plant Hybrid - 57997
36 MW - operation - arizona - Gila Bend Hybrid - 59020
43 MW - planning - california - Dynegy Oakland Power Plant - 6211
30 MW - operation - california - Top Gun Energy Storage - 61366
30 MW - operation - oregon - Wheatridge Hybrid - 62745
30 MW - operation - hawaii - AES Waikoloa Solar Hybrid - 63900
30 MW - construction - hawaii - Hale Kuawehi Solar Hybrid - 62529
25 MW - operation - massachusetts - Outer Cape Community Battery - 62604
25 MW - construction - california - Cascade Energy Storage, LLC - 61801
20 MW - operation - california - Johanna Energy Center, LLC - 63843
20 MW - operation - california - Hecate Energy Johanna Facility - 62889
20 MW - operation - new york - Willis Battery Storage - 63238
20 MW - cancelled - california - Renz Energy Storage - 63529
17 MW - operation - arizona - Cotton Center Solar Hybrid - 57561
17 MW - operation - arizona - Paloma Solar Hybrid - 57562
16 MW - operation - arizona - Hyder Solar Hybrid - 57563
15 MW - cancelled - hawaii - Paeahu Solar Hybrid - 62534
14 MW - operation - hawaii - AES Kekaha Solar, LLC Hybrid - 63280
14 MW - operation - arizona - Hyder II Hybrid - 58383
12 MW - operation - new mexico - Taos Mesa Energy Facility Hybrid - 63728
11 MW - operation - california - Silverstrand Grid Energy Storage System - 63735
22 MW - cancelled - california - Camino Solar - 63508
10 MW - operation - oklahoma - Rush Springs Energy Storage (BA) - 63458
20 MW - operation - california - Stanton Energy Reliability Center Hybrid - 60698
20 MW - operation - california - Stanton Energy Reliability Center Hybrid - 60698
10 MW - operation - california - Vallecito - 62801
10 MW - operation - california - Henrietta D Energy Storage LLC - 60641
10 MW - cancelled - california - Goleta Grid Resiliency - 63736
10 MW - construction - california - Painter Energy Storage - 62729
10 MW - cancelled - california - Chevron - Lost Hills Hybrid - 63545
10 MW - cancelled - arizona - Desert Star Hybrid - 62965
10 MW - operation - arkansas - Searcy Solar Hybrid - 62617
10 MW - construction - california - Sierra Energy Storage, LLC - 61803

Updated projects (0):