Wolf Tank Storage πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2023-06 |
Construction start |
|
Operation start |
2023-07 |
Estimated start |
2023-06 |
Construction time |
|
Capacity in MWh
300
π This is an estimate
Maximum Power in MW
150
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Wolf Tank Storage LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.58101561449517+-95.448185670785
Coordinates
33.58101561449517, -95.448185670785
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1028 / 66616
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2023-06
report):
Plant Name / State
Wolf Tank Storage / TX
go live / power
2023-07 / 150MW
status / status verbose
operation / operation
Plant id / generator id
66616 / 1
Entity name / entity id
Wolf Tank Storage LLC / 65642
Changes:
2023-09
status: construction -> operation πΎ π πΈ
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2023-08
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
date: 2023-06 -> 2023-07 delayed by
1 month
2023-07
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2023-05 -> 2023-06 delayed by
1 month