Black Mesa BESS πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / idaho /
Dates
First heard 2023-03
Construction start
Operation start
Estimated start 2024-02
Construction time
Capacity in MWh
80
πŸ“ This is an estimate
Maximum Power in MW
40
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Idaho Power Co /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:44.361601404211235+-112.97622197218186
Coordinates
44.361601404211235, -112.97622197218186
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
969 / 66326

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2023-03 report):

Plant Name / State
Black Mesa BESS / ID
go live / power
2024-02 / 40MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
66326 / 1
Entity name / entity id
Idaho Power Co / 9191
Changes:
2024-01
date: 2023-12 -> 2024-02 delayed by 2 months
2023-12
date: 2023-11 -> 2023-12 delayed by 1 month
2023-11
date: 2023-10 -> 2023-11 delayed by 1 month
2023-10
date: 2023-09 -> 2023-10 delayed by 1 month
2023-04
date: 2023-06 -> 2023-09 delayed by 3 months