Danish Fields Storage πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2023-09 |
Construction start |
|
Operation start |
|
Estimated start |
2025-01 |
Construction time |
|
Capacity in MWh
300
π This is an estimate
Maximum Power in MW
150
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Danish Fields Storage, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.23340888821952+-95.20174605730502
Coordinates
33.23340888821952, -95.20174605730502
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1056 / 66916
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2025-01
report (Project first appeared in the
2023-09
report):
Plant Name / State
Danish Fields Storage / TX
go live / power
2025-01 / 150MW
status / status verbose
construction / (TS) Construction complete, but not yet in commercial operation
Plant id / generator id
66916 / DANST
Entity name / entity id
Danish Fields Storage, LLC / 65833
Changes:
2025-01
date: 2024-12 -> 2025-01 delayed by
1 month
2024-12
date: 2024-11 -> 2024-12 delayed by
1 month
2024-10
date: 2024-09 -> 2024-11 delayed by
2 months
2024-09
date: 2024-08 -> 2024-09 delayed by
1 month
2024-08
date: 2024-07 -> 2024-08 delayed by
1 month
2024-06
date: 2024-05 -> 2024-07 delayed by
2 months
2024-04
date: 2024-03 -> 2024-05 delayed by
2 months
2024-03
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2024-02
date: 2024-02 -> 2024-03 delayed by
1 month
2024-01
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete