Ortega Grid, LLC πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2022-06 |
Construction start |
2023-05 |
Operation start |
|
Estimated start |
2025-03 |
Construction time |
|
Capacity in MWh
40
π This is an estimate
Maximum Power in MW
20
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Ortega Grid, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.10969828623625+-121.3399933736844
Coordinates
41.10969828623625, -121.3399933736844
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
711 / 65656
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2022-06
report):
Plant Name / State
Ortega Grid, LLC / CA
go live / power
2025-03 / 20MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
65656 / HEORG
Entity name / entity id
Ortega Grid, LLC / 64935
Changes:
2024-07
date: 2024-05 -> 2025-03 delayed by
10 months
2024-03
date: 2024-04 -> 2024-05 delayed by
1 month
2024-01
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2024-01 -> 2024-04 delayed by
3 months
2023-12
date: 2023-11 -> 2024-01 delayed by
2 months
2023-08
date: 2023-08 -> 2023-11 delayed by
3 months
2023-06
date: 2023-06 -> 2023-08 delayed by
2 months
2023-05
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2023-02
date: 2023-03 -> 2023-06 delayed by
3 months
2022-09
status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction