Connolly BESS πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2024-09 |
Construction start |
|
Operation start |
2024-11 |
Estimated start |
2024-11 |
Construction time |
|
Capacity in MWh
250
π This is an estimate
Maximum Power in MW
125
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ BT Connolly Storage, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.47991655110087+-95.2378412522475
Coordinates
33.47991655110087, -95.2378412522475
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1602 / 67861
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2025-01
report (Project first appeared in the
2024-09
report):
Plant Name / State
Connolly BESS / TX
go live / power
2024-11 / 125MW
status / status verbose
operation / operation
Plant id / generator id
67861 / CNLY
Entity name / entity id
BT Connolly Storage, LLC / 66432
Changes:
2025-01
status: construction -> operation πΎ π πΈ
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2024-12
date: 2024-10 -> 2024-11 delayed by
1 month
2024-10
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
date: 2024-08 -> 2024-10 delayed by
2 months