Diablo Energy Storage πŸ“πŸ“ŠπŸ‘€

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california / Pittsburg
Dates
First heard 2020-09
Construction start 2021-05
Operation start 2022-04
Estimated start
Construction time 11 months -> 72 MWh/m
Capacity in MWh
800
Maximum Power in MW
200
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
LS Power / PG & E / Diablo Energy Storage, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:38.015262+-121.846146
Coordinates
38.015262, -121.846146
πŸ“ Coords not known
Notes

Project website
Sources
https://www.energy-storage.news/direct-energy-business-to-use-some-of-worlds-biggest-battery-projects-to-serve-california-customers/
https://www.lspower.com/project-map/
https://www.tdworld.com/distributed-energy-resources/energy-storage/article/21131879/pge-poised-to-expand-battery-energy-storage-capacity-by-more-than-420-mw
Internal / External id
47 / 62175

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2023-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Diablo Energy Storage / CA
go live / power
2022-04 / 200MW
status / status verbose
operation / operation
Plant id / generator id
62175 / DIBLO
Entity name / entity id
Diablo Energy Storage, LLC / 61684
Changes:
2022-06
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2022-05
date: 2022-03 -> 2022-04 delayed by 1 month
2022-04
date: 2022-02 -> 2022-03 delayed by 1 month
2022-02
date: 2022-01 -> 2022-02 delayed by 1 month
2022-01
date: 2021-11 -> 2022-01 delayed by 2 months
2021-12
date: 2021-10 -> 2021-11 delayed by 1 month
2021-11
date: 2021-09 -> 2021-10 delayed by 1 month
2021-09
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2021-08 -> 2021-09 delayed by 1 month
2021-05
status: planning -> construction πŸ—οΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
2021-01
mw: 250 -> 200