Prairie Center Energy LLC πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / colorado /
Dates
First heard |
2024-11 |
Construction start |
2025-01 |
Operation start |
|
Estimated start |
2024-12 |
Construction time |
|
Capacity in MWh
66
π This is an estimate
Maximum Power in MW
33
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Whetstone Power Operations LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.82188597668374+-102.85421674903644
Coordinates
40.82188597668374, -102.85421674903644
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1547 / 68058
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2025-01
report (Project first appeared in the
2024-11
report):
Plant Name / State
Prairie Center Energy LLC / CO
go live / power
2024-12 / 33MW
status / status verbose
construction / (TS) Construction complete, but not yet in commercial operation
Plant id / generator id
68058 / PCEBS
Entity name / entity id
Whetstone Power Operations LLC / 66569
Changes:
2025-01
status: planning -> construction ποΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (TS) Construction complete, but not yet in commercial operation
date: 2024-11 -> 2024-12 delayed by
1 month