Southern Bighorn Solar Hybrid πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / nevada /
Dates
First heard 2020-09
Construction start
Operation start
Estimated start 2027-05
Construction time
Capacity in MWh
600
πŸ“ This is an estimate
Maximum Power in MW
300
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ 300MS 8me LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.70034529690874+-115.02003633894475
Coordinates
41.70034529690874, -115.02003633894475
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
227 / 63113

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Southern Bighorn Solar Hybrid / NV
go live / power
2027-05 / 300MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
63113 / BESS
Entity name / entity id
300MS 8me LLC / 62910
Changes:
2024-02
date: 2026-05 -> 2027-05 delayed by 12 months
mw: 135 -> 300
2023-06
date: 2024-04 -> 2026-05 delayed by 25 months
2022-01
date: 2023-09 -> 2024-04 delayed by 7 months