South Portland ESS, LLC πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / maine /
Dates
First heard 2021-06
Construction start
Operation start
Estimated start 2024-12
Construction time
Capacity in MWh
20
πŸ“ This is an estimate
Maximum Power in MW
10
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ South Portland ESS, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:45.15652305365124+-69.2043404959897
Coordinates
45.15652305365124, -69.2043404959897
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
221 / 64616

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2021-06 report):

Plant Name / State
South Portland ESS, LLC / ME
go live / power
2024-12 / 10MW
status / status verbose
planning / (T) Regulatory approvals received. Not under construction
Plant id / generator id
64616 / 1
Entity name / entity id
South Portland ESS, LLC / 64233
Changes:
2023-11
date: 2024-02 -> 2024-12 delayed by 10 months
2023-09
date: 2023-12 -> 2024-02 delayed by 2 months
2022-08
date: 2023-06 -> 2023-12 delayed by 6 months
2022-03
date: 2023-01 -> 2023-06 delayed by 5 months