Fort Duncan BESS πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2024-08 |
Construction start |
2024-09 |
Operation start |
|
Estimated start |
2025-06 |
Construction time |
|
Capacity in MWh
204
π This is an estimate
Maximum Power in MW
102
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Fort Duncan BESS, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.57864261713374+-95.36395692885304
Coordinates
33.57864261713374, -95.36395692885304
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1607 / 67752
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2025-01
report (Project first appeared in the
2024-08
report):
Plant Name / State
Fort Duncan BESS / TX
go live / power
2025-06 / 102MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
67752 / FTDUN
Entity name / entity id
Fort Duncan BESS, LLC / 66359
Changes:
2024-09
status: planning -> construction ποΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete