Blythe Solar III, LLC Hybrid ππ€
Status
operation
Country / State / Closest City
πΊπΈ usa / california / Riverside County
Dates
First heard |
2020-09 |
Construction start |
2020-11 |
Operation start |
2021-05 |
Estimated start |
|
Construction time |
6 months -> 76 MWh/m
|
Capacity in MWh
460
Maximum Power in MW
115
Manufacturer
Samsung
Type / Number of Packs / Cells
/ / Samsung
Customer / Owner / Developer
Southern California Edison / Blythe Solar III, LLC /
Use case
solar
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.673021+-114.754474
Coordinates
33.673021, -114.754474
β
Coords are exact (+/- 50m)
Notes
part of 523 MW / 2092 MWh of storage at Blythe-McCoy Solar & Storage Complex, TODO: source that samsung supplies batteries
Project website
Sources
https://pv-magazine-usa.com/2020/05/02/southern-california-edison-wants-huge-770-mw-battery-storage-procurement-online-fast/
Internal / External id
65 / 60094
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2022-02
report (Project first appeared in the
2020-09
report):
Plant Name / State
Blythe Solar III, LLC Hybrid / CA
go live / power
2021-05 / 115MW
status / status verbose
operation / operation
Plant id / generator id
60094 / BLST3
Entity name / entity id
Blythe Solar III, LLC / 59844
Changes:
2021-07
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2021-03
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2020-11
status: planning -> construction ποΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete