Willis Battery Storage πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / new york /
Dates
First heard |
2020-09 |
Construction start |
2021-06 |
Operation start |
2023-07 |
Estimated start |
2022-03 |
Construction time |
25 months -> 1 MWh/m
|
Capacity in MWh
40
π This is an estimate
Maximum Power in MW
20
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ New York Power Authority /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:42.482006999999996+-75.50354
Coordinates
42.482006999999996, -75.50354
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
235 / 63238
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2020-09
report):
Plant Name / State
Willis Battery Storage / NY
go live / power
2023-07 / 20MW
status / status verbose
operation / operation
Plant id / generator id
63238 / WB1
Entity name / entity id
New York Power Authority / 15296
Changes:
2023-09
status: construction -> operation πΎ π πΈ
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
date: 2023-09 -> 2023-07 accelerated by
2 months
2023-08
date: 2023-06 -> 2023-09 delayed by
3 months
2023-07
date: 2023-05 -> 2023-06 delayed by
1 month
2023-05
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
date: 2023-03 -> 2023-05 delayed by
2 months
2023-02
date: 2023-02 -> 2023-03 delayed by
1 month
2023-01
date: 2023-01 -> 2023-02 delayed by
1 month
2022-12
date: 2022-12 -> 2023-01 delayed by
1 month
2022-11
date: 2022-11 -> 2022-12 delayed by
1 month
2022-09
date: 2022-09 -> 2022-11 delayed by
2 months
2022-06
date: 2022-08 -> 2022-09 delayed by
1 month
2022-03
date: 2022-06 -> 2022-08 delayed by
2 months
2022-02
date: 2022-03 -> 2022-06 delayed by
3 months
2021-07
date: 2021-09 -> 2022-03 delayed by
6 months
2021-06
status: planning -> construction ποΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
2021-01
date: 2021-06 -> 2021-09 delayed by
3 months