Flint πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / ohio /
Dates
First heard |
2025-06 |
Construction start |
|
Operation start |
|
Estimated start |
2027-07 |
Construction time |
|
Capacity in MWh
400
π This is an estimate
Maximum Power in MW
200
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Flint /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.15070000365377+-80.98233613582602
Coordinates
41.15070000365377, -80.98233613582602
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1777 / 68911
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2025-07
report (Project first appeared in the
2025-06
report):
Plant Name / State
Flint / OH
go live / power
2027-07 / 200MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
68911 / 27288
Entity name / entity id
Flint / 67157