Sun Bear πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / colorado /
Dates
First heard 2024-12
Construction start
Operation start
Estimated start 2028-07
Construction time
Capacity in MWh
300
πŸ“ This is an estimate
Maximum Power in MW
150
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ MS1 /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.834199981454574+-102.78218660280749
Coordinates
40.834199981454574, -102.78218660280749
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1546 / 68261

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-01 report (Project first appeared in the 2024-12 report):

Plant Name / State
Sun Bear / CO
go live / power
2028-07 / 150MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
68261 / SNBR2
Entity name / entity id
MS1 / 66687
Changes: