Cathode (Hinson) BESS πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2022-04
Construction start 2022-08
Operation start
Estimated start 2024-03
Construction time
Capacity in MWh
400
πŸ“ This is an estimate
Maximum Power in MW
200
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Southern California Edison Co /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.17891809297625+-121.12695671403428
Coordinates
41.17891809297625, -121.12695671403428
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
681 / 65457

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
This project has 2 generator ids under the same plant id
Info from the 2024-02 report (Project first appeared in the 2022-04 report):

Plant Name / State
Cathode (Hinson) BESS / CA
go live / power
2024-03 / 100MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
65457 / CATH1
Entity name / entity id
Southern California Edison Co / 17609
Changes:
2024-01
date: 2024-01 -> 2024-03 delayed by 2 months
2023-11
date: 2023-11 -> 2024-01 delayed by 2 months
2023-10
date: 2023-10 -> 2023-11 delayed by 1 month
2023-09
date: 2023-09 -> 2023-10 delayed by 1 month
2023-07
date: 2023-07 -> 2023-09 delayed by 2 months
2023-05
date: 2023-06 -> 2023-07 delayed by 1 month
2023-04
date: 2023-05 -> 2023-06 delayed by 1 month
2023-02
date: 2023-04 -> 2023-05 delayed by 1 month
2022-12
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-11
date: 2022-11 -> 2023-04 delayed by 5 months
2022-09
date: 2022-10 -> 2022-11 delayed by 1 month
2022-08
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2022-07
date: 2022-08 -> 2022-10 delayed by 2 months


Info from the 2024-02 report (Project first appeared in the 2022-04 report):

Plant Name / State
Cathode (Hinson) BESS / CA
go live / power
2024-03 / 100MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
65457 / CATH2
Entity name / entity id
Southern California Edison Co / 17609
Changes:
2024-01
date: 2024-01 -> 2024-03 delayed by 2 months
2023-11
date: 2023-11 -> 2024-01 delayed by 2 months
2023-10
date: 2023-10 -> 2023-11 delayed by 1 month
2023-09
date: 2023-09 -> 2023-10 delayed by 1 month
2023-07
date: 2023-07 -> 2023-09 delayed by 2 months
2023-05
date: 2023-06 -> 2023-07 delayed by 1 month
2023-04
date: 2023-05 -> 2023-06 delayed by 1 month
2023-02
date: 2023-04 -> 2023-05 delayed by 1 month
2022-12
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-11
date: 2022-11 -> 2023-04 delayed by 5 months
2022-09
date: 2022-10 -> 2022-11 delayed by 1 month
2022-08
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2022-07
date: 2022-08 -> 2022-10 delayed by 2 months