Tortolas πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2022-04
Construction start 2023-03
Operation start
Estimated start 2024-04
Construction time
Capacity in MWh
100
πŸ“ This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Broad Reach Power /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.56468208398623+-95.61391623283366
Coordinates
33.56468208398623, -95.61391623283366
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
689 / 65493

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2022-04 report):

Plant Name / State
Tortolas / TX
go live / power
2024-04 / 50MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
65493 / TORTO
Entity name / entity id
Broad Reach Power / 63883
Changes:
2024-01
date: 2024-03 -> 2024-04 delayed by 1 month
2023-10
date: 2023-12 -> 2024-03 delayed by 3 months
2023-04
date: 2023-09 -> 2023-12 delayed by 3 months
2023-03
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
date: 2023-06 -> 2023-09 delayed by 3 months