Beaver Creek I πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / montana /
Dates
First heard 2021-11
Construction start
Operation start
Estimated start 2025-09
Construction time
Capacity in MWh
60
πŸ“ This is an estimate
Maximum Power in MW
30
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Beaver Creek Wind I, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:48.48858627036728+-105.49814730955251
Coordinates
48.48858627036728, -105.49814730955251
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
558 / 65019

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2021-11 report):

Plant Name / State
Beaver Creek I / MT
go live / power
2025-09 / 30MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
65019 / BCW1B
Entity name / entity id
Beaver Creek Wind I, LLC / 64434
Changes:
2023-03
date: 2024-12 -> 2025-09 delayed by 9 months
2022-03
date: 2023-06 -> 2024-12 delayed by 18 months