Ranchland Wind Storage πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2021-05
Construction start 2021-12
Operation start 2024-04
Estimated start 2022-03
Construction time 28 months -> 5 MWh/m
Capacity in MWh
146
πŸ“ This is an estimate
Maximum Power in MW
73
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Ranchland Wind Storage, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.454054+-95.373438
Coordinates
33.454054, -95.373438
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
250 / 64545

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2021-05 report):

Plant Name / State
Ranchland Wind Storage / TX
go live / power
2024-04 / 73MW
status / status verbose
operation / operation
Plant id / generator id
64545 / BA
Entity name / entity id
Ranchland Wind Storage, LLC / 64179
Changes:
2024-06
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
date: 2024-05 -> 2024-04 accelerated by 1 month
2024-05
date: 2024-03 -> 2024-05 delayed by 2 months
2024-03
date: 2024-01 -> 2024-03 delayed by 2 months
2024-02
date: 2023-12 -> 2024-01 delayed by 1 month
2023-12
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
date: 2023-10 -> 2023-12 delayed by 2 months
2023-11
date: 2023-09 -> 2023-10 delayed by 1 month
2023-10
date: 2023-08 -> 2023-09 delayed by 1 month
2023-08
date: 2023-06 -> 2023-08 delayed by 2 months
2023-06
date: 2023-05 -> 2023-06 delayed by 1 month
2023-03
date: 2023-01 -> 2023-05 delayed by 4 months
2022-12
date: 2022-11 -> 2023-01 delayed by 2 months
2022-10
date: 2022-09 -> 2022-11 delayed by 2 months
2022-09
date: 2022-07 -> 2022-09 delayed by 2 months
2022-06
date: 2022-05 -> 2022-07 delayed by 2 months
2022-05
date: 2022-03 -> 2022-05 delayed by 2 months
2021-12
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete