Hudson - High Desert Hybrid πππ 
Status 
operation 
Country / State / Closest City 
πΊπΈ usa / california / 
Dates
    
        
            
                | First heard | 
                2021-06 | 
            
            
                | Construction start | 
                2021-08 | 
            
            
                | Operation start | 
                2021-12 | 
            
            
                | Estimated start | 
                2021-09 | 
            
            
            
                | Construction time | 
                
                    
                    4 months -> 25 MWh/m
                    
                 | 
            
        
     
 
Capacity in MWh 
    100
     
π  This is an estimate 
Maximum Power in MW 
50
Manufacturer 
 
Type / Number of Packs / Cells 
 /  / 
Customer / Owner / Developer
 / Goldman Sachs Renewable Power Group /  
Use case 
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.122677+-121.140049 
Coordinates 
    41.122677, -121.140049 
    
 π Coords are a guess. Only the state is known
Notes 
    
     
     
Project website 
  
 Sources 
     
 Internal / External id 
    180 / 64624
    
 U.S. EIA data 
The government data source for this battery is the U.S. Energy Information Administration (EIA)
    https://www.eia.gov/electricity/monthly/
Info from the 
2022-02 report (Project first appeared in the 
2021-06 report):
Plant Name / State
Hudson - High Desert Hybrid / CA
go live / power 
2021-12 / 50MW
status / status verbose
operation / operation 
Plant id / generator id 
64624 / BESS1
Entity name / entity id 
Goldman Sachs Renewable Power Group / 61944
Changes:
    2022-02
    
        status: construction -> operation πΎ π πΈ
    
        status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation 
     
    
2022-01
    
        date: 2021-11 -> 2021-12 delayed by 
1 month
     
    
2021-12
    
        date: 2021-10 -> 2021-11 delayed by 
1 month
     
    
2021-11
    
        date: 2021-09 -> 2021-10 delayed by 
1 month
     
    
2021-10
    
        status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation 
     
    
2021-09
    
        status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete 
     
    
2021-08
    
        status: planning -> construction ποΈ
    
        status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete