Hudson - High Desert Hybrid πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2021-06 |
Construction start |
2021-08 |
Operation start |
2021-12 |
Estimated start |
2021-09 |
Construction time |
4 months -> 25 MWh/m
|
Capacity in MWh
100
π This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Goldman Sachs Renewable Power Group /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.122677+-121.140049
Coordinates
41.122677, -121.140049
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
180 / 64624
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2022-02
report (Project first appeared in the
2021-06
report):
Plant Name / State
Hudson - High Desert Hybrid / CA
go live / power
2021-12 / 50MW
status / status verbose
operation / operation
Plant id / generator id
64624 / BESS1
Entity name / entity id
Goldman Sachs Renewable Power Group / 61944
Changes:
2022-02
status: construction -> operation πΎ π πΈ
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2022-01
date: 2021-11 -> 2021-12 delayed by
1 month
2021-12
date: 2021-10 -> 2021-11 delayed by
1 month
2021-11
date: 2021-09 -> 2021-10 delayed by
1 month
2021-10
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2021-09
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2021-08
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete