Hudson - High Desert Hybrid πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2021-06
Construction start 2021-08
Operation start 2021-12
Estimated start 2021-09
Construction time 4 months -> 25 MWh/m
Capacity in MWh
100
πŸ“ This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Goldman Sachs Renewable Power Group /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.122677+-121.140049
Coordinates
41.122677, -121.140049
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
180 / 64624

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2022-02 report (Project first appeared in the 2021-06 report):

Plant Name / State
Hudson - High Desert Hybrid / CA
go live / power
2021-12 / 50MW
status / status verbose
operation / operation
Plant id / generator id
64624 / BESS1
Entity name / entity id
Goldman Sachs Renewable Power Group / 61944
Changes:
2022-02
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2022-01
date: 2021-11 -> 2021-12 delayed by 1 month
2021-12
date: 2021-10 -> 2021-11 delayed by 1 month
2021-11
date: 2021-09 -> 2021-10 delayed by 1 month
2021-10
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2021-09
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2021-08
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete