ORCHARD Solar Generation and BESS πŸ“β€οΈπŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / arizona /
Dates
First heard 2025-01
Construction start
Operation start
Estimated start 2027-04
Construction time
Capacity in MWh
1000
πŸ“ This is an estimate
Maximum Power in MW
500
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Yuma bn, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.339711680458976+-109.69432598932751
Coordinates
36.339711680458976, -109.69432598932751
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1638 / 68328

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-01 report (Project first appeared in the 2025-01 report):

Plant Name / State
ORCHARD Solar Generation and BESS / AZ
go live / power
2027-04 / 500MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
68328 / ORCH2
Entity name / entity id
Yuma bn, LLC / 66715
Changes: