Acid BESS πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2023-07 |
Construction start |
2024-02 |
Operation start |
|
Estimated start |
2024-12 |
Construction time |
|
Capacity in MWh
194
π This is an estimate
Maximum Power in MW
97
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Malaga BESS LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.992677+-121.300049
Coordinates
40.992677, -121.300049
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1015 / 66659
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2023-07
report):
Plant Name / State
Acid BESS / CA
go live / power
2024-12 / 97MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
66659 / MAL
Entity name / entity id
Malaga BESS LLC / 65678
Changes:
2024-02
status: planning -> construction ποΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
2023-08
plant name: Malaga BESS -> Acid BESS