Humidor Storage I πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2022-07
Construction start
Operation start
Estimated start 2025-06
Construction time
Capacity in MWh
600
πŸ“ This is an estimate
Maximum Power in MW
300
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Hecate Grid Humidor Storage 1 LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.867793853632904+-121.38286555449248
Coordinates
40.867793853632904, -121.38286555449248
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
694 / 65703

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2022-07 report):

Plant Name / State
Humidor Storage I / CA
go live / power
2025-06 / 300MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
65703 / HEHUM
Entity name / entity id
Hecate Grid Humidor Storage 1 LLC / 64970
Changes:
2023-03
date: 2024-01 -> 2025-06 delayed by 17 months
2023-01
date: 2023-11 -> 2024-01 delayed by 2 months