Dry Bridge Storage πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / virginia /
Dates
First heard 2021-11
Construction start 2022-10
Operation start 2023-11
Estimated start
Construction time 13 months -> 3 MWh/m
Capacity in MWh
40
πŸ“ This is an estimate
Maximum Power in MW
20
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Dominion Energy Inc. /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:38.390223+-77.80875
Coordinates
38.390223, -77.80875
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
565 / 65044

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2021-11 report):

Plant Name / State
Dry Bridge Storage / VA
go live / power
2023-11 / 20MW
status / status verbose
operation / operation
Plant id / generator id
65044 / DBES
Entity name / entity id
Dominion Energy Inc. / 5248
Changes:
2024-01
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
date: 2023-12 -> 2023-11 accelerated by 1 month
2023-12
status_verbose: (V) Under construction, more than 50 percent complete -> (U) Under construction, less than or equal to 50 percent complete
date: 2023-10 -> 2023-12 delayed by 2 months
2023-11
date: 2023-09 -> 2023-10 delayed by 1 month
2023-05
date: 2023-04 -> 2023-09 delayed by 5 months
2023-02
entity name: Dominion Energy Inc -> Dominion Energy Inc.
date: 2022-12 -> 2023-04 delayed by 4 months
2022-12
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2022-10 -> 2022-12 delayed by 2 months
2022-10
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2022-02
date: 2022-12 -> 2022-10 accelerated by 2 months