Archie Horne πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / north carolina /
Dates
First heard 2023-12
Construction start
Operation start
Estimated start 2024-08
Construction time
Capacity in MWh
20
πŸ“ This is an estimate
Maximum Power in MW
10
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ North Carolina El Member Corp /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.5619040160412+-76.800194785395
Coordinates
36.5619040160412, -76.800194785395
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1184 / 67040

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-06 report (Project first appeared in the 2023-12 report):

Plant Name / State
Archie Horne / NC
go live / power
2024-08 / 10MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
67040 / BAT1
Entity name / entity id
North Carolina El Member Corp / 13683
Changes: