Peeler Solar, LLC πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2023-05 |
Construction start |
|
Operation start |
|
Estimated start |
2026-12 |
Construction time |
|
Capacity in MWh
100
π This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Peeler Solar, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.33724557612627+-94.91393863684043
Coordinates
33.33724557612627, -94.91393863684043
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
999 / 65932
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2023-05
report):
Plant Name / State
Peeler Solar, LLC / TX
go live / power
2026-12 / 50MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
65932 / PEEL2
Entity name / entity id
Peeler Solar, LLC / 65105
Changes:
2024-04
date: 2025-10 -> 2026-12 delayed by
14 months
mw: 100 -> 50