Chiquito Grid, LLC πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2022-06
Construction start
Operation start
Estimated start 2025-12
Construction time
Capacity in MWh
160
πŸ“ This is an estimate
Maximum Power in MW
80
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Chiquito Grid, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.232677+-121.300049
Coordinates
41.232677, -121.300049
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
705 / 65655

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2022-06 report):

Plant Name / State
Chiquito Grid, LLC / CA
go live / power
2025-12 / 80MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
65655 / HECHQ
Entity name / entity id
Chiquito Grid, LLC / 64934
Changes:
2023-03
date: 2024-12 -> 2025-12 delayed by 12 months
2023-02
date: 2023-12 -> 2024-12 delayed by 12 months
2022-07
date: 2023-03 -> 2023-12 delayed by 9 months