Greenwater BESS πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / washington /
Dates
First heard 2025-01
Construction start
Operation start
Estimated start 2026-09
Construction time
Capacity in MWh
400
πŸ“ This is an estimate
Maximum Power in MW
200
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ GREE bn, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:48.25990411428471+-118.10135287471748
Coordinates
48.25990411428471, -118.10135287471748
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1674 / 68341

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-01 report (Project first appeared in the 2025-01 report):

Plant Name / State
Greenwater BESS / WA
go live / power
2026-09 / 200MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
68341 / GREE
Entity name / entity id
GREE bn, LLC / 66736