Hickory Park Solar Hybrid πŸ“πŸ“ŠπŸ‘€

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / georgia / Mitchell County
Dates
First heard 2020-09
Construction start 2021-08
Operation start 2022-06
Estimated start
Construction time 10 months -> 8 MWh/m
Capacity in MWh
80
Maximum Power in MW
40
Manufacturer
Wartsila Energy
Type / Number of Packs / Cells
GridSolv Quantum / /
Customer / Owner / Developer
RWE Renewables / RWE Renewables Americas LLC /
Use case
200MW solar farm support
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:31.31621+-84.124752
Coordinates
31.31621, -84.124752
πŸ“ Coords not known
Notes
2021: 30 year PPA with Georgia Power
Project website
Sources
https://www.energy-storage.news/lg-energy-solution-supplying-800mwh-battery-storage-for-rwes-us-solar-plus-storage-projects/
https://www.rwe.com/en/press/rwe-renewables/2020-11-17-rwes-hickory-park-solar-project-with-co-located-storage-facility-under-construction
Internal / External id
43 / 63522

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2023-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Hickory Park Solar Hybrid / GA
go live / power
2022-06 / 40MW
status / status verbose
operation / operation
Plant id / generator id
63522 / HPBAT
Entity name / entity id
RWE Renewables Americas LLC / 56215
Changes:
2022-08
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2022-07
date: 2022-05 -> 2022-06 delayed by 1 month
2022-06
date: 2022-04 -> 2022-05 delayed by 1 month
2022-04
date: 2022-03 -> 2022-04 delayed by 1 month
2022-03
date: 2022-02 -> 2022-03 delayed by 1 month
2022-01
date: 2021-12 -> 2022-02 delayed by 2 months
2021-12
date: 2021-11 -> 2021-12 delayed by 1 month
2021-08
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (V) Under construction, more than 50 percent complete