TX23 Roughneck Storage πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2022-07 |
Construction start |
|
Operation start |
2022-12 |
Estimated start |
2022-07 |
Construction time |
|
Capacity in MWh
100
π This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Key Capture Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.503427961192564+-95.20548057247251
Coordinates
33.503427961192564, -95.20548057247251
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
722 / 65701
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2023-02
report (Project first appeared in the
2022-07
report):
Plant Name / State
TX23 Roughneck Storage / TX
go live / power
2022-12 / 50MW
status / status verbose
operation / operation
Plant id / generator id
65701 / TX23
Entity name / entity id
Key Capture Energy / 63289
Changes:
2023-02
status: construction -> operation πΎ π πΈ
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2023-01
date: 2022-11 -> 2022-12 delayed by
1 month
2022-12
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2022-11
date: 2022-09 -> 2022-11 delayed by
2 months
2022-10
date: 2022-08 -> 2022-09 delayed by
1 month
2022-09
date: 2022-07 -> 2022-08 delayed by
1 month