Purple Sage Energy Center πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / nevada /
Dates
First heard 2024-12
Construction start
Operation start
Estimated start 2026-12
Construction time
Capacity in MWh
800
πŸ“ This is an estimate
Maximum Power in MW
400
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Noble Solar LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.587276413201245+-114.77095597468609
Coordinates
41.587276413201245, -114.77095597468609
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1561 / 68209

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-01 report (Project first appeared in the 2024-12 report):

Plant Name / State
Purple Sage Energy Center / NV
go live / power
2026-12 / 400MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
68209 / PSGBS
Entity name / entity id
Noble Solar LLC / 66650
Changes: