Aramis I Solar Project πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2024-07
Construction start
Operation start
Estimated start 2026-09
Construction time
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ IP Aramis, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.24258519146767+-121.13500953314751
Coordinates
41.24258519146767, -121.13500953314751
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1482 / 66678

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2024-07 report):

Plant Name / State
Aramis I Solar Project / CA
go live / power
2026-09 / 100MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
66678 / IPARB
Entity name / entity id
IP Aramis, LLC / 65682