Resurgence Solar II πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2023-06
Construction start 2023-07
Operation start 2023-08
Estimated start
Construction time 1 months -> 80 MWh/m
Capacity in MWh
80
πŸ“ This is an estimate
Maximum Power in MW
40
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Resurgence Solar II /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.00747109055068+-121.14148166910252
Coordinates
41.00747109055068, -121.14148166910252
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1018 / 66620

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2023-06 report):

Plant Name / State
Resurgence Solar II / CA
go live / power
2023-08 / 40MW
status / status verbose
operation / operation
Plant id / generator id
66620 / GEN2
Entity name / entity id
Resurgence Solar II / 65647
Changes:
2023-10
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-09
date: 2023-07 -> 2023-08 delayed by 1 month
2023-07
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete