Sunday Solar πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / virginia /
Dates
First heard 2025-02
Construction start
Operation start
Estimated start 2028-05
Construction time
Capacity in MWh
280
πŸ“ This is an estimate
Maximum Power in MW
140
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Alpin Holding LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:37.97762014887133+-77.74941873708002
Coordinates
37.97762014887133, -77.74941873708002
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1736 / 68309

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-04 report (Project first appeared in the 2025-02 report):

Plant Name / State
Sunday Solar / VA
go live / power
2028-05 / 140MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
68309 / SUNB
Entity name / entity id
Alpin Holding LLC / 66697
Changes: