Cool Springs Solar (Hybrid) πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / georgia /
Dates
First heard 2020-09
Construction start 2021-01
Operation start 2021-12
Estimated start 2021-11
Construction time 11 months -> 7 MWh/m
Capacity in MWh
80
πŸ“ This is an estimate
Maximum Power in MW
40
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Cool Springs Solar, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:32.265775364886245+-82.18751619022643
Coordinates
32.265775364886245, -82.18751619022643
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
209 / 63721

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2022-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Cool Springs Solar (Hybrid) / GA
go live / power
2021-12 / 40MW
status / status verbose
operation / operation
Plant id / generator id
63721 / CSBAT
Entity name / entity id
Cool Springs Solar, LLC / 63414
Changes:
2022-02
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2022-01
date: 2021-11 -> 2021-12 delayed by 1 month
2021-10
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2021-05
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2021-01
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete