Anode (Springville) BESS πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2022-04 |
Construction start |
2022-05 |
Operation start |
2022-04-08 |
Estimated start |
2024-10 |
Construction time |
-1 months -> -448 MWh/m
|
Capacity in MWh
448
π This is an estimate
Maximum Power in MW
224
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Southern California Edison Co /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.01822925590127+-120.97859189749224
Coordinates
41.01822925590127, -120.97859189749224
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
679 / 65458
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
This project has 2
generator ids under the same plant id
Info from the
2024-07
report (Project first appeared in the
2022-04
report):
Plant Name / State
Anode (Springville) BESS / CA
go live / power
2024-10 / 112MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
65458 / ANOD1
Entity name / entity id
Southern California Edison Co / 17609
Changes:
2024-07
date: 2024-07 -> 2024-10 delayed by
3 months
2024-05
date: 2024-06 -> 2024-07 delayed by
1 month
2023-10
date: 2023-11 -> 2024-06 delayed by
7 months
2023-05
date: 2023-05 -> 2023-11 delayed by
6 months
2023-02
date: 2023-04 -> 2023-05 delayed by
1 month
2022-11
date: 2022-11 -> 2023-04 delayed by
5 months
2022-10
date: 2022-09 -> 2022-11 delayed by
2 months
2022-09
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-08
date: 2022-08 -> 2022-09 delayed by
1 month
2022-05
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
Info from the
2024-07
report (Project first appeared in the
2022-04
report):
Plant Name / State
Anode (Springville) BESS / CA
go live / power
2024-10 / 112MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
65458 / ANOD2
Entity name / entity id
Southern California Edison Co / 17609
Changes:
2024-07
date: 2024-07 -> 2024-10 delayed by
3 months
2024-05
date: 2024-06 -> 2024-07 delayed by
1 month
2023-10
date: 2023-11 -> 2024-06 delayed by
7 months
2023-05
date: 2023-05 -> 2023-11 delayed by
6 months
2023-02
date: 2023-04 -> 2023-05 delayed by
1 month
2022-11
date: 2022-11 -> 2023-04 delayed by
5 months
2022-10
date: 2022-09 -> 2022-11 delayed by
2 months
2022-09
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-08
date: 2022-08 -> 2022-09 delayed by
1 month
2022-05
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete