Wood County πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / wisconsin /
Dates
First heard |
2025-02 |
Construction start |
2025-03 |
Operation start |
|
Estimated start |
2025-10 |
Construction time |
|
Capacity in MWh
150
π This is an estimate
Maximum Power in MW
75
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Wisconsin Power & Light Co /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:45.217776+-88.126482
Coordinates
45.217776, -88.126482
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1740 / 65011
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2025-04
report (Project first appeared in the
2025-02
report):
Plant Name / State
Wood County / WI
go live / power
2025-10 / 75MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
65011 / BESS1
Entity name / entity id
Wisconsin Power & Light Co / 20856
Changes:
2025-03
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
date: 2025-03 -> 2025-10 delayed by
7 months