Hummingbird Energy Storage LLC πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2022-03
Construction start 2023-03
Operation start
Estimated start 2024-11
Construction time
Capacity in MWh
150
πŸ“ This is an estimate
Maximum Power in MW
75
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Hummingbird Energy Storage, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.122677+-121.260049
Coordinates
41.122677, -121.260049
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
620 / 65395

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2022-03 report):

Plant Name / State
Hummingbird Energy Storage LLC / CA
go live / power
2024-11 / 75MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
65395 / HUMB1
Entity name / entity id
Hummingbird Energy Storage, LLC / 64738
Changes:
2024-07
date: 2024-06 -> 2024-11 delayed by 5 months
2024-03
date: 2024-12 -> 2024-06 accelerated by 6 months
2024-02
date: 2023-12 -> 2024-12 delayed by 12 months
2023-03
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2023-02
status_verbose: (T) Regulatory approvals received. Not under construction -> (L) Regulatory approvals pending. Not under construction
2022-10
date: 2023-06 -> 2023-12 delayed by 6 months