Peony Solar 1 πππ
Status
cancelled
Country / State / Closest City
πΊπΈ usa / indiana /
Dates
First heard |
2023-01 |
Construction start |
|
Operation start |
|
Estimated start |
2024-05 |
Month disappeared |
2023-07 |
Construction time |
|
Capacity in MWh
124
π This is an estimate
Maximum Power in MW
62
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Lightsource Renewable Energy Asset Management, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.38901541320124+-85.19728797468608
Coordinates
41.38901541320124, -85.19728797468608
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
861 / 66131
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2023-06
report (Project first appeared in the
2023-01
report):
Plant Name / State
Peony Solar 1 / IN
go live / power
2024-05 / 62MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
66131 / INPE2
Entity name / entity id
Lightsource Renewable Energy Asset Management, LLC / 62842
Changes:
2023-07
This project disappeared in the
2023-07
report.
That's why the status was set to
cancelled