North Central Valley πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2023-02 |
Construction start |
2023-05 |
Operation start |
2023-08 |
Estimated start |
2023-08 |
Construction time |
3 months -> 88 MWh/m
|
Capacity in MWh
264
π This is an estimate
Maximum Power in MW
132
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ North Central Valley Energy Storage, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.02074085870876+-121.37410994178886
Coordinates
41.02074085870876, -121.37410994178886
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
933 / 66208
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2023-02
report):
Plant Name / State
North Central Valley / CA
go live / power
2023-08 / 132MW
status / status verbose
operation / operation
Plant id / generator id
66208 / NCV
Entity name / entity id
North Central Valley Energy Storage, LLC / 65339
Changes:
2023-10
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-05
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete