Estrella Solar & Storage πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2023-08 |
Construction start |
2023-10 |
Operation start |
2023-12 |
Estimated start |
2023-12 |
Construction time |
2 months -> 28 MWh/m
|
Capacity in MWh
56
π This is an estimate
Maximum Power in MW
28
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ AES Clean Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.04295061545127+-121.05467641879585
Coordinates
41.04295061545127, -121.05467641879585
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1039 / 66772
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2023-08
report):
Plant Name / State
Estrella Solar & Storage / CA
go live / power
2023-12 / 28MW
status / status verbose
operation / operation
Plant id / generator id
66772 / ESTRB
Entity name / entity id
AES Clean Energy / 64904
Changes:
2024-02
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-10
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete