Midpoint Solar, LLC πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2023-09 |
Construction start |
2025-01 |
Operation start |
|
Estimated start |
2025-12 |
Construction time |
|
Capacity in MWh
100
π This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Sunraycer Assets I LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.550450781375964+-95.1407592129225
Coordinates
33.550450781375964, -95.1407592129225
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1062 / 66897
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2025-01
report (Project first appeared in the
2023-09
report):
Plant Name / State
Midpoint Solar, LLC / TX
go live / power
2025-12 / 50MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
66897 / MIDBA
Entity name / entity id
Sunraycer Assets I LLC / 65815
Changes:
2025-01
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
date: 2025-05 -> 2025-12 delayed by
7 months
mw: 52 -> 50
2024-10
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (T) Regulatory approvals received. Not under construction
date: 2025-08 -> 2025-05 accelerated by
3 months