SR McNeal πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / arizona /
Dates
First heard 2023-09
Construction start 2023-11
Operation start 2023-12
Estimated start 2023-12
Construction time 1 months -> 40 MWh/m
Capacity in MWh
40
πŸ“ This is an estimate
Maximum Power in MW
20
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ SR McNeal, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.308429+-109.885254
Coordinates
36.308429, -109.885254
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1035 / 66925

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2023-09 report):

Plant Name / State
SR McNeal / AZ
go live / power
2023-12 / 20MW
status / status verbose
operation / operation
Plant id / generator id
66925 / MCBA
Entity name / entity id
SR McNeal, LLC / 65303
Changes:
2024-02
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2024-01
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2023-11
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete