Borden County BESS πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2023-08
Construction start 2024-01
Operation start 2024-08
Estimated start 2024-05
Construction time 7 months -> 42 MWh/m
Capacity in MWh
300
πŸ“ This is an estimate
Maximum Power in MW
150
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Borden County Battery Energy Storage System LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.27525537493651+-95.3315331949425
Coordinates
33.27525537493651, -95.3315331949425
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1054 / 66804

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-01 report (Project first appeared in the 2023-08 report):

Plant Name / State
Borden County BESS / TX
go live / power
2024-08 / 150MW
status / status verbose
operation / operation
Plant id / generator id
66804 / 1
Entity name / entity id
Borden County Battery Energy Storage System LLC / 65765
Changes:
2024-10
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2024-09
date: 2024-07 -> 2024-08 delayed by 1 month
2024-08
date: 2024-06 -> 2024-07 delayed by 1 month
2024-07
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2024-01
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
date: 2024-05 -> 2024-06 delayed by 1 month