Desert Peak Energy Storage II πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2022-11 |
Construction start |
2023-03 |
Operation start |
2023-07 |
Estimated start |
2023-06 |
Construction time |
4 months -> 37 MWh/m
|
Capacity in MWh
150
π This is an estimate
Maximum Power in MW
75
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Desert Peak Energy Storage II, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.902031888219526+-121.22835705730502
Coordinates
40.902031888219526, -121.22835705730502
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
856 / 65988
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2022-11
report):
Plant Name / State
Desert Peak Energy Storage II / CA
go live / power
2023-07 / 75MW
status / status verbose
operation / operation
Plant id / generator id
65988 / DP2
Entity name / entity id
Desert Peak Energy Storage II, LLC / 65169
Changes:
2023-09
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-05
date: 2023-06 -> 2023-07 delayed by
1 month
2023-03
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete