Camino Solar πππ
Status
cancelled
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2020-09 |
Construction start |
|
Operation start |
|
Estimated start |
2024-12 |
Month disappeared |
2023-04 |
Construction time |
|
Capacity in MWh
44
π This is an estimate
Maximum Power in MW
22
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Avangrid Renewables LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.867793853632904+-121.38286555449248
Coordinates
40.867793853632904, -121.38286555449248
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
194 / 63508
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
This project has 2
generator ids under the same plant id
Info from the
2021-01
report (Project first appeared in the
2020-09
report):
Plant Name / State
Camino Solar / CA
go live / power
2022-05 / 11MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
63508 / CS2
Entity name / entity id
Avangrid Renewables LLC / 15399
Changes:
Info from the
2023-03
report (Project first appeared in the
2021-02
report):
Plant Name / State
Camino Solar Hybrid / CA
go live / power
2024-12 / 11MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
63508 / CSBA1
Entity name / entity id
Avangrid Renewables LLC / 15399
Changes:
2023-02
date: 2023-12 -> 2024-12 delayed by
12 months
2022-05
date: 2023-03 -> 2023-12 delayed by
9 months
2021-07
date: 2022-05 -> 2023-03 delayed by
10 months
2023-04
This project disappeared in the
2023-04
report.
That's why the status was set to
cancelled