Camino Solar πŸ“πŸ“ŠπŸ“

Status
cancelled
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2020-09
Construction start
Operation start
Estimated start 2024-12
Month disappeared 2023-04
Construction time
Capacity in MWh
44
πŸ“ This is an estimate
Maximum Power in MW
22
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Avangrid Renewables LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.867793853632904+-121.38286555449248
Coordinates
40.867793853632904, -121.38286555449248
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
194 / 63508

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
This project has 2 generator ids under the same plant id
Info from the 2021-01 report (Project first appeared in the 2020-09 report):

Plant Name / State
Camino Solar / CA
go live / power
2022-05 / 11MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
63508 / CS2
Entity name / entity id
Avangrid Renewables LLC / 15399
Changes:


Info from the 2023-03 report (Project first appeared in the 2021-02 report):

Plant Name / State
Camino Solar Hybrid / CA
go live / power
2024-12 / 11MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
63508 / CSBA1
Entity name / entity id
Avangrid Renewables LLC / 15399
Changes:
2023-02
date: 2023-12 -> 2024-12 delayed by 12 months
2022-05
date: 2023-03 -> 2023-12 delayed by 9 months
2021-07
date: 2022-05 -> 2023-03 delayed by 10 months



2023-04 This project disappeared in the 2023-04 report.
That's why the status was set to cancelled