San Juan Solar I πŸ“πŸ“ŠπŸ‘€

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / new mexico /
Dates
First heard 2023-05
Construction start 2023-10
Operation start
Estimated start 2024-05
Construction time
Capacity in MWh
400
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
PNM / San Juan Solar I, LLC /
Use case
200MW solar farm support
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.804042+-108.445356
Coordinates
36.804042, -108.445356
πŸ“ Coords not known
Notes

Project website
Sources
https://reneweconomy.com.au/new-mexico-utility-to-replace-coal-plant-with-four-solar-and-battery-projects-31989/
Internal / External id
103 / 66574

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2023-05 report):

Plant Name / State
San Juan Solar I / NM
go live / power
2024-05 / 100MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
66574 / SJSS
Entity name / entity id
San Juan Solar I, LLC / 65626
Changes:
2024-01
date: 2024-07 -> 2024-05 accelerated by 2 months
2023-11
date: 2024-08 -> 2024-07 accelerated by 1 month
2023-10
status: planning -> construction πŸ—οΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete