Middlebrook Creek Solar and BESS πŸ“ŠπŸ‘€πŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2022-09
Construction start
Operation start
Estimated start 2026-02
Construction time
Capacity in MWh
604
πŸ“ This is an estimate
Maximum Power in MW
302
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Solar Proponent LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:31.598849+-94.598401
Coordinates
31.598849, -94.598401
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
https://www.solarproponent.com/projects/#
Internal / External id
790 / 65853

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2022-09 report):

Plant Name / State
Middlebrook Creek Solar and BESS / TX
go live / power
2026-02 / 302MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
65853 / MIDBS
Entity name / entity id
Solar Proponent LLC / 65079
Changes:
2023-12
date: 2024-10 -> 2026-02 delayed by 16 months