NISA Electric Generation Project πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / new york /
Dates
First heard 2021-03
Construction start
Operation start
Estimated start 2026-03
Construction time
Capacity in MWh
598
πŸ“ This is an estimate
Maximum Power in MW
299
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ NYC Energy LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:42.55007085870876+-75.57760094178886
Coordinates
42.55007085870876, -75.57760094178886
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
233 / 61331

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
This project has 2 generator ids under the same plant id
Info from the 2024-07 report (Project first appeared in the 2021-03 report):

Plant Name / State
NISA Electric Generation Project / NY
go live / power
2026-03 / 79MW
status / status verbose
planning / (T) Regulatory approvals received. Not under construction
Plant id / generator id
61331 / BA1
Entity name / entity id
NYC Energy LLC / 60971
Changes:
2023-05
entity name: NYC ENERGY LLC -> NYC Energy LLC
date: 2024-03 -> 2026-03 delayed by 24 months
2022-03
date: 2023-11 -> 2024-03 delayed by 4 months
mw: 300 -> 79


Info from the 2024-07 report (Project first appeared in the 2022-03 report):

Plant Name / State
NISA Electric Generation Project / NY
go live / power
2026-03 / 220MW
status / status verbose
planning / (T) Regulatory approvals received. Not under construction
Plant id / generator id
61331 / BA2
Entity name / entity id
NYC Energy LLC / 60971
Changes:
2023-05
entity name: NYC ENERGY LLC -> NYC Energy LLC
date: 2025-07 -> 2026-03 delayed by 8 months