Bexar ESS πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2023-04
Construction start
Operation start
Estimated start 2025-03
Construction time
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ OCI Solar Power /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.244802450183876+-94.98542795000252
Coordinates
33.244802450183876, -94.98542795000252
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
998 / 66400

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2023-04 report):

Plant Name / State
Bexar ESS / TX
go live / power
2025-03 / 100MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
66400 / OCBEX
Entity name / entity id
OCI Solar Power / 58489
Changes:
2023-09
date: 2024-08 -> 2025-03 delayed by 7 months